Will County Public Works & Transportation Committee Meeting October 7, 2025

Article Summary: The Will County Public Works & Transportation Committee on Tuesday confirmed the award of a $10.4 million contract to P.T. Ferro Construction Co. for the major reconstruction and widening of a segment of Bell Road. The project, spanning from 151st Street to Martingale Lane, is expected to begin in November 2025 and will include new sidewalks, storm sewers, and modernized traffic signals.

Bell Road Project Key Points:

  • P.T. Ferro Construction Co. was the low bidder for the project with a bid of $10,400,058.22.

  • The project involves roadway widening and reconstruction on Bell Road (County Highway 16) from 151st Street to Martingale Lane.

  • Work is scheduled to begin in November 2025 and is estimated to be completed by November 20, 2026.

  • The roadway will remain open during construction with periodic lane closures controlled by flaggers.

JOLIET, IL – A significant road improvement project is set to begin in the Homer Glen area next year after the Will County Public Works & Transportation Committee on Tuesday, October 7, 2025, approved a $10.4 million construction contract.

The committee unanimously confirmed the award to Joliet-based P.T. Ferro Construction Co., which submitted the lowest bid for the reconstruction and widening of Bell Road (County Highway 16) between 151st Street and Martingale Lane. The contract is for $10,400,058.22.

The project is a major undertaking aimed at improving traffic flow and safety along the busy corridor. According to a project summary from the Will County Division of Transportation, the scope of work includes roadway widening and reconstruction with new pavement, installation of sidewalks and storm sewers, and modernization of traffic signals. The project will also involve building a soldier pile retaining wall, new street lighting, and pavement markings.

Construction is slated to begin in November 2025, with an estimated completion date of November 20, 2026. Officials have stated that Bell Road will remain open to traffic throughout the construction period, though drivers should expect periodic lane closures controlled by flaggers.

The contract was awarded following a bid letting on September 17, 2025.

The resolution confirming the contract award will now go to the full Will County Board for final approval at its October 16 meeting. Funding for the improvements will come from a combination of sources, including Motor Fuel Tax, RTA Tax, and County Highway Tax funds.

Events

No events

Leave a Comment





Latest News Stories

WCO Landfill 8.5.25.2

Report Finding Few Trucks Littering Sparks Debate on Cleanup Responsibility

Article Summary: A Will County report found that a very small percentage of waste-hauling trucks are the source of litter on roadways near the county landfill, sparking a debate among...
Meeting Briefs

Meeting Summary and Briefs: Will County Landfill Committee for August 7, 2025

The Will County Landfill Committee on Thursday heard a detailed technical update on the ongoing investigation for the county landfill expansion, confirming that the complex project remains on schedule. Consultants...
Ad Hoc.8.12.25.3

Water Well, Waste Hauler Ordinances Updated by Will County Committee

Article Summary: The Will County Ad-Hoc Ordinance Review Committee approved updates to chapters governing water well permits and waste hauler reporting, forwarding them to the Executive Committee for consideration. Changes...
Beecher Graphic.3

Beecher to Draft Ordinances Regulating Scooters and Fishing in Village Ponds

Article Summary: The Beecher Village Board is moving to create new local laws governing the use of electric scooters and fishing in village-owned ponds. Citing safety concerns and resident inquiries,...
Beecher Graphic.4

Beecher’s National Night Out Draws Large Crowd to New Police Station

Article Summary: Beecher's National Night Out was a resounding success, drawing a large and enthusiastic crowd to the new Public Safety Facility for the first time. The August 5 event...
Meeting-Briefs

Meeting Summary and Briefs: Village of Beecher Board of Trustees for July 28 & August 11, 2025

Over its last two meetings, the Beecher Village Board took significant steps on fiscal policy, new local regulations, and community appointments. On July 28, the board unanimously passed an ordinance...
beecher ilinois school board graphic.4

Finance Committee: Beecher Schools Project Balanced Budget, Earmark Funds for Major Projects

Article Summary: The Beecher School District 200-U Finance Committee reviewed a preliminary Fiscal Year 2026 budget that projects a narrow surplus, a significant turnaround from last year's initial deficit forecast....
WCO Finance Aug 5.1

Will County Health Department Seeks $1 Million to Avert ‘Drastic’ Service Cuts from Expiring Grants

ARTICLE SUMMARY: The Will County Health Department is requesting an additional $1 million in county funding for its 2026 budget to prevent the elimination of 11 critical staff positions, warning...
WCO Cap Imp 8.5.1

Will County’s “First-in-Nation” Veterans Center to House Workforce Services, Sparking Debate

ARTICLE SUMMARY: The new Will County Veteran's Assistance & Support Center will also become the home for the county's Workforce Services department, a move officials say will save approximately $250,000 in...
WCO Finance Aug 5.2

Improved Vendor Service Creates $1.2 Million Shortfall in Sheriff’s Medical Budget

ARTICLE SUMMARY: The Will County Sheriff’s Office is facing a more than $1.2 million shortfall in its budget for inmate medical services, a problem officials attribute to an ironic cause:...
WCO P&Z Aug 5.1

Will County Public Works Committee Unveils 25-Year Transportation Plan, Projects $258 Million Gap

ARTICLE SUMMARY: Will County officials have presented "Our Way Forward 2050," a new long-range transportation plan that provides a 25-year vision for infrastructure projects while forecasting a $258 million shortfall in...
WCO Public Safety.4

Will County Animal Protection Services Seeks New Facility Amid “Gaping Wound” of Space Crisis

Article Summary: Will County Animal Protection Services is seeking approval for a new facility, telling a county committee that its current building is critically inadequate for housing animals, leading to...
WCO Cap Imp 8.5.2

Board Confronts Animal Services Crowding, Explores Future Facility Options

ARTICLE SUMMARY: Will County officials are grappling with an ongoing animal housing crisis that has overwhelmed the county’s Animal Protective Services facility, prompting discussions about expansion, new construction, or even repurposing...
WCO Finance Aug 5.3

Will County Board Members Demand Transparency in Cannabis Tax Fund Allocation

ARTICLE SUMMARY: A debate over transparency and process erupted at the Will County Board’s Finance Committee meeting regarding the distribution of local cannabis tax revenue. Board members called for more...
WCO P&Z Aug 5.2

Homer Glenn Residents Push Back on 143rd Street Widening as Officials Signal “Tentative Agreement”

ARTICLE SUMMARY: A Homer Glenn farm owner voiced strong opposition to the planned widening of 143rd Street during a county meeting, while committee members indicated a "tentative agreement" is in the...