Solar Project Extensions Approved as Industry Faces Permitting Delays
Three solar energy projects received 180-day extensions from Will County’s Land Use & Development Committee Thursday as developers continue working through lengthy permitting processes with utility companies and other agencies.
The extensions cover projects in Peotone, Channahon, and Crete townships that received special use permits in 2023 but haven’t yet obtained building permits. Under county rules, special use permits expire within two years unless construction permits are issued.
A Peotone Township solar project by Turning Point Energy received its extension after experiencing delays with updated conservation plans and changing fire district requirements. Joseph Chessup, representing the developer, said soil and water conservation standards were updated last year, requiring them to restart their conservation planning process.
The Manhattan Fire Protection District also changed safety standards as recently as May 20, requiring wider access roads and higher weight capacity to accommodate 80,000-pound fire equipment.
“There’s been a few unexpected delays with getting the permits finalized for this project,” Chessup said.
Staff also provided an update on solar interconnection requirements after meeting with ComEd officials. The utility company clarified that they don’t require above-ground power connections for solar projects, contrary to claims made by some developers.
ComEd uses a five-step process taking about 180 days for interconnection agreements. While they typically install four riser poles for connections, they can accommodate underground lines for 12KV systems, though 34KV lines remain economically impractical to bury.
The committee expressed interest in requiring more underground infrastructure for future solar projects to preserve rural aesthetics. “I would like to see us have them put it underground as much as they possibly can,” said Committee member Judy Ogala.
Latest News Stories
Meeting Summary and Briefs: Will County Land Use & Development Committee for February 5, 2026
Beecher Village Board Splits on Capital Spending: Park Stage Renovation Rejected, Police Sign Approved
Meeting Summary and Briefs: Will County Executive Committee for February 11, 2026
Group Presents Allegations of 2024 Voter Roll Errors to County Board
Library Moves Forward with Entrance Project, Faces Heating System Failure
Will County Board Advised on Strict “Judicial” Role Ahead of Landfill Expansion Application
Land Use Committee Rejects Shorewood Solar Farm Despite 25-Year Lease Offer
Executive Committee Advances $28.7 Million BNSF Bridge Project for Lorenzo Road
Land Use Committee: ‘Clean Fill’ Proposal Stalls After Unauthorized Tree Removal Sparks Environmental Concerns
Meeting Summary and Briefs: Will County Planning and Zoning Commission for February 17, 2026