Exec Cmte 8.14.25.4

Executive Committee Details Spending of $134 Million in Pandemic Relief Funds

Spread the love

Article Summary: Will County has expended 61% of its $134 million in federal American Rescue Plan Act (ARPA) funds, with significant investments made in infrastructure, health, and economic development. Officials reported that over $81.2 million has been spent, with the remaining balance to be fully allocated by the end of 2026.

ARPA Program Key Points:

  • Over $81.2 million of the $134 million total award has been spent as of June 30, 2025.

  • Infrastructure projects account for the largest allocation at $47.5 million, with 31% expended so far due to ongoing construction.

  • Funds have supported over 200 subrecipients, including municipalities, non-profits, and park and library districts.

  • All funds must be fully expended by the federal deadline of December 31, 2026.

JOLIET, IL – Will County has spent just over 61% of its $134 million federal pandemic relief allocation, with a little over a year and a half remaining before the program’s spending deadline, officials reported to the County Board Executive Committee on Thursday.

Anna Sitton of Accenture, the firm managing the county’s ARPA program, presented an annual update showing that $81.2 million had been expended as of June 30, 2025. The funds, authorized under the American Rescue Plan Act of 2021, have been distributed across more than 200 subrecipients, including local governments, non-profits, and special districts, through a framework of six pillars established by the county.

The largest portion of the funding, $47.5 million, was allocated to infrastructure. Sitton noted that the 31% expenditure rate in this category is expected to rise sharply, as many capital projects are still underway. “We’re anticipating that 60% of all infrastructure projects will be complete by the end of this year,” Sitton said, adding that an “influx of spending” would be reflected in reports for the final two quarters of 2025.

Recent completions include the Tinley Park Post 13 Lift Station project, which installed a new control system and backup generator to ensure reliable sewer service, and work by the Manhattan Fire Department to establish water and sewer infrastructure for its new safety complex.

Other pillars show higher expenditure rates. The Revenue Replacement category is 92% spent, while Economic Development and Unmet Needs are at 84% and 87%, respectively. The $6.16 million Administration pillar, which includes the cost of managing the program, is 82% spent. Sitton confirmed for board members that the allocated administration amount is the final topline number.

The Health pillar, at 57% expended, funds ongoing staffing and operations for healthcare partners, resulting in a “steady tick up of expenditures on a month-to-month basis,” Sitton explained. Highlights from this category include Silver Cross Hospital expending its full $737,500 award to help renovate its new healthcare facility in Crest Hill, which opened in June. The United Way of Will County’s MAPP Food for All Program, which supports five partners to combat food insecurity, has a remaining balance of about $173,000 from its original $779,805 allocation.

During questions, board member Judy Ogalla inquired about the “Heroes” scholarship program, which dedicated $10 million to be split between Joliet Junior College, University of St. Francis, Lewis University, and Governors State University. The funds provide scholarships of up to $5,000 per year for students pursuing degrees in healthcare and education.

“JJC has expended their funds, so they have successfully completed their program, and we’re working with the four-year institutions on expenditure through the end of 2026,” Sitton reported, offering to provide a detailed breakdown of student participation numbers to the board.

The final deadline for all ARPA funds to be expended is December 31, 2026, with a final report due to the federal government in April 2027.

Events

No events

Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Washington Township Board of Trustees for August 4, 2025

The Washington Township Board of Trustees focused on employee compensation and infrastructure needs during its August 4 meeting, approving a comprehensive overhaul of its wage structure and job descriptions. The...
washington township graphic.2

Washington Township Board Backs Special Use Permit for Barn on Corning Road

Article Summary: The Washington Township Board of Trustees will support a resident's request for a Special Use Permit to construct a barn on a 5-acre property on E. Corning Road....
Meeting Briefs

Meeting Summary and Briefs: Beecher Public Library District Board for August 19, 2025

The Beecher Public Library District Board of Trustees addressed major financial milestones and a significant leadership change at its August 19 meeting. The board unanimously approved the final budget for...
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...
diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
washington township graphic.3

Failed Repair Forces Replacement of 25-Year-Old Furnace at Washington Township Center

Article Summary: A failed repair attempt on the 25-year-old furnace at the Washington Township Center, which caused a fire alarm to activate, has prompted the board to authorize a full...
OLYMPUS DIGITAL CAMERA

Beecher Library Board Approves Budgets for Current and Upcoming Fiscal Years

Article Summary: The Beecher Public Library District Board of Trustees formally approved its final budget for the current 2024-2025 fiscal year and, following a public hearing, passed the new budget...
Meeting Briefs

Meeting Summary and Briefs: Beecher School District 200-U for September 10, 2025

The Beecher School District 200-U Board of Education approved its annual budget, appointed a new member, and greenlit a cosmetic upgrade for the high school during its meeting on September...
Meeting Briefs

Meeting Summary and Briefs: Village of Beecher Board of Trustees for September 22, 2025

The Beecher Village Board addressed persistent structural issues at the new Public Safety Facility during its meeting on September 22. After a report confirmed that new roof leaks have appeared...
washington township graphic.1

Washington Township Overhauls Wage Structure, Boosts Bus Driver Pay

Article Summary: The Washington Township Board of Trustees has initiated a comprehensive review of its wage and job structures to align with state law, improve competitiveness for key positions like...
beecher illinois public library graphic.1

Beecher Library Board President Shirley Biery Announces Resignation

Article Summary: Shirley Biery has announced she will resign from her position as President and Trustee of the Beecher Public Library District Board, effective August 31, 2025. Following the announcement...
Screenshot 2025-09-23 at 7.57.19 PM

Beecher Creates New Adjudication Clerk Position to Manage Municipal Court

Article Summary: The Village of Beecher has formally created the position of Adjudication Clerk by amending its municipal code, aiming to streamline the management of its local ordinance violation hearings....