Report: Claims that preserving coal plants will cost $6B based on unlikely assumptions

Report: Claims that preserving coal plants will cost $6B based on unlikely assumptions

Spread the love

A new report released Tuesday by America’s Power challenges environmental organization-sponsored claims circulating that say the Trump administration’s decision to preserve coal power plants will cost ratepayers $3 billion to $6 billion more a year.

America’s Power is a “national trade organization whose sole mission is to advocate at the federal and state levels on behalf of the U.S. coal fleet and its supply chain,” according to its website.

As stated by America’s Power, consulting firm Grid Strategies released a report sponsored by four environmental organizations that claimed recent “orders issued by the Department of Energy (DOE) to keep fossil power plants operating for reliability purposes instead of retiring could cost $3 billion per year and perhaps as much as $6 billion per year by the end of 2028.”

The Grid Strategies report came to such conclusions by a series of extreme and unlikely assumptions, America’s Power said.

For instance, it was assumed that all the 54 fossil power plants that have announced intentions of retiring by 2028 – called “possible retirements” – would in fact retire.

Additionally, it was assumed that 36 fossil power plants that are 60 years old – called “speculative retirements” – would retire in 2028.

Both these “possible” and “speculative” retirements representing almost 66,400 megawatts were assumed to be soon receiving 202(c) orders from the Department of Energy that would extend for a year, bringing Grid Strategies’ report to the estimated cost of $3 billion to $6 billion a year.

A 202(c) order is a temporary order “that require[s] power plants that are needed during an ‘emergency’ to operate until the emergency ends,” according to America’s Power.

America’s Power said in its report that it “seems unlikely” that every possible and speculative retirement “will actually happen within the next three years and that every retiring plant will receive a 202(c) order directing it to continue operating for one year.”

Twenty-five out of the 27 times 202(c) orders have been in effect since 2000 have been for 90 days or less, America’s Power said.

“There are a couple of reasons to be a little skeptical about the large number of retirements assumed by Grid Strategies,” the report said.

“One is that load growth and other factors are driving utilities to reassess their plans to retire fossil power plants,” the report said. “For example, utilities have already deferred the retirement of almost 29,000 MW of coal-fired generation for a number of reasons, including concerns about load growth and reliability.”

Matt Kandrach from Consumer Action for a Strong Economy (CASE) said in a statement after the report’s release that the U.S. needs coal to avoid an energy shortage.

“It’s the height of lunacy when a highly available and affordable energy resource like coal is attacked by the same radical environmental groups who gladly support trillions of dollars in green energy mandates. We’re concerned that the North American Electricity Reliability Corporation – the nation’s reliability watchdog – warned recently that more than half the nation faces the risk of blackouts in the next decade from higher demand. That would be a disaster of astronomical costs to American businesses and consumers that President Trump is helping prevent by strengthening and stabilizing America’s energy resources.”

Another reason to be skeptical of 90 assumed retirements according to America’s Power is that the EPA “is rewriting or repealing a number of regulations that were expected to cause more fossil power plant retirements.”

America’s Power used different “just as plausible” assumptions such as “only half of the possible and speculative retirements actually occur,” “only half of these retirements receive DOE orders,” and “the orders extend for 90 days, not one year,” and came up with different results.

The estimate per year falls between $195 million and $370 million using these assumptions.

For reference, “customer expenditures nationally for electricity total close to $500 billion per year,” according to America’s Power.

“Obviously, no one knows for sure what will happen over the next three years or what the cost of DOE orders might be if they are needed to maintain reliability,” America’s Power’s report said.

The report additionally stated that “one of the main reasons” for the North American Electric Reliability Corporation’s warning that more than half the nation is possibly headed for “inadequate electricity supplies” is due to “the retirement of fossil power plants.”

