“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Spread the love

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited “ongoing uncertainty regarding federal renewable energy policy” as a cause for delay. The extension for the Pralle Farms Partnership project on West Kennedy Road pushes its deadline to February 2026.

Peotone Solar Farm Extension Key Points:

  • Project: A commercial solar farm by Pralle Farms Partnership on West Kennedy Road in Peotone Township.

  • Action: The board approved a second 180-day extension for the project’s special use permit, now valid until February 8, 2026.

  • Reason: The developer cited delays related to new federal renewable energy legislation, referred to as the “One Big Beautiful Bill.”

  • Vote: The extension was approved 19-1, with board member Katie Deane-Schlottman voting against the measure.

JOLIET — Citing “ongoing uncertainty regarding federal renewable energy policy,” developers of a commercial solar farm in Peotone Township were granted a second extension on their special use permit by the Will County Board on Thursday.

The project, located on a vacant property on West Kennedy Road and owned by Pralle Farms Partnership, was initially approved on March 16, 2023. Developer Trajectory Energy Partners received its first extension in February 2025.

In a memo to the board’s Land Use and Development Committee, Marguerite Kenny, a county Zoning Administrator, noted that the applicant submitted the second extension request on August 6, 2025. The request “provided a detailed letter further explaining the current federal regulation climate” following the passage of new legislation in July referred to as the “One Big Beautiful Bill.”

A building permit for the solar facility was created on March 7, 2025, but the application is still under review and awaiting required submittals, according to the memo. Special use permits typically expire after two years if construction is not lawfully established.

The board approved the second 180-day extension in a 19-1 vote, with Katie Deane-Schlottman casting the lone dissenting vote. The permit is now valid through February 8, 2026, giving the developers more time to navigate the federal policy landscape and finalize their construction permit.

Leave a Comment





Latest News Stories

Screenshot 2025-05-04 at 3.03.49 PM

County’s First Roundabout Planned for Exchange Street and Beecher Road Intersection

Will County's first roundabout is advancing to the final public meeting phase, with construction tentatively scheduled for 2027. County Engineer Jeff Ronaldson announced that the Department of Transportation will hold...
Screenshot 2025-05-04 at 3.03.49 PM

County Accepts $377,000 Developer Donation for Romeo Road Improvements

The Will County Public Works and Transportation Committee has accepted a $377,000 donation from a developer to fund roadway improvements at the southeast corner of Romeo Road and Weber Road...
Screenshot 2025-05-04 at 3.03.49 PM

Contracts Awarded for LED Signal Upgrades and Guardrail Maintenance

The Will County Public Works and Transportation Committee has approved contracts for two significant infrastructure maintenance projects: LED traffic signal upgrades and guardrail maintenance across the county. A contract for...
Screenshot 2025-05-04 at 3.03.49 PM

BRIEFS: Will County Public Works Projects

County Line Road Resurfacing Contract Awarded: The committee approved a $767,249 contract to Iroquois Paving Corporation for resurfacing County Highway 58 (County Line Road) from N5000 East Road east to...
Screenshot 2025-05-04 at 2.36.35 PM

County Approves Two Solar Energy Projects, Committee Discusses Zoning Challenges

The Will County Land Use and Development Committee approved two commercial solar energy projects Wednesday despite objections from the Village of Manhattan regarding one of the proposals. In a 6-1...
Screenshot 2025-05-04 at 2.36.35 PM

Committee Debates Easing Size Restrictions on Accessory Dwelling Units

Will County's Land Use and Development Committee is considering changes to its accessory dwelling unit (ADU) regulations that could provide more flexibility for homeowners looking to create additional living spaces...
Screenshot 2025-05-04 at 2.36.35 PM

“Tiny Homes” Status Creates Regulatory Confusion for County Officials

Will County officials are struggling to establish clear regulations for "tiny homes," with committee members expressing confusion over terminology and appropriate standards during Wednesday's Land Use and Development Committee meeting....
Screenshot 2025-05-04 at 2.36.35 PM

County Officials Begin Exploring Regulations for Small Modular Nuclear Reactors

Will County is beginning to explore potential regulations for small modular nuclear reactors (SMRs) after recent Illinois legislation allowed their development, planning staff told the Land Use and Development Committee...
Screenshot 2025-05-04 at 2.17.47 PM

Will County Land Use News Briefs

Truck Terminal Proposal Tabled for Traffic Study: The committee tabled a special use permit request from Litmax Multi-Service Inc. for a truck terminal in New Lenox Township at 22645 Cherry...
Screenshot 2025-05-04 at 2.57.14 PM

County Moves Forward with Veterans Building Renovations, Questions Arise on Pace Building Plans

Will County's Capital Improvements Committee received updates Tuesday on multiple county facility projects, including progress on the Copperfield Drive building renovations for veterans services, while discussions revealed questions about the...
Screenshot 2025-05-04 at 2.57.14 PM

County Continues Efforts to Reduce Leased Office Space Footprint

Will County officials reported Tuesday that efforts to consolidate county operations in owned facilities are continuing to reduce the county's leased office space footprint, with further reductions expected when the...
Screenshot 2025-05-04 at 2.57.14 PM

County Reports Significant Cost Savings Through In-House Facility Projects

Will County is achieving substantial cost savings by completing facility improvement projects with in-house staff rather than contracting the work out, according to a presentation to the Capital Improvements Committee...
Screenshot 2025-05-04 at 2.50.36 PM

County Legislative Committee Endorses Electronic Recycling Bill, Reviews Transit Governance

The Will County Legislative Committee voted Thursday to support proposed state legislation that would extend and expand Illinois' electronic recycling program, while also reviewing potential changes to regional transit governance...
Screenshot 2025-05-04 at 2.57.14 PM

Will County Capital Improvements News Briefs

Courthouse Scaffolding Expected to Come Down Soon: Scaffolding on one corner of the Will County Courthouse should be removed within the next two weeks, pending reports from material scientists. "We're...
Screenshot 2025-05-04 at 2.44.33 PM

County Finance Committee Advances Proposal for Elected Official Pay Raises After 20-Year Freeze

The Will County Finance Committee voted Thursday to advance a proposal that would provide the first salary increases for countywide elected officials and county board members in nearly two decades....