Will County’s Major Capital Projects Hit Key Milestones, VAC Buildout on “Aggressive Schedule”
Will County is making significant headway on several major capital improvement projects, with the new Veterans Assistance Commission (VAC) & Support Center in Joliet on an “aggressive schedule” for a November completion, Facilities Director Bill Fern reported Tuesday.
During an update to the Will County Board’s Capital Improvements & IT Committee, Fern detailed progress across multiple county-owned properties, highlighting the extensive work at the former Silver Cross Hospital building at 1300 Copperfield Avenue, which will house the VAC.
“This is probably the biggest news we have at this point in time,” Fern said.
The VAC buildout has seen the full replacement of the front lobby glass and the installation of an advanced security camera system that issues audible warnings to trespassers and can automatically contact the police. The building’s roof is 95% finished, and crews have begun work on the interior space.
“We’re looking at getting them in there by November,” Fern told the committee. “Very aggressive schedule.”
In response to questions from board members, Fern confirmed the building will likely have “shared occupancy” with other county entities, though a full space needs analysis is still underway to determine the final tenants.
Other key projects are also moving toward completion:
-
Land Use/Public Defender Renovations: Work at 58 E. Clinton Street is nearly finished. One floor’s renovation is complete, another is underway, and the final move-in and consolidation is expected by the end of August 2025.
-
Court Annex/State’s Attorney Renovations: Following a bid opening on June 4, construction on interior modifications at 57 N. Ottawa Street is set to begin on July 17, with an anticipated completion in the fall of 2025.
-
Will County Courthouse: The long-awaited replacement of exterior stone panels is expected within the next 30 days as the natural product is currently being manufactured. Fern noted that the large scaffolding currently in place for protection will be removed, and a swing stage will be used for the installation.
The committee also learned that the parking lot at the River Valley Justice Center has been fully restored, with new surfacing, striping, and signage installed by the county’s Division of Transportation, a move that saved “a considerable amount of money.”
Latest News Stories
Trump says Iran agrees to no nuclear weapon, claims deal is close
Late-Inning Surge and Dominant Relief Lift Beecher Past Bloom 12-5
Democrats call on Lutnick to resign over Epstein ties
Norkus Strikes Out 16 in One-Hit Masterpiece as Beecher Downs Donovan 10-1
Carmela Irwin Throws One-Hitter as Beecher Offense Erupts in 18-1 Rout of Donovan
Texas congressional delegation calls for federal investigation into H-1B visa fraud
Foxx: Prosecutors’ ‘silence’ on murder exonerations doesn’t mean ‘innocent’
Illinois Quick Hits: ISU union workers reach deal, return to work
Trump’s Iran objective moves from ‘surrender’ to nuclear deal
Democrats demand answers from Trump on consumer costs of Iran conflict
Illinois Dems eye $7B from new tax proposals, push ‘Billionaire Wealth Tax’
Plan would have state taxpayers provide $50M for ICE-impacted businesses