Screenshot 2025-05-04 at 2.17.47 PM

County Considers Two Options for Prairie View Landfill Expansion

Prairie View landfill could extend its lifespan by up to 35 additional years under expansion plans presented to the county’s landfill committee on Wednesday.

Consultant Marty Fallon outlined two potential expansion strategies that would either build vertically on the existing footprint or combine vertical growth with a horizontal expansion to the northeast.

“We’ve generated dozens of different iterations of concept designs,” said Fallon, an operations manager with Geologic Associates who has spent 25 years designing and permitting waste management infrastructure. “We’ve come to a consensus to site both a vertical expansion option and a horizontal and vertical expansion option and to run those parallel.”

The existing landfill has approximately nine years of capacity remaining at current filling rates. The vertical-only option would add approximately 24.5 years, while the combined vertical and horizontal expansion would provide about 35 years total.

Both options would increase the landfill’s height by approximately 170 feet from its currently permitted elevation, bringing the peak to 965 feet above sea level. According to calculations presented at the meeting, this would make the landfill approximately 320 feet high from its base.

The horizontal expansion would require relocating a 1.4 million cubic yard soil stockpile currently stored in the northeastern portion of the property. Fallon noted that finding an off-site location for this material would be necessary before proceeding with that option.

“The closer the better because it is a lot of soil. It’s going to be a lot of trucks, a lot of excavation, a lot of loading,” Fallon said when questioned about potential sites for relocating the soil.

To advance both design options, Geologic Associates plans to conduct a site investigation beginning April 21, including nine new boring locations extending the grid established during the original late 1990s site assessment. This investigation will characterize the geology and collect data to ensure designs are “protective of public health, safety and welfare,” according to Fallon.

Committee member Van Dyke expressed concern about the increased height, but Fallon presented visual simulations suggesting the expanded landfill would remain largely obscured from surrounding roadways due to existing tree cover and setbacks.

“This site is really buffered very well from the perimeter roadways. Height shouldn’t really be that big of a deal for the committee,” Fallon said.

The development of a final application will be “a huge undertaking,” according to Fallon, potentially requiring a year to 18 months following completion of the geological investigation. The application will include detailed engineering calculations, geological modeling, operating plans, construction quality assurance plans, closure plans, traffic impact analysis and real estate impact studies.

Engineering aspects of the existing landfill, including the integrity of pipes that collect leachate (water that filters through the waste), have received preliminary review to verify they can support the additional weight of expanded waste storage.

During public comments, concerns were raised about garbage debris along roadways used by trucks traveling to and from the landfill. Committee member Butler noted complaints from the farming community about litter along transportation routes.

“I know we do have a county highway that goes from I-55 to Route 53 and is consistently littered with garbage,” said another community member. “I wish there was a way to figure out how to monitor these trucks or do a better job of covering them.”

The landfill committee’s next meeting is scheduled for May 13, though Fallon indicated that complete testing results might not be available for “a couple of months.”

Events

No events

Leave a Comment





Latest News Stories

Meeting Briefs

Will County Legislative Committee July 1 Meeting Briefs

Federal Budget Impact: Will County could face significant funding challenges if federal budget reconciliation measures reduce Medicaid and SNAP benefits. The county health department and social services rely heavily on...
Will County Finance Committee Meeting July 1, 2025

County Moves Forward with $200.8 Million Bond Refinancing Plan

Will County Finance Committee members on July 1 approved moving forward with a comprehensive bond refinancing ordinance that could save taxpayers more than $716,000 over the life of the bonds...
Will County Public Works & Transportation Committee Meeting July 1, 2025

Access Will County Dial-a-Ride Program Sees Record Growth, Eyes Expansion

Will County's dial-a-ride transportation service for seniors and disabled residents reached record ridership levels while officials plan major expansion to cover all county townships. The Access Will County program served...
Will County Capital Improvements & IT Committee Meeting July 1, 2025

Will County to Launch New Public Meeting Agenda System in August Amidst Data Conversion Concerns

Will County is set to launch its new public meeting agenda and records software, Granicus “OneMeeting,” in August, but the transition will see over a decade of historical records converted...
Will County Planning and Zoning Commission Meeting July 1, 2025

Green Garden Township Poised for First Major Subdivision in Years After Rezoning

The Will County Planning and Zoning Commission has recommended a rezoning that could pave the way for the first major residential subdivision in Green Garden Township in nearly two decades....
Will County Finance Committee Meeting July 1, 2025

County RNG Facility Shows Strong Performance Despite Solar Challenges

Will County's Renewable Natural Gas facility is exceeding production targets while officials explore options to reduce substantial electricity costs that currently impact profitability. Project manager Greg Komperda told Finance Committee...
Meeting Briefs

PZC Briefs: Solar Farm in Crete, Post-Fire Permit for Troy Business, and More

The Will County Planning and Zoning Commission handled several other cases during its July 1 meeting, including a new solar farm, a temporary permit for a fire-damaged business, and routine...
Meeting Briefs

In Brief: Capital & IT News

Here are other highlights from the Will County Capital Improvements & IT Committee meeting on Tuesday. Successful Fire Drill at County BuildingThe Will County Office Building held its first full...
Meeting Briefs

Will County Finance Committee July 1 Meeting Briefs

Bond Refinancing Advances: Finance Committee approved an ordinance authorizing up to $200.8 million in bond refinancing that could save taxpayers more than $716,000. The measure moves to the full County...
Meeting Briefs

Will County Public Works Committee Juliy 1 Meeting Briefs

ROAD CONTRACTS APPROVED Austin Tyler Construction Contract: The committee approved a $691,544 contract with Austin Tyler Construction for resurfacing River Road from East Frontage Road to Prairie Creek Bridge and...
prairie state college graphic.2

Prairie State College Braces for Potential Federal Cuts to TRIO Student Support Program

Article Summary: Prairie State College leadership is developing contingency plans amid uncertainty over federal funding for its TRIO programs, which provide critical academic and personal support to first-generation, low-income, and...
prairie state college graphic.1

Prairie State College Showcases Booming Allied Health and Emergency Services Programs

Article Summary: Prairie State College's (PSC) Allied Health and Emergency Services division is experiencing a period of significant growth and success, marked by high student pass rates, expanding programs, and...
Meeting-Briefs

Meeting Summary and Briefs: Beecher Fire Protection District Board of Trustees for May 29, 2025

The Beecher Fire Protection District Board of Trustees conducted its annual reorganization on May 29, reappointing Margie Cook as board president. Trustees also approved a significant technology upgrade by signing...
Beecher Fire Protection District graphic.3

Beecher Fire District Bolsters Staff with Four New Part-Time Hires

Article Summary: The Beecher Fire Protection District has added four new part-time emergency responders to its roster, a move that enhances its operational readiness and ability to serve the community....
Beecher Fire Protection District graphic.1

Beecher Fire District Reorganizes Board, Approves New Record System and Community Donations

Article Summary: The Beecher Fire Protection District Board of Trustees has established its leadership for the upcoming year, reappointing Margie Cook as president, while also approving a major technology upgrade...