Estimated power demand will outstrip supply by 2032

Estimated power demand will outstrip supply by 2032

Spread the love

(The Center Square) – The impact on electricity demand from a growing number of data centers is a recurring point of concern among energy leaders who warn that, without swift policy reform, unchecked growth could drive up costs and threaten reliability.

A recent briefing hosted by nonprofit consumer watchdog Citizens Utility Board of Illinois, or CUB, explored the issues facing the PJM region.

Panelists from CUB and the Natural Resources Defense Council, or NRDC, suggested potential solutions that would protect consumers and acknowledged an urgent need for coordinated action, they say, to contain costs and safeguard reliability.

CUB’s Jim Chillsen noted that consumers are often unaware their electric bills include capacity charges – payments that cover the power they use, but also the cost of maintaining extra generation for times of peak demand.

He highlighted that after years of flat consumption demand, PJM estimates that by 2031 data centers could add 22-30 GW of new demand, or enough electricity for more than 10 million homes, while expecting only 6-12 GW of new supply, or enough to power as many as 2.6 million homes. This imbalance, he said, has led to record-high capacity prices for which consumers will be paying for through at least May 2027 – something the panelists fear will become a “new normal.”

Without reforms, the NRDC estimates cumulative capacity costs could reach $163 billion from 2027 through 2033.

Claire Lang-Ree, NRDC clean energy advocate, stated that average utility bills have already increased by $20-$30 due to the price increase in the grid’s last auction, and it will get worse through the coming decade if nothing is done. “We’re estimating that average bills could increase by another $70 per month,” she added.

Panelists found fault with PJM’s Critical Issue Fast Path, or CIFP – an initiative launched in August to fast-track discussions and policy decisions aimed at managing rapid growth of large load customers like data centers.

The current proposal, they say, does not require data centers to reduce energy consumption during peak demand; rather, it is voluntary, which increases the risk of rolling blackouts.

They were also critical of the proposed 10-month fast track for new data center-related resources that would allow them to jump ahead in the interconnection queue, which is dominated by clean energy projects – some that have been waiting years for approval.

A better approach stressed Clara Summers, CUB’s Consumers for a Better Grid campaign manager, would require data centers to cover their own costs and bring their own capacity.

Lang-Ree added that by removing large loads out of the capacity market until they bring their own supply may bring capacity prices back down to historic levels of around $60 billion versus the $163 billion projected.

Other measures proposed include implementation of reforms such as separate tariffs, the need for accurate load forecasting, and incentives for new, fast-to-build, clean energy supply.

Stressing that accurate load forecasting is essential to controlling costs and maintaining reliability, she warned that many projects never get built, but their projected demand is used in pricing – driving up capacity pricing for everyone.

By requiring stricter standards such as financial commitments and proof of constructability from developers, consumers won’t be forced to pay for power that is never used, she said.

Summers also highlighted that battery storage is the fastest source to build. Citing analysis by Brattle, she said battery storage can be built in about 20 months or less, as opposed to a gas fired power plant which could take 44 to 50 months. She added that the batteries can store power from today’s resource mix to handle peak capacity needs and are just as reliable as a new gas plant.

Governors of PJM states are among the grid operator’s critics. They recently attended a summit convened by Gov. Josh Shapiro to discuss reforms and having a larger voice in PJM’s governance.

According to PJM, as of August, a total of 46,000 MW of new generation has signed interconnection agreements and are ready to construct, which once operational, could supply as many as 46 million homes. Many of the projects, however, are hampered by factors outside of their control – such as siting and permitting challenges, supply chain backlogs, and financial dynamics.

PJM’s stakeholders are scheduled to vote on a final proposal regarding the allocation of costs for new electric infrastructure on November 19.

