Estimated power demand will outstrip supply by 2032

Estimated power demand will outstrip supply by 2032

Spread the love

(The Center Square) – The impact on electricity demand from a growing number of data centers is a recurring point of concern among energy leaders who warn that, without swift policy reform, unchecked growth could drive up costs and threaten reliability.

A recent briefing hosted by nonprofit consumer watchdog Citizens Utility Board of Illinois, or CUB, explored the issues facing the PJM region.

Panelists from CUB and the Natural Resources Defense Council, or NRDC, suggested potential solutions that would protect consumers and acknowledged an urgent need for coordinated action, they say, to contain costs and safeguard reliability.

CUB’s Jim Chillsen noted that consumers are often unaware their electric bills include capacity charges – payments that cover the power they use, but also the cost of maintaining extra generation for times of peak demand.

He highlighted that after years of flat consumption demand, PJM estimates that by 2031 data centers could add 22-30 GW of new demand, or enough electricity for more than 10 million homes, while expecting only 6-12 GW of new supply, or enough to power as many as 2.6 million homes. This imbalance, he said, has led to record-high capacity prices for which consumers will be paying for through at least May 2027 – something the panelists fear will become a “new normal.”

Without reforms, the NRDC estimates cumulative capacity costs could reach $163 billion from 2027 through 2033.

Claire Lang-Ree, NRDC clean energy advocate, stated that average utility bills have already increased by $20-$30 due to the price increase in the grid’s last auction, and it will get worse through the coming decade if nothing is done. “We’re estimating that average bills could increase by another $70 per month,” she added.

Panelists found fault with PJM’s Critical Issue Fast Path, or CIFP – an initiative launched in August to fast-track discussions and policy decisions aimed at managing rapid growth of large load customers like data centers.

The current proposal, they say, does not require data centers to reduce energy consumption during peak demand; rather, it is voluntary, which increases the risk of rolling blackouts.

They were also critical of the proposed 10-month fast track for new data center-related resources that would allow them to jump ahead in the interconnection queue, which is dominated by clean energy projects – some that have been waiting years for approval.

A better approach stressed Clara Summers, CUB’s Consumers for a Better Grid campaign manager, would require data centers to cover their own costs and bring their own capacity.

Lang-Ree added that by removing large loads out of the capacity market until they bring their own supply may bring capacity prices back down to historic levels of around $60 billion versus the $163 billion projected.

Other measures proposed include implementation of reforms such as separate tariffs, the need for accurate load forecasting, and incentives for new, fast-to-build, clean energy supply.

Stressing that accurate load forecasting is essential to controlling costs and maintaining reliability, she warned that many projects never get built, but their projected demand is used in pricing – driving up capacity pricing for everyone.

By requiring stricter standards such as financial commitments and proof of constructability from developers, consumers won’t be forced to pay for power that is never used, she said.

Summers also highlighted that battery storage is the fastest source to build. Citing analysis by Brattle, she said battery storage can be built in about 20 months or less, as opposed to a gas fired power plant which could take 44 to 50 months. She added that the batteries can store power from today’s resource mix to handle peak capacity needs and are just as reliable as a new gas plant.

Governors of PJM states are among the grid operator’s critics. They recently attended a summit convened by Gov. Josh Shapiro to discuss reforms and having a larger voice in PJM’s governance.

According to PJM, as of August, a total of 46,000 MW of new generation has signed interconnection agreements and are ready to construct, which once operational, could supply as many as 46 million homes. Many of the projects, however, are hampered by factors outside of their control – such as siting and permitting challenges, supply chain backlogs, and financial dynamics.

PJM’s stakeholders are scheduled to vote on a final proposal regarding the allocation of costs for new electric infrastructure on November 19.

