Hunter’s Chase Residents Confront Beecher Board Over Lennar Construction Issues

Article Summary: A group of frustrated residents from Beecher’s Hunter’s Chase subdivision attended the July 28 Village Board meeting to voice numerous complaints about Lennar’s new home construction, citing early morning work, property damage, and significant safety concerns, including a recent gas leak allegedly caused by digging without proper utility locates. Village officials listened to the concerns and promised to address the issues with the developer and the village’s contracted inspection service.

Lennar Construction Concerns Key Points:

  • Residents reported construction work starting before the village’s 7 a.m. ordinance allows.

  • A primary concern was the developer’s alleged failure to call for JULIE utility locates, which residents said resulted in a gas leak.

  • Other complaints included heavy equipment tearing up a public easement around a pond, potential damage to roads, and foundation holes being left open and unsecured.

  • Village officials, including the attorney and police chief, assured residents they would enforce local ordinances.

BEECHER – Residents of the Hunter’s Chase subdivision have brought a list of serious concerns regarding homebuilder Lennar’s construction practices directly to the Village Board, citing safety violations, property damage, and a disregard for local ordinances.

During the public comment portion of the July 28 board meeting, several residents described a pattern of carelessness at the construction sites. One major issue was work beginning before the village’s permitted 7 a.m. start time.

“I’m sitting out having a coffee at 6:30 a.m. last week and we have truck after truck after truck of gravel rolling in,” resident Sharon H. told the board.

A more serious safety concern involved the developer allegedly digging without first calling for JULIE utility locates. “There were no Julie markings,” the resident said, explaining that the oversight led to a gas leak that required an emergency response from Nicor Gas. “Could have been bad. Luckily it wasn’t.”

Residents also expressed frustration over damage to their neighborhood. They reported that heavy equipment, including an excavator with steel treads, was being driven on a public easement around the subdivision’s pond, tearing up the property. They also voiced worries about damage to area roads from the constant traffic of heavy trucks.

Other safety issues included deep foundation holes being left open with uncapped rebar sticking out, posing a danger to the many small children in the neighborhood.

Village officials and Village Attorney Tim Kuiper listened to the complaints and assured residents the issues would be addressed. Kuiper explained the legal liabilities associated with failing to call for utility locates. Police Chief Terry Lemming advised residents to call the police department immediately if they witness work starting before 7 a.m.

“If they’re operating before 7 a.m., please call the police department. It’s something we can address right away and one ticket will stop them from doing that,” Lemming said.

Board members affirmed they would follow up with Lennar and Safebuilt, the village’s third-party building inspection service, to ensure compliance. “We will absolutely look into it,” said Village President Marcy Meyer. “We’re not looking at having them do things they’re not supposed to do out there.”

Events

No events

Leave a Comment





Latest News Stories

will county board

Will County Health Department Faces Funding Uncertainty as Federal Grants Under Review

Multiple revenue sources threatened as department seeks legislative support for public health programs Will County Health Department officials are closely monitoring potential federal funding cuts that could impact multiple programs...

Will County Land Use Meeting Briefs

LAND USE ACTIONS Accessory Dwelling Unit Rules Modified: The committee recommended approval of text amendments allowing accessory dwelling units to exceed current building area limitations in certain circumstances. The changes...
will county board.2

Public Health and Safety Committee Meeting Briefs

Sunny Hill Nursing Home Tour Praised: Committee members who attended the May 9 tour of Sunny Hill Nursing Home praised the facility's condition and operations. Member Raquel Mitchell called it...
Medicaid-logo

Federal Reconciliation Bill Targets Medicaid, SNAP Programs

Will County Legislators Briefed on Potential Local Impacts Federal legislation making sweeping cuts to Medicaid and food assistance programs could significantly impact Will County residents and services, county legislators learned...
will county board.2

Will County Approves Modified $756 Million Transportation Plan Despite Terminology Debate

Will County's Public Works and Transportation Committee approved a five-year, $756 million transportation improvement plan on June 3, but not before a heated debate over whether to call it a...
will county board.3

Will County completes major projects while others move forward

Will County's facilities team has completed several major projects while advancing others throughout the county, officials reported during a Capital Improvements & IT Committee meeting Monday. The Old Courthouse Plaza...
will county board.3

Will County Accepts $140,000 Developer Donation for Road Improvements

Will County's Public Works and Transportation Committee accepted a $140,143.90 donation from a developer in lieu of constructing traffic improvements along Laraway Road. The donation comes from the Lakes Park...
will county board.2

State Legislative Session Wrap-Up Shows Mixed Results

Will County's state legislative priorities saw mixed results as the Illinois General Assembly concluded its spring session on May 31, with several key bills advancing while others stalled. The Legislative...
will county board.2

Will County expands safety initiatives across facilities

Will County has implemented new safety protocols and training programs across its facilities, including the selection of department safety monitors and participation in community health education events. Each county department...
will county board.3

Leglislative Committee Meeting Briefs

Federal Grant Deadline Extended: The Surface Transportation Reauthorization deadline has been extended to May 30 for policy submissions, with both House and Senate committees actively seeking stakeholder input ahead of...
will county board.3

Speed Limits Reduced on Two Township Roads

The committee approved new speed zones for two township roads based on engineering studies showing current limits exceed safe driving speeds. Offner Road in Green Garden Township will have a...
will county board.2

Will County Finance Committee Approves Juvenile Detention Center Upgrades

Committee votes to keep facility operational, moves forward with compliance modifications Will County Finance Committee members voted unanimously Monday to recommend keeping the River Valley Detention Center operational and making...
will county board.2

Major Grade Separation Projects Advance with Engineering Contracts

The committee approved two significant engineering agreements for major railroad overpass projects totaling over $4 million. TranSystems Corporation received a $4,003,256 contract for construction engineering services on the Lorenzo Road...
County Board Room

County Authorizes Condemnation for Francis Road Project

The committee authorized the State's Attorney's Office to proceed with condemnation cases for right-of-way acquisition needed for Francis Road improvements between Gougar Road and Interstate 80. Eight property parcels are...
will county board

Solar Farm Access Approved for Manhattan-Arsenal Road

The committee granted access approval for a solar farm development on Manhattan-Arsenal Road approximately 1,000 feet east of Cherry Hill Road. The MCH Solar 1 project, developed by Soltage LLC,...