Article Summary: The Beecher Village Board unanimously approved more than $35,000 in emergency repairs for Well #5 after a recent video inspection revealed significant corrosion, mineral buildup, and a failing check valve. The essential repairs are needed to address a corroding component that risks breaking and to treat deposits inside the well casing.

Beecher Public Works Key Points:

  • Approved $23,920 to Layne Christensen Company for well casing scarification, chlorination, and replacement of a corroded pitless spool.

  • Approved two proposals from Core & Main totaling $11,980.59 for a new check valve and a new 18-year-old master meter.

  • Repairs were deemed necessary after a video survey found a leaking discharge pipe, a corroding spool, and significant sulfate-based deposits and biofilm on the borehole walls.

BEECHER – The Village of Beecher will undertake a series of urgent repairs on a critical piece of its water infrastructure after the Board of Trustees approved three separate proposals totaling $35,900.59 to rehabilitate Well #5. The action came during the board’s June 9 meeting following a report from the Public Works Committee.

The need for the repairs was identified after a downhole video survey revealed several issues, including a buildup of iron and calcium deposits on the inside of the well pipe.

Trustee Erik Gardner presented the first proposal from Layne Christensen Company for $23,920. This work involves “scarification,” a process using a specialized tool to scrape the mineral deposits off the well’s interior walls. The well will then be chlorinated to prevent bacterial growth before being brought back online.

“There’s a buildup of iron and deposit calcium on the inside of the pipe that they want to take a basically a bit and run it down the inside of the pipe to scarify the walls,” Public Works Superintendent Matt Conner explained to the board.

The inspection also discovered that a “pitless spool,” a component welded into place, was suffering from significant corrosion. According to a proposal from Layne Christensen, the corrosion was advanced enough that it could lead to holes developing, potentially causing the “entire column pipe, pump and motor from falling down hole.”

“The corrosion attached to the weld where the weld actually weakens the metal,” Conner said. “So the corrosion actually started eating away at the weld that was done previously when the pipe was originally put in in 2007.”

In addition to the work by Layne Christensen, the board approved two proposals from Core & Main. The first, for $3,430, is to replace a check valve that is no longer functioning correctly. According to the agenda, the faulty valve is allowing water from the distribution system to leak back into the well house and down the shaft.

The second Core & Main proposal, for $8,550.59, will replace the well’s master meter. “The master meter is 18 years old and the public works committee made the recommendation to replace the meter while the well house is down,” Gardner read from the agenda.

All three measures were approved unanimously by Trustees Gardner, Roger Stacey, Brian Diachenko, Todd Kraus, Jessica Smith, and Joe Tieri.

Events

No events

Leave a Comment





Latest News Stories

Screenshot 2025-05-04 at 3.03.49 PM

County Approves $4.3 Million Purchase of Wetland Banking Credits for Highway Projects

The Will County Public Works and Transportation Committee has approved an agreement to purchase wetland banking site credits for $4,324,550 from V3 Wetland Restoration LLC to support future county highway...
Meeting-Briefs

Meeting Summary and Briefs: Beecher Fire Protection District Board of Trustees for March 20, 2025

The Beecher Fire Protection District is preparing for changes in its leadership and staffing after the Board of Trustees on March 20 approved the creation of a new Lieutenant position....
Beecher Fire Protection District graphic.1

Beecher Fire District to Hire New Lieutenant, Approves Updated Appointment Process

Article Summary: The Beecher Fire Protection District Board of Trustees has authorized the creation of a new Lieutenant position and will begin accepting applications at the end of March. The...
Screenshot 2025-05-04 at 2.01.41 PM

Labor Representative Addresses County Committee on Public Transportation Reform Efforts

JOLIET — A labor representative warned Will County officials Thursday that proposed reforms to regional public transportation governance could diminish the county's voice in transit decisions during a presentation to...
Screenshot 2025-05-04 at 2.01.41 PM

Committee Advances $1.7 Million Upgrade Plan for River Valley Juvenile Detention Center

JOLIET — The Will County Executive Committee voted Thursday to advance a $1.7 million proposal to upgrade the River Valley Juvenile Detention Center rather than pursuing costlier alternatives to house...
Screenshot 2025-05-04 at 2.01.41 PM

County Executive Committee Briefs: Transportation Program Expands, Ordinances Updated

Mobility Management Program Expands to Three Townships: The Executive Committee approved an intergovernmental agreement to expand the Will County Mobility Management Program to include Channahon, Manhattan, and Plainfield townships. The...
Screenshot 2025-05-04 at 2.01.41 PM

County Executive Committee Advances Elected Officials’ Pay Increases After Extended Debate

The Will County Executive Committee voted Thursday to advance a proposal for pay increases for countywide elected officials and county board members, setting the stage for a final vote at...
Screenshot 2025-05-04 at 2.01.41 PM

County Considers Bond Refinancing That Could Save Millions

JOLIET — Will County officials on Thursday discussed a potential bond refinancing opportunity that could save the county approximately $3.6 million in debt service costs by taking advantage of favorable...
Screenshot 2025-05-04 at 2.14.20 PM

Will County Ordinance Committee Briefs: Unanimous Votes for Proclamations, Title Changes, Audits Discussed

Committee Clarifies Unanimous Vote Requirement for Honorary Proclamations: The Ordinance Committee refined language in Chapter 30 regarding honorary proclamations, specifying that they shall be allowed "only by unanimous vote" of...
Screenshot 2025-05-04 at 2.14.20 PM

County Undertakes Formatting Overhaul of Decades-Old Ordinances

JOLIET — Will County officials are modernizing the format and structure of the county's ordinances, some of which date back to 1943, as part of a comprehensive review process to...
Screenshot 2025-05-04 at 2.14.20 PM

County Reviews Rules on Virtual Meeting Attendance, Committee Participation

JOLIET — Will County officials discovered Thursday that their current practices regarding virtual meeting attendance may not fully comply with state law, as the Ordinance Committee worked through updates to...
Screenshot 2025-05-04 at 2.14.20 PM

Will County Ordinance Committee Reviews Administrative Code, Clarifies Official Powers

JOLIET — The Will County Ordinance Committee spent several hours Thursday reviewing and updating Chapter 30 of the county's Code of Ordinances, which governs county administration, with particular attention to...
Screenshot 2025-05-04 at 2.17.47 PM

Farmers, Residents Call for Action on Roadside Debris from Landfill Trucks

Local farmers and residents are urging county officials to address persistent litter problems along routes used by trucks traveling to and from Prairie View landfill. The issue emerged during public...
Screenshot 2025-05-04 at 2.17.47 PM

County Landfill Meeting Briefs

Landfill Minutes Approved: The landfill committee unanimously approved minutes from its February 11, 2025 meeting. All committee members were present, including Hickey, Brooks, Bulock, Logan, Newquest, Pretzel, and Dean Schlotman....
Screenshot 2025-05-04 at 2.17.47 PM

Geological Features Central to Landfill Expansion Plans

Geological characteristics that were formed thousands of years ago make Prairie View an ideal location for landfill operations, according to the geologist leading expansion plans for the facility. During Wednesday's...