Commission Grants Green Garden Solar Farm Project Variance Extension
Will County Planning and Zoning Commission Meeting | November 4, 2025
Article Summary: The Will County Planning and Zoning Commission granted a 180-day extension for two variances related to a commercial solar energy facility in Green Garden Township, allowing the developer to wait for optimal planting conditions in Spring 2026 before proceeding. The variances, originally approved in March, concern the mowing schedule and plant height for the native pollinator habitat required for the project.
Green Garden Solar Farm Key Points:
-
The first-time extension was granted for variances associated with a 35-acre solar project on LaGrange Road near West Manhattan-Monee Road.
-
The variances reduce the required number of mowings from five to one per year and increase the maximum allowed ground cover height from 13 to 36 inches.
-
The developer requested the extension to allow time to prepare the site for planting a native pollinator seed mix in favorable spring conditions.
A commercial solar energy facility planned for Green Garden Township received a procedural timeline extension from the Will County Planning and Zoning Commission on Tuesday, November 4, 2025.
The commission approved a 180-day extension for two variances previously granted to applicant TPE IL WI258, LLC, an affiliate of TPE Development, LLC, for a 35-acre solar farm. The project is located on vacant property at the northeast corner of LaGrange Road and West Manhattan-Monee Road in Monee.
The variances, originally approved by the commission on March 4, 2025, are key to the project’s use of native plantings and agrivoltaics—the simultaneous use of land for agriculture and solar power generation. One variance reduces the required number of mowings from five times per year to just one, while the other increases the maximum allowable plant height from 13 inches to 36 inches. These changes are necessary to establish and maintain a healthy native pollinator habitat on the site, which is a requirement of the state’s community solar program.
According to a memo from county staff, the developer has not yet applied for a building permit because “favorable planting conditions for the site are not expected until after the variances expire on March 4, 2026.” The extension was requested to allow the developer time to prepare the site for planting in the spring of 2026.
The commission, which is authorized to grant up to two 180-day extensions for good cause, approved the request. The variances will now expire on August 31, 2026.
Latest News Stories
Illinois quick hits: Midway Blitz nabs nine drunk drivers; Madigan prosecutor to depart
Here’s how to get the $20 credit offered by YouTube TV in Disney dispute
Democrats want call program for immigrant detainees
Flight troubles not likely to end when shutdown does
Trump admin signals support for Paramount bid as Warner Bros. considers sale
WATCH: Trump says Veterans Day is ‘Victory Day’
Lawmakers divided after federal complaint targets student mental health screening law
Cruz, Cornyn file bill to make federal benefit fraud a deportable offense
DHS, USCIS report record job applications under Trump administration
Virginia Beach, Chesapeake rank among best cities for veterans
Normal, IL fire and EMS challenges highlight need for statewide task force
Analysis: Chicago among worst cities to drive in