County Considers Two Options for Prairie View Landfill Expansion

Spread the love

Prairie View landfill could extend its lifespan by up to 35 additional years under expansion plans presented to the county’s landfill committee on Wednesday.

Consultant Marty Fallon outlined two potential expansion strategies that would either build vertically on the existing footprint or combine vertical growth with a horizontal expansion to the northeast.

“We’ve generated dozens of different iterations of concept designs,” said Fallon, an operations manager with Geologic Associates who has spent 25 years designing and permitting waste management infrastructure. “We’ve come to a consensus to site both a vertical expansion option and a horizontal and vertical expansion option and to run those parallel.”

The existing landfill has approximately nine years of capacity remaining at current filling rates. The vertical-only option would add approximately 24.5 years, while the combined vertical and horizontal expansion would provide about 35 years total.

Both options would increase the landfill’s height by approximately 170 feet from its currently permitted elevation, bringing the peak to 965 feet above sea level. According to calculations presented at the meeting, this would make the landfill approximately 320 feet high from its base.

The horizontal expansion would require relocating a 1.4 million cubic yard soil stockpile currently stored in the northeastern portion of the property. Fallon noted that finding an off-site location for this material would be necessary before proceeding with that option.

“The closer the better because it is a lot of soil. It’s going to be a lot of trucks, a lot of excavation, a lot of loading,” Fallon said when questioned about potential sites for relocating the soil.

To advance both design options, Geologic Associates plans to conduct a site investigation beginning April 21, including nine new boring locations extending the grid established during the original late 1990s site assessment. This investigation will characterize the geology and collect data to ensure designs are “protective of public health, safety and welfare,” according to Fallon.

Committee member Van Dyke expressed concern about the increased height, but Fallon presented visual simulations suggesting the expanded landfill would remain largely obscured from surrounding roadways due to existing tree cover and setbacks.

“This site is really buffered very well from the perimeter roadways. Height shouldn’t really be that big of a deal for the committee,” Fallon said.

The development of a final application will be “a huge undertaking,” according to Fallon, potentially requiring a year to 18 months following completion of the geological investigation. The application will include detailed engineering calculations, geological modeling, operating plans, construction quality assurance plans, closure plans, traffic impact analysis and real estate impact studies.

Engineering aspects of the existing landfill, including the integrity of pipes that collect leachate (water that filters through the waste), have received preliminary review to verify they can support the additional weight of expanded waste storage.

During public comments, concerns were raised about garbage debris along roadways used by trucks traveling to and from the landfill. Committee member Butler noted complaints from the farming community about litter along transportation routes.

“I know we do have a county highway that goes from I-55 to Route 53 and is consistently littered with garbage,” said another community member. “I wish there was a way to figure out how to monitor these trucks or do a better job of covering them.”

The landfill committee’s next meeting is scheduled for May 13, though Fallon indicated that complete testing results might not be available for “a couple of months.”

Leave a Comment





Latest News Stories

Committee-Land Use.Graphic

Meeting Summary and Briefs: Will County Land Use & Development Committee for February 5, 2026

Will County Land Use & Development Committee Meeting | February 5, 2026 The Will County Land Use and Development Committee met on Thursday, February 5, 2026, to deliberate on several...
Beecher Graphic.1

Beecher Village Board Splits on Capital Spending: Park Stage Renovation Rejected, Police Sign Approved

Village of Beecher Board Meeting | Feb 23, 2026 Article Summary: The Beecher Village Board engaged in a debate over how to allocate nearly $227,000 in proceeds from the sale...
Committee-Executive.Graphic

Meeting Summary and Briefs: Will County Executive Committee for February 11, 2026

Will County Executive Committee Meeting | February 11, 2026 Meeting SummaryThe Will County Board Executive Committee met on Wednesday, February 11, 2026, tackling a heavy agenda focused on economic development...
Election Vote Graphic

Group Presents Allegations of 2024 Voter Roll Errors to County Board

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board approved a resolution calling for the review of election systems and integrity, following public comments alleging inaccuracies...
beecher illinois public library graphic.1

Library Moves Forward with Entrance Project, Faces Heating System Failure

Beecher Public Library District Meeting | Jan. 20, 2026 Article Summary: The Beecher Public Library District Board set the timeline for bidding on its main front entrance project and addressed...
Will County Board Graphic.04

Will County Board Advised on Strict “Judicial” Role Ahead of Landfill Expansion Application

Will County Landfill Committee Meeting | February 10, 2026 Article Summary: During a detailed legal briefing on Tuesday, the Will County Landfill Committee received strict instructions regarding their conduct during...
Committee-Ad-Hoc.Graphic

Ad-Hoc Committee: Bath House Regulations Updated; Removes 60-Day Licensing Window

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee approved updates to the regulations governing bath houses and...
Committee-Land Use.Graphic

Land Use Committee Rejects Shorewood Solar Farm Despite 25-Year Lease Offer

Will County Land Use & Development Committee Meeting | February 5, 2026 Article Summary: The Will County Land Use and Development Committee voted against recommending a controversial solar farm proposal...
Committee-Executive.Graphic

Executive Committee Advances $28.7 Million BNSF Bridge Project for Lorenzo Road

Will County Executive Committee Meeting | February 11, 2026 Article Summary: The Executive Committee approved an agreement with BNSF Railway to construct a grade separation bridge on Lorenzo Road in...
Committee-Land Use.Graphic

Land Use Committee: ‘Clean Fill’ Proposal Stalls After Unauthorized Tree Removal Sparks Environmental Concerns

Will County Land Use & Development Committee Meeting | February 5, 2026 Article Summary: A request to rezone land for a "clean fill" operation in Joliet Township stalled in committee...
Committee-Planning & Zoning.Graphic

Meeting Summary and Briefs: Will County Planning and Zoning Commission for February 17, 2026

Will County Planning and Zoning Commission Meeting | February 17, 2026 JOLIET, IL – The Will County Planning and Zoning Commission met on Tuesday, February 17, 2026, with Acting Chairman John...
Committee-Ad-Hoc.Graphic

Ad-Hoc Committee: Liquor Ordinance Stalls Over Drafting Errors; Debates License Cap Policy

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee postponed a vote on the comprehensive update to the...
Committee-Executive.Graphic

Green Garden Township Residents Threaten Incorporation to Block 6,000-Acre Solar Farm

Will County Executive Committee Meeting | February 11, 2026 Article Summary: Residents of Green Garden Township warned county officials they are moving to incorporate as a village to gain zoning...
Meeting Briefs

Meeting Summary and Briefs: Beecher Board of Education for February 11, 2026

Beecher Board of Education Meeting | February 11, 2026 The Beecher Board of Education met on Wednesday, February 11, 2026, to review academic data and approve several operational contracts. The...
Elsie's Place, located at 1140 Dixie Highway, Unit 1, marked its official launch today with a grand opening and ribbon-cutting ceremony! Elsie's Place is a sandwhich shop with gaming.

Elsies Place Grand Opening

Elsie's Place, located at 1140 Dixie Highway, Unit 1, marked its official launch today with a grand opening and ribbon-cutting ceremony! Elsie's Place is a sandwhich shop with gaming.