Will County Awards $1.46 Million Contract for Kankakee Street Bridge Replacement in Manhattan Township

Article Summary
The Will County Board has awarded a $1.46 million contract to “D” Construction, Inc. of Coal City to replace the Kankakee Street Bridge over Jackson Creek in Manhattan Township. The project, set to begin in spring 2026, will require a full road closure and a posted detour during construction.

Manhattan Bridge Replacement Key Points:

  • Contractor: “D” Construction, Inc. was the low bidder for the project.

  • Project Cost: The total contract amount is $1,465,938.49.

  • Scope & Timeline: The project involves complete removal and replacement of the bridge, with construction estimated to run from April 2026 to August 2026.

  • Funding: The construction will be paid for using the Manhattan Road District’s motor fuel tax funds and Will County’s bridge tax funds.

JOLIET, IL – A crucial infrastructure project in Manhattan Township is set to move forward after the Will County Board awarded a nearly $1.5 million contract for the replacement of the Kankakee Street Bridge over Jackson Creek.

On Thursday, the board approved a resolution confirming the award to “D” Construction, Inc. of Coal City, which submitted the lowest bid at $1,465,938.49. The project is being funded through a combination of the Manhattan Road District’s motor fuel tax funds and county bridge tax funds.

The scope of the work is extensive and includes the complete removal of the existing bridge. The new structure will be a single-span, cast-in-place concrete slab bridge. The project also involves constructing new full-depth hot-mix asphalt pavement approaches, aggregate shoulders, guardrails, and stream regrading.

Construction is scheduled to begin in April 2026, with an estimated completion date of August 21, 2026. According to the project summary, the roadway will be closed to all traffic during construction, and a posted detour route will be implemented to guide drivers around the work zone. The Public Works and Transportation Committee recommended the contract award earlier this month before it received final approval from the full County Board.

Events

No events

Leave a Comment





Latest News Stories

will county board.2

Will County expands safety initiatives across facilities

Will County has implemented new safety protocols and training programs across its facilities, including the selection of department safety monitors and participation in community health education events. Each county department...
will county board.3

Leglislative Committee Meeting Briefs

Federal Grant Deadline Extended: The Surface Transportation Reauthorization deadline has been extended to May 30 for policy submissions, with both House and Senate committees actively seeking stakeholder input ahead of...
will county board.3

Speed Limits Reduced on Two Township Roads

The committee approved new speed zones for two township roads based on engineering studies showing current limits exceed safe driving speeds. Offner Road in Green Garden Township will have a...
will county board.2

Will County Finance Committee Approves Juvenile Detention Center Upgrades

Committee votes to keep facility operational, moves forward with compliance modifications Will County Finance Committee members voted unanimously Monday to recommend keeping the River Valley Detention Center operational and making...
will county board.2

Major Grade Separation Projects Advance with Engineering Contracts

The committee approved two significant engineering agreements for major railroad overpass projects totaling over $4 million. TranSystems Corporation received a $4,003,256 contract for construction engineering services on the Lorenzo Road...
County Board Room

County Authorizes Condemnation for Francis Road Project

The committee authorized the State's Attorney's Office to proceed with condemnation cases for right-of-way acquisition needed for Francis Road improvements between Gougar Road and Interstate 80. Eight property parcels are...
will county board

Solar Farm Access Approved for Manhattan-Arsenal Road

The committee granted access approval for a solar farm development on Manhattan-Arsenal Road approximately 1,000 feet east of Cherry Hill Road. The MCH Solar 1 project, developed by Soltage LLC,...
will county board.3

Will County Finance Committee Meeting Briefs

Budget Transfers Approved: The Finance Committee approved transferring $18,643 within the Supervisor of Assessments budget to move funds from software licensing to computer hardware purchases. Animal Protection Services Funding: Committee...
will county board.2

Public Works Committee Briefs

Major Projects Update: Construction continues on several major projects including the 80th Avenue expressway overpass, Laraway Road widening near Cedar Road, and Bell Road improvements. The Bell Road project at...
will county board

Capital Improvements & IT Committee Briefs

Bed donation program: Will County donated old beds from Sunny Hill Nursing Home to Joliet Junior College and Project Cure after the nursing home received all new beds for residents....
washington township graphic.1

Washington Township Approves $13,260 Security Overhaul, Opts for Local Vendor with 24/7 Service

Article Summary: The Washington Township Board of Trustees unanimously approved a $13,260 contract with TK Audio & Visual to comprehensively upgrade the security system at the Township Center. The final...
washington township graphic.2

Washington Township Board Appoints Teresa Peterson to Fill Vacancy

Article Summary: The Washington Township Board of Trustees is once again at full strength after unanimously appointing resident Teresa Peterson to fill a trustee vacancy. Peterson took the Oath of...
washington township graphic.3

Washington Township Board Passes 2025-2026 Town Budget

Article Summary: The Washington Township Board of Trustees gave its final approval to the fiscal year 2025-2026 Town Budget, passing the ordinance with a unanimous 4-0 vote. The action occurred...
Meeting-Briefs

Meeting Summary and Briefs: Washington Township Board of Trustees for June 2, 2025

The Washington Township Board of Trustees approved a major security upgrade for its township center and appointed a new trustee to fill a board vacancy during a busy meeting on...
Meeting-Briefs

Meeting Summary and Briefs: Beecher Fire Protection District Board of Trustees for April 24, 2025

The Beecher Fire Protection District Board of Trustees approved a major investment in firefighter safety during its April 24 meeting, authorizing over $91,000 for the purchase of new turnout gear...