will county Committee-Capital Improvement.Graphic

Will County Leaders Debate New Construction to Escape $1.2 Million in Leases

Spread the love

Capital Improvements & IT Committee Meeting | March 2026

Article Summary: The Will County Capital Improvements and IT Committee is aggressively exploring options to consolidate county offices and exit leased properties, sparking a debate over where to build a new government campus and how to fund it.

Capital Improvements 5-Year Plan Key Points:

  • Will County currently utilizes approximately 65,000 square feet of leased space, costing taxpayers roughly $1.2 million annually.

  • A Master Plan Update in the agenda packet projects the county will need 118,000 square feet for the County Office Building and 101,040 square feet for Judicial Agencies by 2050.

  • Committee members are divided on whether to build a new facility on the site of the recently demolished old courthouse or expand the current county office campus.

  • A debt capacity report indicates the county could potentially issue up to $142.6 million in new bonds without increasing the overall annual debt service level.

The Will County Capital Improvements and IT Committee on Tuesday, March 3, 2026, waded into a complex debate over the future of the county’s physical footprint, driven by a desire to consolidate scattered departments and eliminate expensive rental leases.

Committee Chair Mica Freeman initiated the discussion by outlining her vision to bring currently displaced departments—such as the Public Defender, State’s Attorney, and Regional Office of Education—under a single, county-owned roof.

According to County Board Member Daniel J. Butler, the county’s reliance on leased spaces is currently a significant financial drain.

“We use 65,000 square feet of rental space and we paid $1.2 million for rental,” Butler said, noting that these costs were part of the original argument for attempting to save and expand the old 140,000-square-foot county courthouse before the board ultimately voted to demolish it.

“Building a new courthouse building in that exact same location would be the height of folly. I mean, really, tearing down the building and building it right back,” Butler remarked, though he acknowledged the urgent need to address the spatial deficit.

Member Steve Balich argued that the most logical and cost-effective long-term solution is to construct a new, basic facility—potentially on the site of the old courthouse—to eliminate the rental overhead.

“You just build a two-story building, steel, it’s cheaper, and move everybody in there, move everybody into different places in the building, and we’ll save a ton of money in rental,” Balich said. “We don’t really need to have bonds because we’ll be able to take the rent money to pay for the cost of a building.”

However, Member Jacqueline Traynere strongly opposed any plan that might increase the tax burden, and pushed back against utilizing the old courthouse site due to historical construction hurdles.

“I’m not in favor of raising property taxes to pay for new buildings,” Traynere said. She advocated for constructing a smaller, expandable building on the current County Office Building campus instead. “We could put parking at the bottom of the building, but we can’t go down deep because that’s limestone. That was the problem we had with the jail. Building anywhere in that general vicinity costs us a lot of extra money.”

While the committee did not take a formal vote, the agenda packet included deep contextual data to inform their upcoming decisions. A Master Plan Update provided by Wight projects that by the year 2050, the County Office Building departments will require 118,000 Departmental Gross Square Feet (DGSF), up from their current 62,260 DGSF. Similarly, Judicial Agency Departments will see their needs grow from 88,841 DGSF to 101,040 DGSF.

To finance potential construction, the committee referenced a recent debt profile from Speer Financial, included in the packet. The report shows that as older bonds are paid off, Will County will experience a significant drop in outstanding debt payments after 2026 and 2030. By structuring a split-issuance of General Obligation Alternate Revenue Source bonds, the county could theoretically capture up to $142.6 million in project funds without raising its current $25 million annual debt service target.

Member Mark V. Revis suggested that once staff returns with concrete price-per-square-foot estimates, the board should convene a special meeting to ensure all members are aligned before moving forward.

“This is one of those items that is going to cross the threshold where everybody is going to want to have a firm understanding of it before they cast their vote,” Revis said.

