New Beecher Public Safety Facility Nears Completion Amidst Minor Setbacks
Article Summary: Beecher’s new Public Safety Facility is nearing the final stages of completion, with the parking lot recently paved and striped, but the village is now addressing a potential roof issue and a plan to fix the garage floor. Police Chief Terry Lemming praised the new building, calling it “beautiful” and a major asset for the community.
Public Safety Facility Key Points:
-
A potential roof problem involving broken screws holding down decking boards is being investigated by the contractor.
-
The plan to fix pooling water in the garage involves installing two new drains and applying an industrial epoxy coating to the entire floor.
BEECHER – With the parking lot now paved and striped, the new Beecher Public Safety Facility is moving closer to its grand opening, though officials are still resolving a few final construction issues.
During the June 9 village board meeting, Trustee Brian Diachenko reported that while major exterior work is complete, a potential problem with the roof has emerged. Administrator Charity Mitchell explained that during an inspection, broken screws were found holding down the roof’s decking boards, causing some sections to “heave.” The construction contractor and roofer are investigating and developing a solution.
A resolution has also been reached for an issue with water pooling on the garage floor. “JMA is going to put two drains in the rear portion of the garage where the water is standing, and then they’re going to epoxy the entire floor,” Mitchell said. The board confirmed the coating will be a durable, industrial-grade epoxy.
Despite the minor setbacks, Police Chief Terry Lemming expressed immense satisfaction with the new facility. “The building is beautiful. It’s just absolutely more than better than I ever expected,” Lemming said. “It’s going to be great for recruiting, great for retention, great for getting the community to the police station for a good reason.”
Lemming added that the building’s community room is now available for use by any non-profit community groups. The fence for the property is scheduled to be installed the week of June 23.
Latest News Stories
Washington Township Approves $13,260 Security Overhaul, Opts for Local Vendor with 24/7 Service
Washington Township Board Appoints Teresa Peterson to Fill Vacancy
Washington Township Board Passes 2025-2026 Town Budget
Meeting Summary and Briefs: Washington Township Board of Trustees for June 2, 2025
Meeting Summary and Briefs: Beecher Fire Protection District Board of Trustees for April 24, 2025
Beecher Public Bodies Renew Joint Fuel Purchasing Agreement to Save Taxpayer Money
Beecher Fire District Invests Over $91,000 in New Protective Gear and Helmets
Beecher Library Board Installs New Trustees, Elects Officers for Two-Year Term
Beecher Library Board Streamlines Bill Payments Between Meetings
Meeting Summary and Briefs: Beecher Community Library Board for May 20, 2025
Will County Board Rejects Two Solar Farm Projects After Heated Public Opposition
County Approves $15 Million Water System Takeover for Southeast Joliet Area
Board Postpones County Purchasing Code Overhaul Amid Union Contractor Debate
Animal Permit Hearing Reveals Neighborhood Disputes Over Horses, Roosters in Crete Township