Will County completes major projects while others move forward

Spread the love

Will County’s facilities team has completed several major projects while advancing others throughout the county, officials reported during a Capital Improvements & IT Committee meeting Monday.

The Old Courthouse Plaza concrete replacement project at 14 W. Jefferson has been finished, with new picnic benches installed and the area fully restored with handicap-accessible ramps meeting current ADA standards, according to Facilities Director Bill Fern.

“The plaza is completely usable again, safe level, all new concrete, all handicap ramps all been replaced,” Fern told committee members during his monthly facilities update.

The county has also completed parking lot resurfacing at both the Community Health Center and River Valley Juvenile Detention Center. The River Valley project addressed serious deterioration issues and brought handicap ramps up to current ADA compliance standards after the original construction was determined to be too steep by today’s requirements.

“That parking lot was in serious need of resurfacing,” Fern said. “The handicap ramps, the ADA accessible areas when they built it were too steep to today’s standards, so now they are all compliant.”

Work continues on several other major projects across county properties. The Court Annex/State’s Attorney Level 2 renovations at 57 N. Ottawa are scheduled to begin construction July 10 following bid openings set for June 4. The project, which involves combining unused courtrooms on the second and third floors to create more usable space, is expected to be completed by fall 2025.

Similarly, Land Use/Public Defender renovations at 58 E. Clinton are progressing with Level 3 complete and Level 4 work beginning June 16. That project is also slated for completion in August.

The Veterans Assistance Commission buildout at 1300 Copperfield has reached several milestones, with roof replacement 95% complete and both glass replacement and interior renovations set to begin June 9. The project involves UV-coated, double-pane glass replacement and is expected to wrap up in fall 2025.

Committee Chair Mica Freeman noted the county is expecting facility assessment reports by month’s end that will merge facility condition evaluations with space needs analysis. The comprehensive assessment covers 75% of county-owned properties, with the largest facilities – Adult Detention Facility and River Valley – nearing completion of their evaluations.

Fern reported his team handled over 760 work orders in May, completing them with 98% on-time performance at an average cost of $19.75 per work order. The facilities team logged more than 800 hours of labor during the month.

“The team is really moving,” Fern said, highlighting the department’s productivity while maintaining zero workplace injuries – a safety record Committee member Herbert Brooks Jr. praised as worthy of celebration.

The committee also addressed ongoing courthouse issues, with scaffolding removal underway as stone replacement work continues. Water infiltration behind limestone panels caused damage when freezing temperatures expanded the moisture, pushing stones outward. Sixteen new quarried limestone pieces are being manufactured for replacement, with installation planned using swing stages rather than scaffolding.

A facilities report from material specialists examining the courthouse damage is expected by the end of next week, providing definitive analysis of the stone failure and remediation efforts.

The next committee meeting is scheduled for July 1.

Latest News Stories

Camp Mystic suspends summer operation 2 days after Texas lawmakers' demands

Camp Mystic suspends summer operation 2 days after Texas lawmakers’ demands

By Bethany BlankleyThe Center Square Camp Mystic owners have agreed to suspend camp operations this summer after being called to do so by state lawmakers and parents whose daughters were...
Six Democrats seeking 13th Congressional District post

Six Democrats seeking 13th Congressional District post

By Andrew RiceThe Center Square Six candidates are competing for the Democratic nomination in Georgia's 13th Congressional District. Incumbent David Scott died on April 22. Scott served in Congress for...
DHS shutdown ends after 76 days

DHS shutdown ends after 76 days

By Thérèse BoudreauxThe Center Square After weeks of delay, the U.S. House on Thursday approved the Senate’s legislation reopening the Department of Homeland Security. President Donald Trump signed the legislation...
Farm bill passes U.S. House, heads to Senate for approval

Farm bill passes U.S. House, heads to Senate for approval

By Thérèse BoudreauxThe Center Square The Farm, Food, and National Security Act of 2026 passed the U.S. House Thursday in a 224-200 vote, a hopeful sign for America’s agricultural industry...
Alleged WHCD shooter to remain in federal custody until trial

Alleged WHCD shooter to remain in federal custody until trial

By Andrew RiceThe Center Square The accused shooter at the White House Correspondents’ Association Dinner on Saturday will remain in federal custody while awaiting a trial, a judge said on...
DeSantis: Ruling vindicates Florida redrawing congressional maps

DeSantis: Ruling vindicates Florida redrawing congressional maps

By David BeasleyThe Center Square A U.S. Supreme Court ruling Wednesday “compelled” Florida to redraw congressional districts, second-term Republican Gov. Ron DeSantis said Thursday a day after the Legislature approved...
Congress advances bills targeting $186 billion payment problem

Congress advances bills targeting $186 billion payment problem

By Brett RowlandThe Center Square Congress moved this week on both sides of the Capitol to address a problem that has persisted for decades after a new report found federal...
Beasley Allen booted from looming talc trial in Chicago

Beasley Allen booted from looming talc trial in Chicago

By John O’Brien | Legal NewslineThe Center Square Judges in Miami and Chicago have revoked permission that allowed the firm Beasley Allen to pursue talc lawsuits because it collaborated with...
Ten candidates vying for Georgia's 11th District post

Ten candidates vying for Georgia’s 11th District post

By Andrew RiceThe Center Square Ten candidates are running to fill the seat vacated by Georgia U.S. Congressman Barry Loudermilk, who announced he was not running for reelection. Republicans John...
New Jersey sued over ICE mask ban

New Jersey sued over ICE mask ban

By Chris WadeThe Center Square The Trump administration is taking New Jersey Gov. Mikkie Sherrill to federal court over newly signed legislation banning ICE agents from wearing masks during immigration...
Illinois Quick Hits: Gas prices rise again

Illinois Quick Hits: Gas prices rise again

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – AAA says the average price for regular unleaded gasoline in Illinois has jumped 14 cents in one...
Massive drug busts in California, Texas, enough to kill more than 32.7 million people

Massive drug busts in California, Texas, enough to kill more than 32.7 million people

By Bethany BlankleyThe Center Square Massive drug busts are continuing along the southwest border primarily in California and Texas. In roughly a dozen stops this month federal agents seized enough...
Union Pacific, Norfolk Southern submit new merger application

Union Pacific, Norfolk Southern submit new merger application

By Dan McCaleb and Tom JoyceThe Center Square Union Pacific and Norfolk Southern on Thursday submitted a new merger application to the U.S. Surface Transportation Board that would create the...
Mills drops out of Maine U.S. Senate race

Mills drops out of Maine U.S. Senate race

By Andrew RiceThe Center Square Maine Gov. Janet Mills announced she would suspend her campaign in the race for U.S. Senate on Thursday. Mills was one of the top contenders...
beecher ilinois school board graphic.5

Beecher Board Tables $16,000 Junior High Digital Sign; Approves Sealcoating and New Elementary Desks

Beecher Board of Education Meeting | April 15, 2026 Article Summary: The Beecher Board of Education approved over $17,000 in facility and equipment upgrades but delayed the purchase of a new...