Screenshot 2025-10-10 at 11.39.50 AM

Will County’s Gas-to-Energy Plant Reports Nearly $460,000 Net Loss Amid Operational Setbacks

Spread the love

Will County Finance Committee Meeting October 7, 2025

Article Summary: Will County’s Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the fiscal year through August, after a summer plagued by mechanical failures, power outages, and maintenance issues that hampered production. Despite the challenges, officials remain optimistic about closing the financial gap by the end of the fiscal year, pointing to a strong performance in September and the plant’s long-term revenue potential.

RNG Plant Performance Key Points:

  • As of August 31, 2025, the RNG plant reported a net loss of $459,484.52 for the fiscal year.

  • Production in July and August fell below targets due to valve failures, sensor issues, severe storms, and computer errors.

  • Production exceeded targets in June, and a strong rebound in September has officials hopeful of breaking even for the year.

  • The plant is in its third year of repaying a 12-year, $48 million green bond used for its construction.

JOLIET, IL – Will County’s gas-to-energy plant has faced a series of operational challenges this summer, resulting in a net loss of $459,484 as of August 31, according to a report presented to the Finance Committee on Tuesday, October 7, 2025.

Greg Komperda, the RNG Facility Project Manager, detailed a difficult summer for the plant, which converts landfill gas into pipeline-quality natural gas. While production in June exceeded its target, generating over 73,000 Million British Thermal Units (MMBtu), performance dipped significantly in July and August.

In July, the plant produced 68,768 MMBtu against a target of 71,300 MMBtu. August production fell further to 64,446 MMBtu. Komperda attributed the shortfalls to a string of problems, including:

  • Valve failures in the nitrogen removal system, likely caused by moisture in the compressed air supply.

  • A delivery rejection from the pipeline operator due to faulty sensors at the delivery point.

  • Ongoing landfill wellfield maintenance, which temporarily reduced the flow of gas to the plant.

  • Sporadic power outages caused by severe storms in late August.

  • Computer errors in the nitrogen control system that required the manufacturer to reprogram it.

Despite the setbacks, Komperda reported that production rebounded in September to over 69,000 MMBtu. “We are closing in on the gap,” he said. “If we could maintain production at a good level, we have a chance of closing that gap in on our under revenue.”

Board members questioned the operational reliability and long-term financial viability of the project. In response to questions about frequent power outages, officials stated that installing a backup generator system capable of powering the plant was not financially feasible. Similarly, a significant solar array to offset the plant’s high electricity consumption—more than all other county facilities combined—would require 70-80 acres and cost an estimated $28 to $48 million.

Board member Daniel J. Butler highlighted the project’s long-term investment perspective. He confirmed with officials that the plant was financed with a 12-year, $48 million green bond. With three years of payments made, the facility has nine years of debt service remaining.

“After 12 years, we are going to be having generate extra money and it should lessen the tax burden,” Butler said, framing the current challenges within the context of the plant’s projected 35-plus-year lifespan. “Here we are making an investment into the future for the people of Will County.”

Leave a Comment





Latest News Stories

Screenshot 2025-06-16 at 3.26.08 PM

Will County Board Rejects Two Solar Farm Projects After Heated Public Opposition

New Lenox area residents cite safety concerns, property values in opposing commercial solar facilities The Will County Board voted decisively against two proposed commercial solar energy facilities during its May...
will county board.3

County Approves $15 Million Water System Takeover for Southeast Joliet Area

700 homes to receive upgraded service as Joliet takes control of failing sanitary district The Will County Board voted 20-1 to support dissolving the Southeast Joliet Sanitary District and transferring...
will county board

Board Postpones County Purchasing Code Overhaul Amid Union Contractor Debate

Members seek clarification on requirements that could favor unionized businesses The Will County Board postponed action on proposed changes to county purchasing ordinances after members raised concerns about language that...
will county board.2

Animal Permit Hearing Reveals Neighborhood Disputes Over Horses, Roosters in Crete Township

Board postpones decision on Torres family request pending barn variance appeal A contentious hearing over Fernando Torres' request to keep horses on his Crete Township property exposed deep neighborhood divisions...
will county board.3

Transportation Projects Advance as Board Approves Vision Zero, Road Improvements

County adopts traffic safety initiative while funding major infrastructure upgrades The Will County Board approved a comprehensive transportation agenda including adoption of Vision Zero principles and multiple road improvement projects...
County Board Room

Health Department Receives Budget Boost, Sunny Hill Admission Policy Updated

Board approves funding increases and policy changes for county health services The Will County Board approved budget appropriations for the health department and updated admission policies for Sunny Hill Nursing...
Screenshot 2025-06-16 at 3.26.08 PM

Will County Board Meeting Briefs Package

COUNTY APPOINTMENTS Fire Protection District: Board approved county executive appointments to Manhattan Fire Protection District board. Agricultural Committee: Approved appointment to Agricultural Area Committee with Member Judy Ogala abstaining due...
beecher ilinois school board graphic.1

Beecher High School Slated for Over $88,000 in Major Plumbing Repairs

Article Summary: The Beecher Board of Education unanimously approved two separate, significant plumbing projects for the high school totaling over $88,000 during its May 14 meeting. The board awarded both...
beecher ilinois school board graphic.4

Beecher School Board Issues Suspension, Formal Notice to Remedy to Employee

Article Summary: The Beecher Board of Education has taken formal disciplinary action against district employee Jessica Carter, unanimously approving a resolution for an unpaid suspension and a "Third Issuance of...
beecher ilinois school board graphic.12

Dr. Marie Hansel Appointed to Fill Vacancy on Beecher School Board

Article Summary: Dr. Marie Hansel has been appointed to the Beecher Board of Education, filling a vacant seat on the seven-member board. Hansel took the official oath of office during...
beecher ilinois school board graphic.3

Beecher School Board Approves Amended Budget, New Staff Hires

Article Summary: The Beecher Board of Education unanimously approved the Fiscal Year 2025 amended budget following a brief public hearing with no comment from the public. The board also approved...
Meeting-Briefs

Meeting Summary and Briefs: Beecher Board of Education for May 14, 2025

The Beecher Board of Education appointed a new member, approved over $88,000 in major infrastructure repairs for the high school, and took formal disciplinary action against an employee during its...
washington township graphic.1

Washington Township Tables Decision on $11,000+ Security Upgrade, Seeks More Details

Article Summary: The Washington Township Board of Trustees has deferred a decision on a significant security system overhaul, citing the need to clarify key differences between two bids from TK...
washington township graphic.2

Washington Township Approves $2,500 in Sponsorships for Beecher EMS, July 4th Celebration

Article Summary: The Washington Township Board unanimously approved two community sponsorships totaling $2,500, continuing its financial support for the Village of Beecher's Emergency Management Agency (EMA) and the annual 4th...
washington township graphic.3

Washington Township to Continue Annual Senior Breakfast Amid Post-COVID Attendance Changes

Article Summary: Following a discussion about lower-than-historic attendance at its recent Senior Breakfast, the Washington Township Board decided to maintain one breakfast event per year. The board concluded that the...