Federal judge allows New York wind project to proceed

Federal judge allows New York wind project to proceed

Spread the love

A federal judge has given a green light for construction to resume on New York’s largest offshore wind project that was abruptly shut down by the Trump administration last month.

In a ruling issued Thursday, U.S. District Court judge Carl Nichols granted Empire Offshore Wind LLC a preliminary injunction that allows construction activities to resume on the wind project while he considers the broader legal challenge by the company. It’s the second ruling in a week blocking the Trump administration’s effort to stop several offshore wind projects.

In a statement, Norway-based Equinor said it looks forward to resuming construction of the Empire Wind I project, which, when completed, will provide enough energy to power 500,000 homes and “deliver a critical new, near-term source of electricity for New York and bolster grid reliability at a time of rapidly growing demand.”

“Empire Wind will now focus on safely restarting construction activities that were halted during the suspension period,” the company said. “In addition, the project will continue to engage with the U.S. government to ensure the safe, secure and responsible execution of its operations.”

The Interior Department did not immediately respond to a request for comment.

In its legal challenge, Equinor said the Interior Department’s stop-work order is “unlawful” and threatens the progress of ongoing work with significant implications for the project, which is nearly 60% complete.

President Donald Trump has pledged to end federal support for wind and other clean energy projects as he focuses on boosting fossil fuel production as part of broader efforts to improve the nation’s energy independence. He and other Republicans argue that the higher energy costs paid by many in the Northeast are being driven in part by the embrace of clean energy policies.

In December, the Interior Department announced it is halting federal leases for Empire and other large-scale offshore wind projects currently under construction. Besides Empire, the halt included Sunrise Wind, Vineyard Wind 1, Revolution Wind off the New England coast and Coastal Virginia Offshore Wind.

Earlier this week, a federal judge allowed the Revolution Wind project to resume construction while a separate legal challenge filed by its developers is considered by the court.

Interior Secretary Doug Burgum cited unspecified national security risks posed by the offshore wind turbines in pausing federal permits for the projects, but said the move is aimed at “protecting” the American people.

But Nichols, a Trump appointee, said in his order that the federal government’s national security concerns didn’t outweigh the “irreparable harm” Empire Wind would suffer if Trump’s order is not paused.

Speaking at an event on Thursday, Hochul praised the ruling and renewed criticism of the Trump administration for issuing the stop-work order just before Christmas, impacting thousands of workers.

“I’m sick and tired of having to go to court time and time and time again to stop these decisions,” she said in remarks. “They’re designed to do nothing other than hurt workers, hurt our states, hurt our economy and hurt our energy future.”

Leave a Comment





Latest News Stories

Meeting-Briefs

Meeting Summary and Briefs: Washington Township Board for September 4, 2024

Washington Township Board Meeting | September 4, 2024 The Washington Township Board convened on Wednesday, September 4, 2024, making several key financial decisions and hearing updates on local issues. The...
Screenshot 2025-10-17 at 2.37.04 PM

Beecher School Board Reviews Adding Accountability Clause to Oath of Office

Beecher Board of Education Regular Board Meeting | October 8, 2025 Article Summary: The Beecher Board of Education held a first reading of a policy update that would add a formal...
solar panels photovoltaics in solar farm

Washington Township Asks Will County to Deny Beecher-Area Solar Farm

Washington Township Board Meeting | September 4, 2024 Article Summary: The Washington Township Board has formally stated its opposition to a proposed solar farm in Beecher's "backyard," sending a letter...
Screenshot 2025-10-17 at 2.36.52 PM

Beecher School District Invests Over $100,000 in New Bus and GPS System

Beecher Board of Education Regular Board Meeting | October 8, 2025 Article Summary: The Beecher Board of Education approved the purchase of a new school bus for nearly $90,000 and a...
washington township graphic.2

Washington Township Board Approves Nearly $20,000 for New Digital Sign

Washington Township Board Meeting | September 4, 2024 Article Summary: The Washington Township Board has approved the purchase of a new, high-resolution LED message board for its highway sign at...
Meeting Briefs

Meeting Summary and Briefs: Village of Beecher Board for October 14, 2025

The Village of Beecher Board on Tuesday, October 14, 2025, heard a detailed proposal for a large-scale solar project in nearby unincorporated Will County that includes a $100,000 donation offer...
Screenshot 2025-10-17 at 2.36.39 PM

Facing Trainer Shortage, Beecher Schools to Use Paramedics for Athletic Coverage

Beecher Board of Education Regular Board Meeting | October 8, 2025 Article Summary: In response to a shortage of available athletic trainers, the Beecher School District will partner with the Beecher...
washington township graphic.1

Washington Township Assessor Details New Veteran Tax Exemption, Rising Farmland Values

Washington Township Board Meeting | September 4, 2024 Article Summary: Washington Township Assessor Patricia Peters updated the board on a new state law that modifies the property tax exemption for...
Beecher Graphic.3

Annual Audit Affirms Beecher’s ‘Healthy Financial Position’

Article Summary: An independent audit of the Village of Beecher's finances for the fiscal year ending April 30, 2025, resulted in a clean opinion, with auditors confirming the village is...
Screenshot 2025-10-17 at 2.36.18 PM

Beecher School Board Approves Over $42,000 to Remediate Elementary School Tunnels

Beecher Board of Education Regular Board Meeting | October 8, 2025 Article Summary: The Beecher Board of Education has approved a $42,645 contract with Allied Services to address long-standing moisture issues...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Legislative Committee for October 7, 2025

The Will County Legislative Committee held a long and contentious meeting on Tuesday, October 7, 2025, highlighted by the narrow 4-3 passage of a controversial resolution supporting protections for immigrant...
Screenshot 2025-10-16 at 8.18.26 PM

Beecher Board Considers $100,000 Offer Tied to Plum Valley Solar Project

Article Summary: A developer planning a 260-megawatt solar facility near Beecher has offered the village a $100,000 community benefit donation in exchange for a resolution of non-objection for the project....
Screenshot 2025-10-10 at 12.05.55 PM

Will County Board Committee Passes Contentious ‘Live and Work Without Fear’ Resolution on 4-3 Vote

Will County Legislative Committee Meeting October 7, 2025 Article Summary: The Will County Legislative Committee on Tuesday narrowly passed a controversial resolution affirming the county's commitment to ensuring all residents...
Meeting Briefs

Will County Awards $10.4 Million Contract for Bell Road Widening in Homer Glen Area

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Will County Public Works & Transportation Committee on Tuesday confirmed the award of a $10.4 million...
Screenshot 2025-10-10 at 12.12.16 PM

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for October 7, 2025

The Will County Public Works & Transportation Committee on Tuesday, October 7, 2025, approved a major construction contract and reviewed extensive plans for both county and state transportation initiatives. The...