Events

No events

Leave a Comment





Latest News Stories

Meeting-Briefs

Meeting Summary: Peotone School District 207-U for July 21, 2025

District Weighs Budget Cuts vs. More Debt: Peotone schools must create a state-mandated deficit reduction plan to address a recurring ~$2 million operating shortfall. The Board of Education is debating whether...
Beecher Graphic.1

Beecher Officially Adopts 1% Grocery Tax to Avert $202,000 Budget Hit

Article Summary: The Beecher Village Board unanimously passed an ordinance to establish a local 1% grocery tax, a proactive measure to prevent an estimated annual revenue loss of over $200,000...
Beecher Graphic.3

Hunter’s Chase Residents Confront Beecher Board Over Lennar Construction Issues

Article Summary: A group of frustrated residents from Beecher's Hunter's Chase subdivision attended the July 28 Village Board meeting to voice numerous complaints about Lennar's new home construction, citing early...
Beecher Graphic.4

Beecher Denies RV Parking Permit Over Precedent Concerns, Approves Fence Variance

Article Summary: The Beecher Village Board denied a special use permit for parking a recreational vehicle in a residential driveway, citing concerns about setting a difficult precedent for future requests....
Meeting-Briefs

Meeting Summary and Briefs: Village of Beecher Board of Trustees for July 28, 2025

The Beecher Village Board passed a crucial financial ordinance and addressed a wave of resident complaints about new home construction during its meeting on July 28. Trustees unanimously approved a...
Peotone-School-Cmte-Of-Whole-July-21.2

Peotone Schools to Launch “Go Big Blue” Unity Initiative

Peotone School District 207-U will rally under a new theme, “Go Big Blue,” for the 2025-26 school year in a comprehensive initiative aimed at unifying the district around common character...
Peotone-School-Cmte-Of-Whole-July-21.2

Peotone FFA Alumni Propose Privately Funded Greenhouse to Expand Program

The Peotone High School agriculture program could see a major expansion after the Peotone FFA Alumni and Friends group presented a proposal to the Board of Education to privately fund...
Ad Hock July 22nd

Will County Committee Forwards Overhauled Purchasing Code Amid Debate on Local Contractor Preference

The Will County Ad-Hoc Ordinance Review Committee advanced a major overhaul of the county's purchasing code Tuesday, but only after a split vote and a pointed debate over a separate,...
Ad Hock July 22nd

Finance Officials Clarify How Will County Tracks Assets, From Vehicles to Desks

Will County finance officials on Tuesday detailed the policies governing how the county tracks its physical and digital assets, explaining the $5,000 threshold for items that are formally capitalized and...
Ad Hock July 22nd

Will County Treasurer Confirms Free Online Tax Payment Option, Warns Against High Credit Card Fees

Will County Treasurer Tim Brophy confirmed Tuesday that property owners have a free online payment option available and advised residents to avoid the high convenience fees associated with using credit...
Ad Hock July 22nd

Committee Highlights ‘Lack of Teeth’ in County Code Enforcement Process

While the Will County Ad-Hoc Ordinance Review Committee quickly approved minor updates to its administrative adjudication ordinance Tuesday, the action sparked a broader discussion about resident frustration over the enforcement...
Meeting Briefs

Meeting Briefs: Will County Ad-Hoc Ordinance Review Committee for July 22, 2025

AI Policy Discussion Urged: Chair Jackie Triner called for the county to develop a comprehensive policy on the use of Artificial Intelligence. Citing a recent conference, Triner noted the potential benefits...
WCO P&Z July 15

Crete Township Wins Approval for New Digital Sign at Community Center

Crete Township received approval from the Will County Planning and Zoning Commission on Tuesday for a new digital sign at its community center, a project that required a special use...
WCO P&Z July 15

Will County Planners OK Oversized Garage Near Naperville, Overriding Staff Recommendation

The Will County Planning and Zoning Commission on Tuesday approved variances for a new oversized accessory garage in Wheatland Township, siding with a homeowner and builder over a staff recommendation...
WCO P&Z July 15

Green Garden Landscaping Business Gains Permit Amid Strong Neighbor Support

A small landscaping and lawn maintenance business operating on a residential property in Green Garden Township received official approval Tuesday after neighbors voiced overwhelming support for the operation. The Will...