Leave a Comment





Latest News Stories

WATCH: Chicago mayor warns of budget ‘chaos,’ end-of-life options bill on gov’s desk

WATCH: Chicago mayor warns of budget ‘chaos,’ end-of-life options bill on gov’s desk

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square Editor Greg Bishop provides highlights from...
Judy Ogalla

Ogalla Blasts New State Solar Legislation

Will County Land Use & Development Committee Meeting | December 2025 Article Summary: During a discussion on zoning matters, Will County Board Member Judy Ogalla strongly criticized the passage of...
Will County Board Land Use Committee Graphic.4

Committee Postpones Vote on Brandon Road Fill Operation After Tree Clearing Allegations

Will County Land Use & Development Committee Meeting | December 2025 Article Summary: The Will County Land Use and Development Committee voted to postpone a decision on a proposed clean...
beecher ilinois school board graphic.3

Beecher Schools to Publish Curriculum Maps Online; Board Discusses Future Foreign Language Mandates

Beecher Board of Education Curriculum Committee Meeting | Dec. 2025 Article Summary: The Beecher School District 200-U Curriculum Committee outlined plans to increase transparency by publishing full curriculum maps on...
Meeting Briefs

Meeting Summary and Briefs: Will County Planning and Zoning Commission for December 2, 2025

Will County Planning and Zoning Commission Meeting | December 2, 2025 Overall Meeting SummaryThe Will County Planning and Zoning Commission met on December 2, 2025, to consider a variety of...
Metra

Metra Announces No Fare Hikes; Highlights Bridge Projects in Joliet and Mokena

Will County Committee of the Whole Meeting | December 2025 Article Summary: Metra officials presented a balanced 2026 budget to the Will County Board, confirming that riders will not see...
beecher ilinois school board graphic.3

Committee and Parents Discuss Safety Concerns at Daycare Drop-Offs

Beecher School District Transportation Committee Meeting | Dec. 8, 2025 Article Summary: Discussion at the Beecher Transportation Committee meeting highlighted safety hazards at daycare drop-off points, specifically regarding students running...
Rent collusion suit tossed vs manufactured home community operators

Rent collusion suit tossed vs manufactured home community operators

By Scott Holland | Legal NewslineThe Center Square A federal judge has dismissed, for now, a class action accusing some of the nation’s largest manufactured home community landlords of rent...
Illinois quick hits: Planned vigil opposes physician-assisted suicide; NFIB urges veto of energy bill

Illinois quick hits: Planned vigil opposes physician-assisted suicide; NFIB urges veto of energy bill

By Jim Talamonti | The Center SquareThe Center Square Planned vigil opposes physician-assisted suicide A vigil is planned Thursday afternoon outside the State of Illinois building in Chicago’s West Loop,...
beecher ilinois school board graphic.5

Beecher Transportation Committee: Adjust Daycare Transportation Schedule to Address Overcrowding

Beecher School District Transportation Committee Meeting | Dec. 8, 2025 Article Summary: The Beecher School District 200-U Transportation Committee announced immediate changes to afternoon daycare bussing to alleviate overcrowding. Starting...
Beecher Graphic.3

Beecher Board Approves 2025 Tax Levy with 2% Increase

Village of Beecher Board Meeting | Dec. 8, 2025 Article Summary: The Village of Beecher Board of Trustees approved a 2025 tax levy featuring a 2% increase to address rising...
OLYMPUS DIGITAL CAMERA

Library Temporarily Increases Book Budget Following Distributor Closure

Beecher Public Library District Meeting | October 2025 Article Summary: The Beecher Public Library District Board voted to increase its book purchasing budget for two months after receiving a report...

Public Works Committee: Will County Consolidates Paratransit Services Amid Funding Debates

Public Works & Transportation Committee Meeting | December 2, 2025 Article Summary: The Will County Board’s Public Works Committee advanced an agreement to consolidate paratransit services into a single countywide...
Will County P&Z Logo Planning Zoning

P&Z Commission: Peotone Area Variances Forwarded for Garage and Pole Barn

Will County Planning and Zoning Commission Meeting | December 2, 2025 Article Summary: The Will County Planning and Zoning Commission approved variance requests for two properties in Peotone Township, allowing...
Meeting-Briefs

Meeting Summary and Briefs: Beecher Fire Protection District for October 2025

Beecher Fire Protection District Meeting | October 2025 The Beecher Fire Protection District Board of Trustees convened on Thursday, October 23, 2025, to handle routine business and receive departmental updates....