Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

Meeting-Briefs

Meeting Summary and Briefs: Washington Township Board for September 4, 2024

Washington Township Board Meeting | September 4, 2024 The Washington Township Board convened on Wednesday, September 4, 2024, making several key financial decisions and hearing updates on local issues. The...
Screenshot 2025-10-17 at 2.37.04 PM

Beecher School Board Reviews Adding Accountability Clause to Oath of Office

Beecher Board of Education Regular Board Meeting | October 8, 2025 Article Summary: The Beecher Board of Education held a first reading of a policy update that would add a formal...
solar panels photovoltaics in solar farm

Washington Township Asks Will County to Deny Beecher-Area Solar Farm

Washington Township Board Meeting | September 4, 2024 Article Summary: The Washington Township Board has formally stated its opposition to a proposed solar farm in Beecher's "backyard," sending a letter...
Screenshot 2025-10-17 at 2.36.52 PM

Beecher School District Invests Over $100,000 in New Bus and GPS System

Beecher Board of Education Regular Board Meeting | October 8, 2025 Article Summary: The Beecher Board of Education approved the purchase of a new school bus for nearly $90,000 and a...
washington township graphic.2

Washington Township Board Approves Nearly $20,000 for New Digital Sign

Washington Township Board Meeting | September 4, 2024 Article Summary: The Washington Township Board has approved the purchase of a new, high-resolution LED message board for its highway sign at...
Meeting Briefs

Meeting Summary and Briefs: Village of Beecher Board for October 14, 2025

The Village of Beecher Board on Tuesday, October 14, 2025, heard a detailed proposal for a large-scale solar project in nearby unincorporated Will County that includes a $100,000 donation offer...
Screenshot 2025-10-17 at 2.36.39 PM

Facing Trainer Shortage, Beecher Schools to Use Paramedics for Athletic Coverage

Beecher Board of Education Regular Board Meeting | October 8, 2025 Article Summary: In response to a shortage of available athletic trainers, the Beecher School District will partner with the Beecher...
washington township graphic.1

Washington Township Assessor Details New Veteran Tax Exemption, Rising Farmland Values

Washington Township Board Meeting | September 4, 2024 Article Summary: Washington Township Assessor Patricia Peters updated the board on a new state law that modifies the property tax exemption for...
Beecher Graphic.3

Annual Audit Affirms Beecher’s ‘Healthy Financial Position’

Article Summary: An independent audit of the Village of Beecher's finances for the fiscal year ending April 30, 2025, resulted in a clean opinion, with auditors confirming the village is...
Screenshot 2025-10-17 at 2.36.18 PM

Beecher School Board Approves Over $42,000 to Remediate Elementary School Tunnels

Beecher Board of Education Regular Board Meeting | October 8, 2025 Article Summary: The Beecher Board of Education has approved a $42,645 contract with Allied Services to address long-standing moisture issues...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Legislative Committee for October 7, 2025

The Will County Legislative Committee held a long and contentious meeting on Tuesday, October 7, 2025, highlighted by the narrow 4-3 passage of a controversial resolution supporting protections for immigrant...
Screenshot 2025-10-16 at 8.18.26 PM

Beecher Board Considers $100,000 Offer Tied to Plum Valley Solar Project

Article Summary: A developer planning a 260-megawatt solar facility near Beecher has offered the village a $100,000 community benefit donation in exchange for a resolution of non-objection for the project....
Screenshot 2025-10-10 at 12.05.55 PM

Will County Board Committee Passes Contentious ‘Live and Work Without Fear’ Resolution on 4-3 Vote

Will County Legislative Committee Meeting October 7, 2025 Article Summary: The Will County Legislative Committee on Tuesday narrowly passed a controversial resolution affirming the county's commitment to ensuring all residents...
Meeting Briefs

Will County Awards $10.4 Million Contract for Bell Road Widening in Homer Glen Area

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Will County Public Works & Transportation Committee on Tuesday confirmed the award of a $10.4 million...
Screenshot 2025-10-10 at 12.12.16 PM

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for October 7, 2025

The Will County Public Works & Transportation Committee on Tuesday, October 7, 2025, approved a major construction contract and reviewed extensive plans for both county and state transportation initiatives. The...