The Will County Landfill Committee received a comprehensive technical update on the site investigation for the planned horizontal expansion of the county landfill, confirming the project remains on schedule. Consultants presented detailed findings from the completed geological and hydrogeological fieldwork, which will inform the final engineering and design of the new landfill area to ensure public and environmental safety.

Landfill Expansion Key Points:

  • Drilling of nine new borings and continuous soil and bedrock sampling for the expansion area is complete, with samples being sent for extensive laboratory analysis.

  • Fourteen new piezometers, or monitoring wells, have been installed to characterize groundwater conditions and will be used for an impact evaluation model.

  • Engineers are refining the expansion’s design, including adjusting the northern boundary to maximize airspace and designing a V-notched base for efficient leachate collection.

  • Despite the fieldwork phase taking slightly longer than anticipated, project consultants confirmed the overall expansion timeline has not been delayed.

The Will County Landfill Committee on Thursday received a detailed update on the extensive site investigation for the planned expansion of the county landfill, learning that the project remains on schedule as engineers begin analyzing a trove of geological data.

A consultant for the project, Mr. Fallon, walked committee members through the now-completed fieldwork phase, which involved drilling nine borings as deep as 140 feet to characterize the soil, clay, and bedrock at the proposed expansion site. He explained that the purpose of the in-depth investigation is to provide engineers with the necessary data to design a site that protects public health, safety, and welfare.

“We have logged and continuously sampled nine additional borings to supplement that information at the existing facility,” Fallon stated. “Those samples have all been delivered to the lab. And actually… we have already received back I would say about 75% of those analytical results.”

The investigation included collecting undisturbed soil samples using Shelby tubes and rock cores to conduct a battery of laboratory tests. These tests, Fallon explained, measure properties like soil density, moisture content, permeability, and shear strength. The results are critical for engineering calculations that ensure the stability of the landfill’s slopes and foundation.

In addition to soil stability, the investigation is focused on groundwater. Fourteen new piezometers—small-diameter wells—have been installed at various depths to monitor different water-bearing zones. This data will be used to create a groundwater impact evaluation model.

“We’ll take the landfill design once it’s once our engineers have developed that and then we’ll… place it into the into the geologic system,” Fallon said in response to a question from member Dawn Bullock. “And then we’ll assume that it’s leaking and we’ll evaluate… after 100 years after closure what are the what are the concentrations of this hypothetical plume at the zone of attenuation.”

Fallon noted that this modeling is a state requirement for the sighting application.

The data is already informing design tweaks. Stormwater modeling has shown that the planned retention ponds are larger than necessary, allowing engineers to push the landfill’s northern boundary slightly to “eek out a little more airspace.” They are also designing the base grades with a “V-notch design” to better channel leachate to a sump location for extraction.

County Board Speaker Joe VanDuyne asked if the water from the underlying aquifer could be utilized by the county. Fallon explained that this would be out of the question, citing both the unsuitability of the small monitoring wells for water supply and a deed restriction on the property. “We have a deed restriction we’re not allowed to use any of the water for drinking purposes,” he said.

Vice-Chair Kelly Hickey, who chaired the meeting, asked if there were any changes to the project’s timeline.

“We haven’t had a delay in the project yet,” Fallon responded. “The field investigation did take a little longer than we than we had thought it would… but within the larger framework of the project, I feel like we’re still on schedule.”

Events

No events

Latest News Stories

Beecher Graphic.4

Beecher Nuisance Property Owner Makes ‘Substantial Effort’ to Clean Up

Article Summary: The owner of a long-problematic property on Catalpa Street has cleaned up the yard and ordered a dumpster, showing significant progress after years of complaints and recent threats...

Meeting Summary and Briefs: Village of Beecher Board of Trustees for July 14, 2025

The Beecher Village Board passed a major overhaul of its governmental structure at its meeting on July 14, approving ordinances that dissolve the Planning and Zoning and Beautification Commissions and...
WCO Exec Cmte July 10.1

County Approves School Resource Officer, Multi-Year Planning Requirements

Will County approved hiring an additional sheriff's deputy for a school resource officer position that will be fully funded by Summit Hill School District 161, while also passing new transparency...
WCO Exec Cmte July 10.2

County Addresses Senior Tax Exemption Processing Error

A processing error that cost County Board member Julie Berkowicz $600 in senior tax exemptions has prompted discussions about improving verification systems for property tax breaks. Will County Chief Assessment...
Meeting Briefs

Executive Committee Meeting July 10 Meeting Briefs

Liquor License Expansion: The county approved increasing Class C1 liquor licenses from eight to nine to accommodate Lockport Gas and Food LLC at 14747 W. 159th Street in Homer Glen....
Screenshot 2025-08-22 at 8.12.43 PM

Beecher School Board Begins Overhaul of District Goals, Focusing on Transparency, Inclusivity, and Student Success

Article Summary: The Beecher Board of Education has initiated a comprehensive update of its district-wide goals, beginning a process to replace a strategic plan that has been in place since...
beecher ilinois school board graphic.12

Beecher School Board Finalizes Policy Updates, Approves New Student Handbook

Article Summary: The Beecher Board of Education gave its final approval to a series of policy updates and a revised Student Handbook for the 2025-2026 school year. The unanimous votes...
beecher ilinois school board graphic.5

District Modifies Janitorial Contract, Saving Money by Bringing Junior High In-House

Article Summary: The Beecher Board of Education approved a new janitorial contract with Citywide Janitorial for the 2025-2026 fiscal year that covers only the elementary school, a change that will...
Meeting Briefs

Meeting Summary and Briefs: Beecher Board of Education for July 9, 2025

The Beecher Board of Education began the process of creating a new five-year strategic plan by holding an in-depth discussion to overhaul its district goals at its July 9 meeting....
washington township graphic.1

Washington Township to Reduce Office Hours in Summer Trial

Article Summary: The Washington Township Board of Trustees has approved a plan to reduce public office hours for a trial period this summer, citing less foot traffic and potential cost...
washington township graphic.2

Washington Township Opts for $1,050 AC Repair Over $10,200 Replacement

Article Summary: The Washington Township Board of Trustees chose to repair two non-functional, 25-year-old air conditioning units for $1,050 rather than pursue a full replacement of all three units at...
washington township graphic.3

Property Assessments Set to Rise Across Washington Township

Article Summary: Washington Township Assessor Pat Peters has advised residents that property assessments are expected to rise for nearly every property in the township. The increase is due to a...
Meeting-Briefs

Meeting Summary and Briefs: Washington Township Board of Trustees for July 7, 2025

The Washington Township Board of Trustees voted to reduce its public office hours for the summer, a key decision made during its meeting on Monday, July 7. Citing a decline...
Will County Land Use July 3.1

Committee Rejects Troy Township Solar Projects Amid Strong Local Opposition

The Will County Land Use and Development Committee recommended denial for two controversial commercial solar energy projects in Troy Township on Thursday, following a wave of opposition from local municipalities,...
Will County Land Use July3.2

Controversial DuPage Township Rezoning for Outdoor Storage Advances

A contentious proposal to rezone a 20-acre parcel in DuPage Township from agricultural (A-1) to heavy industrial (I-3) for an outdoor vehicle storage facility narrowly passed the Will County Land...