Will County Public Works & Transportation Committee Meeting October 7, 2025

Article Summary: The Will County Public Works & Transportation Committee on Tuesday confirmed the award of a $10.4 million contract to P.T. Ferro Construction Co. for the major reconstruction and widening of a segment of Bell Road. The project, spanning from 151st Street to Martingale Lane, is expected to begin in November 2025 and will include new sidewalks, storm sewers, and modernized traffic signals.

Bell Road Project Key Points:

  • P.T. Ferro Construction Co. was the low bidder for the project with a bid of $10,400,058.22.

  • The project involves roadway widening and reconstruction on Bell Road (County Highway 16) from 151st Street to Martingale Lane.

  • Work is scheduled to begin in November 2025 and is estimated to be completed by November 20, 2026.

  • The roadway will remain open during construction with periodic lane closures controlled by flaggers.

JOLIET, IL – A significant road improvement project is set to begin in the Homer Glen area next year after the Will County Public Works & Transportation Committee on Tuesday, October 7, 2025, approved a $10.4 million construction contract.

The committee unanimously confirmed the award to Joliet-based P.T. Ferro Construction Co., which submitted the lowest bid for the reconstruction and widening of Bell Road (County Highway 16) between 151st Street and Martingale Lane. The contract is for $10,400,058.22.

The project is a major undertaking aimed at improving traffic flow and safety along the busy corridor. According to a project summary from the Will County Division of Transportation, the scope of work includes roadway widening and reconstruction with new pavement, installation of sidewalks and storm sewers, and modernization of traffic signals. The project will also involve building a soldier pile retaining wall, new street lighting, and pavement markings.

Construction is slated to begin in November 2025, with an estimated completion date of November 20, 2026. Officials have stated that Bell Road will remain open to traffic throughout the construction period, though drivers should expect periodic lane closures controlled by flaggers.

The contract was awarded following a bid letting on September 17, 2025.

The resolution confirming the contract award will now go to the full Will County Board for final approval at its October 16 meeting. Funding for the improvements will come from a combination of sources, including Motor Fuel Tax, RTA Tax, and County Highway Tax funds.

Events

No events

Leave a Comment





Latest News Stories

Peotone-Committee-8.18.25.1

Facing Budget Crisis, Peotone Committee Questions Athletic Field Project

Committee of the Whole Article Summary: With Peotone School District 207-U on the verge of a financial crisis, board members are questioning the wisdom of moving forward with a long-awaited...
Meeting-Briefs

Committee Summary and Briefs: Peotone Board of Education Committee of the Whole

The Peotone School District 207-U is on a collision course with a major financial crisis, which dominated the Board of Education’s committee meeting on August 18. Facing a projected $4.2...
Soaring utility bills, solar federal tax credit cuts dominate Illinois energy debate

Soaring utility bills, solar federal tax credit cuts dominate Illinois energy debate

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Energy prices and clean energy policy took center stage during a senate energy and public utilities...

Illinois quick hits: Pritzker signs crypto regulations

By Jim Talamonti | The Center SquareThe Center Square Pritzker signs crypto regulations Gov. J.B. Pritzker has signed two laws to regulate cryptocurrency. Senate Bill 1797 requires cryptocurrency companies to...
Trucking industry leader: New law may drive business out of Illinois

Trucking industry leader: New law may drive business out of Illinois

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A trucking industry leader says more businesses may leave Illinois after the signing of Senate Bill 328....
Exec Cmte 8.14.25.3

Executive Committee Considers $12,000 Strategic Planning Initiative with University of St. Francis

Article Summary: The Will County Executive Committee is considering a proposal from the University of St. Francis to lead a six-month, $12,178 strategic planning process. The initiative is aimed at...
Exec Cmte 8.14.25.2

Executive Committee Members Decry Roadside Litter, Call for Action Against Garbage Haulers

Article Summary: Will County Executive Committee members expressed frustration over what they described as a worsening problem of litter blowing from garbage trucks across the county. Members called for better...
Ad Hoc.8.12.25.3

Will County Updates Solid Waste Ordinance, Increases Fines and Reporting to Landfill Committee

Article Summary: The Will County Ad-Hoc Ordinance Review Committee advanced an updated solid waste ordinance that doubles the maximum fine for violations and requires the county auditor's annual report to...
Ad Hoc.8.12.25.2

Citing Liability Concerns, Will County Committee Postpones Vote on Septic System Ordinance

Article Summary: The Will County Ad-Hoc Ordinance Review Committee postponed a vote on updating its sewer and sewage disposal ordinance after a member raised significant concerns about the county's liability...
Ad Hoc.8.12.25.1

Will County Moves to Repeal Obsolete 1972 Fire Hydrant Ordinance

Article Summary: An ordinance from 1972 regulating the placement and specifications of fire hydrants in Will County is set to be repealed after the Ad-Hoc Ordinance Review Committee approved its...
Committee of teh Whole 8.12.25

Will County Board Gets Back to Basics with Robert’s Rules of Order Training

Article Summary: The Will County Board Committee of the Whole received a detailed training session on Robert's Rules of Order from parliamentary expert Matthew Prochaska to clarify procedures for conducting...
Exec Cmte 8.14.25.1

Executive Committee Approves Amended Houbolt Bridge Agreement to Settle Litigation

Article Summary: The Will County Executive Committee has approved an amendment to the Houbolt Road Toll Bridge agreement, formalizing a settlement between the bridge operators and the City of Joliet....
Meeting Briefs

Meeting Summary and Briefs: Will County Board Committee of the Whole for August 12, 2025

The Will County Board’s Committee of the Whole dedicated its August 12 meeting to an in-depth training session on Robert’s Rules of Order, aiming to foster more efficient and orderly...
Meeting Briefs

Meeting Summary and Briefs: Will County Ad-Hoc Ordinance Review Committee for August 12, 2025

The Will County Ad-Hoc Ordinance Review Committee advanced several updated chapters of the county’s public works code during its August 12 meeting, addressing topics from solid waste to waste hauler...
WCO Landfill 8.5.25.1

Will County Receives Detailed Update on Landfill Expansion Investigation

Article Summary: The Will County Landfill Committee received a comprehensive technical update on the site investigation for the planned horizontal expansion of the county landfill, confirming the project remains on...