County RNG Facility Shows Strong Performance Despite Solar Challenges
Will County’s Renewable Natural Gas facility is exceeding production targets while officials explore options to reduce substantial electricity costs that currently impact profitability.
Project manager Greg Komperda told Finance Committee members July 1 that the facility has operated at 94-95% capacity for three consecutive months, representing full operational capacity. Production has consistently exceeded both targets and minimum contractual obligations.
“We met our production targets in April, May, and June,” Komperda reported. The facility generated $5.26 million in revenue through June 20 against $3.89 million in expenses, though debt service payments result in approximately $1.2 million negative cash flow.
County Board member Julie Berkowicz questioned whether solar power could help offset electricity costs, noting the facility’s consumption of 3,500 kilowatts per hour. Dave Hartke, director of Land Use, explained that meeting those power needs would require 40-50 acres of solar panels.
“You’re probably looking at a solar farm around maybe 40 50 acres maybe around there to supply the electricity for the plant,” Hartke said. “At this point there’s no room around unless we’ve had to create a solar farm adjacent property.”
Any solar development faces complications from uncertainty about potential landfill expansion. Officials indicated they prefer to wait until expansion decisions are made before committing to permanent solar installations.
Daniel Butler noted that a complete solar installation could cost hundreds of millions of dollars, questioning the return on investment. Officials acknowledged that even partial solar power could help reduce costs but emphasized the need for careful analysis of long-term planning.
The facility successfully hosted tours in June and has improved spare parts inventory planning to reduce downtime risks. Despite minor operational challenges including utility outages and equipment repairs, the facility has maintained strong performance metrics above the 92% target runtime.
Latest News Stories
Traffic Alert: Wolf Road water repairs rescheduled for Tuesday
Ex-Illinois candidate sides with Vance after Duckworth–Rubio clash
Illinois Quick Hits: Judge rules Cook County misspent $243M
Will County P&Z Forwards Monee and Manhattan Residential Projects
Meeting Summary and Briefs: Village of Beecher for January 26, 2026
Will County P&Z: Wilton Township Wedding Venue Secured for 2026 Season
Beecher Library Board Approves Personnel Changes Following Executive Session
Chicago FOP boss: Mayor’s ICE on Notice order is ‘piece of toilet paper’
Lawmaker, officer: ‘Blue Envelope” could help navigate autism during stops
Will County P&Z Grants Variances for Unpermitted Structures in Crete and Manhattan
Village Authorizes Collective Bidding for Electricity Rates
Meeting Summary and Briefs: Will County Landfill Committee for Jan. 13, 2026