Leave a Comment





Latest News Stories

Screenshot 2025-05-04 at 3.03.49 PM

Will County Approves Vision Zero Initiative to Reduce Traffic Fatalities

Will County has officially adopted Vision Zero, a data-driven safety initiative aimed at eliminating traffic fatalities throughout the county. The Public Works and Transportation Committee unanimously approved the resolution, which...
Screenshot 2025-05-04 at 3.03.49 PM

County’s First Roundabout Planned for Exchange Street and Beecher Road Intersection

Will County's first roundabout is advancing to the final public meeting phase, with construction tentatively scheduled for 2027. County Engineer Jeff Ronaldson announced that the Department of Transportation will hold...
Screenshot 2025-05-04 at 3.03.49 PM

County Accepts $377,000 Developer Donation for Romeo Road Improvements

The Will County Public Works and Transportation Committee has accepted a $377,000 donation from a developer to fund roadway improvements at the southeast corner of Romeo Road and Weber Road...
Screenshot 2025-05-04 at 3.03.49 PM

Contracts Awarded for LED Signal Upgrades and Guardrail Maintenance

The Will County Public Works and Transportation Committee has approved contracts for two significant infrastructure maintenance projects: LED traffic signal upgrades and guardrail maintenance across the county. A contract for...
Screenshot 2025-05-04 at 3.03.49 PM

BRIEFS: Will County Public Works Projects

County Line Road Resurfacing Contract Awarded: The committee approved a $767,249 contract to Iroquois Paving Corporation for resurfacing County Highway 58 (County Line Road) from N5000 East Road east to...
Screenshot 2025-05-04 at 2.36.35 PM

County Approves Two Solar Energy Projects, Committee Discusses Zoning Challenges

The Will County Land Use and Development Committee approved two commercial solar energy projects Wednesday despite objections from the Village of Manhattan regarding one of the proposals. In a 6-1...
Screenshot 2025-05-04 at 2.36.35 PM

Committee Debates Easing Size Restrictions on Accessory Dwelling Units

Will County's Land Use and Development Committee is considering changes to its accessory dwelling unit (ADU) regulations that could provide more flexibility for homeowners looking to create additional living spaces...
Screenshot 2025-05-04 at 2.36.35 PM

“Tiny Homes” Status Creates Regulatory Confusion for County Officials

Will County officials are struggling to establish clear regulations for "tiny homes," with committee members expressing confusion over terminology and appropriate standards during Wednesday's Land Use and Development Committee meeting....
Screenshot 2025-05-04 at 2.36.35 PM

County Officials Begin Exploring Regulations for Small Modular Nuclear Reactors

Will County is beginning to explore potential regulations for small modular nuclear reactors (SMRs) after recent Illinois legislation allowed their development, planning staff told the Land Use and Development Committee...
Screenshot 2025-05-04 at 2.17.47 PM

Will County Land Use News Briefs

Truck Terminal Proposal Tabled for Traffic Study: The committee tabled a special use permit request from Litmax Multi-Service Inc. for a truck terminal in New Lenox Township at 22645 Cherry...
Screenshot 2025-05-04 at 2.57.14 PM

County Moves Forward with Veterans Building Renovations, Questions Arise on Pace Building Plans

Will County's Capital Improvements Committee received updates Tuesday on multiple county facility projects, including progress on the Copperfield Drive building renovations for veterans services, while discussions revealed questions about the...
Screenshot 2025-05-04 at 2.57.14 PM

County Continues Efforts to Reduce Leased Office Space Footprint

Will County officials reported Tuesday that efforts to consolidate county operations in owned facilities are continuing to reduce the county's leased office space footprint, with further reductions expected when the...
Screenshot 2025-05-04 at 2.57.14 PM

County Reports Significant Cost Savings Through In-House Facility Projects

Will County is achieving substantial cost savings by completing facility improvement projects with in-house staff rather than contracting the work out, according to a presentation to the Capital Improvements Committee...
Screenshot 2025-05-04 at 2.50.36 PM

County Legislative Committee Endorses Electronic Recycling Bill, Reviews Transit Governance

The Will County Legislative Committee voted Thursday to support proposed state legislation that would extend and expand Illinois' electronic recycling program, while also reviewing potential changes to regional transit governance...
Screenshot 2025-05-04 at 2.57.14 PM

Will County Capital Improvements News Briefs

Courthouse Scaffolding Expected to Come Down Soon: Scaffolding on one corner of the Will County Courthouse should be removed within the next two weeks, pending reports from material scientists. "We're...