Leave a Comment





Latest News Stories

Beecher Softball ladycats

Beecher Varsity Softball Powers Past Sterling 12-1 Behind Johnson’s Two-Hitter

Sophomore Allie Johnson pitched a complete-game two-hitter, and the Beecher offense erupted for 11 hits to secure a commanding 12-1 non-conference victory over host Sterling in a five-inning matchup on...
Beecher Softball ladycats

Norkus Shines as Beecher Varsity Softball Blanks Harvard 9-0

Senior Taylor Norkus struck out 13 batters over six scoreless innings to lead the Beecher varsity softball team to a commanding 9-0 non-conference victory on the road against Harvard on...
Generic Track & Field Graphic

Dwight Sweeps Team Titles at St. Anne Invitational

The Dwight High School track and field program delivered a commanding all-around performance on Friday, April 10, sweeping both the boys' and girls' team titles at the 2026 St. Anne...
Beecher Baseball Bobcats

Massive Eight-Run Second Inning Propels Seneca Past Beecher

Seneca used a massive eight-run outburst in the bottom of the second inning to hold off Beecher 8-6 in a wild, defensively sloppy Friday non-conference matchup. Despite committing six errors...
—Photo courtesy of Laurie Lasseter

Fish fight: action-packed eagle pic wins March photo contest

Laurie Lasseter of Woodridge snapped a photo of an eagle and herring gull locked in battle recently, and the shot was picked as the March winner in the District's Preserve...
Police Crime

Illinois State Police Investigating Fatal Officer-Involved Shooting in Bradley

Article Summary: The Illinois State Police is investigating a fatal officer-involved shooting that occurred after Bradley Police officers encountered an armed man during a mid-day well-being check. Bradley Officer-Involved Shooting...
Monee Car Fire

Fire Department Responds to Monee Car Fire

Monee firefighters responded to a car fire on Manhattan-Monee Road April 10th. No injuries were reported.
NL Fire

New Lenox Firefighters Extinguish Garage Fire, Rescue Pets on Somerset Court

Article Summary: The New Lenox Fire Protection District quickly contained a Friday morning garage fire on Somerset Court, preventing the blaze from spreading to the home's main living area and...
WCO-Capital Improvements & IT Apr 07 214

Will County Explores Multi-Million Dollar Downtown Joliet Consolidation and City Partnership

Will County Capital Improvements & IT Committee Meeting | April 7, 2026 Article Summary: The Will County Capital Improvements and IT Committee reviewed four sweeping architectural options to consolidate county...
will county board meeting.6

Will County Partners with LNS Development for Laraway Road Drainage Improvements in New Lenox

Will County Public Works & Transportation Committee Meeting | April 7, 2026 Article Summary: The county approved a cost-sharing agreement with a private developer to build shared stormwater management facilities...
Will County Board Graphic.03

Will County Hires LEAP HR Consulting for $12,000 Strategic Plan

Will County Board Meeting | March 19, 2026 Article Summary: Seeking to unify its vision and improve onboarding for new members, the Will County Board will launch a four-month strategic...
Will County Finance Logo

Will County Finalizes 2025 Tax Levy at $159.5 Million, Limiting Rate Drops

Briefs: Will County Board Finance Committee Meeting | April 7, 2026 Article Summary: The Will County Finance Committee reviewed the final 2025 tax levy extension numbers, which came in slightly...
Will County Board Graphic.02

Will County to Take Jurisdiction of Countyline Road Following $1.8 Million Agreement with Kankakee County

Will County Public Works & Transportation Committee Meeting | April 7, 2026 Article Summary: Will County will absorb a 4.27-mile stretch of Countyline Road into its highway system, aided by...
will county board meeting.6

Will County Expands Narcan Distribution Amid Shifts in Opioid Overdose Demographics

Will County Public Health & Safety Committee Meeting | April 2, 2026 Article Summary: The Will County Health Department is ramping up its opioid overdose prevention efforts by distributing more...
Police Crime

Additional Skeletal Remains Discovered at Mokena Property

Article Summary: Law enforcement officials have secured a property in Mokena for an extended search after a secondary sweep of the area revealed additional skeletal remains near the site where...