Will County Committee Grants Extensions for Crete, Washington Township Solar Projects

Spread the love

Will County Land Use & Development Committee Meeting | November 6, 2025

Article Summary: The Will County Land Use and Development Committee granted 180-day extensions for two commercial solar energy projects in Crete and Washington Townships, giving the developer additional time to complete the necessary permitting before their initial approvals expire.

Solar Farm Permit Extensions Key Points:

  • A first extension was approved for a TPE Development affiliated project in Crete Township (ZC-23-108), pushing its deadline to June 19, 2026.

  • A first extension was also granted for a related TPE project in Washington Township (ZC-24-020), moving its deadline to November 12, 2026.

  • The extensions were requested to allow more time to complete complex permitting and pre-construction processes.

  • Special use permits for solar facilities in Will County typically expire after two years if construction has not legally commenced.

JOLIET, IL — Two large-scale solar energy projects in eastern Will County were granted more time to get off the ground after the Will County Land Use and Development Committee on Thursday, November 6, 2025, approved their first 180-day permit extensions.

The committee unanimously approved the requests for projects in Crete and Washington townships, both associated with TPE Development, LLC. The extensions are necessary because the special use permits approved by the County Board are set to expire within the next year, and the projects have not yet completed the building permit process to legally establish the use.

The first extension was for case SEXT-25-019, concerning a commercial solar facility at the southeast corner of South Nacke Road and West Loves Lane in Crete Township. Originally approved on December 21, 2023, the permit was set to expire in December 2025. The applicant has applied for a building permit but cited needing more time to complete the process. The extension is now valid through June 19, 2026.

The second approval was for case SEXT-25-020, for a solar facility at the southeast corner of West Indiana Avenue and South Western Avenue in Washington Township, near Beecher. This project was approved on May 16, 2024, and its permit was set to expire in May 2026. According to county staff, the applicant has not yet applied for a building permit. The extension pushes the new expiration date to November 12, 2026.

Under the Will County Zoning Ordinance, a special use permit lapses after two years if the use has not been legally established. The ordinance allows the County Board to grant up to four separate 180-day extensions for “good cause.” Jordan Belknap, representing the applicant, stated they have been working with local authorities, including University Park, on necessary road improvements for the Crete project before construction can begin.

Events

No events

Leave a Comment





Latest News Stories

Meeting-Briefs

Meeting Summary and Briefs: Beecher Fire Protection District for August 28, 2025

Beecher Fire Protection District Meeting | August 28, 2025 The Beecher Fire Protection District Board of Trustees took a significant step toward a potential renewable energy project on Thursday, August...
Beecher Fire Protection District graphic.3

Beecher Fire District Pledges $2,000 to Local Emergency Management Agency

Beecher Fire Protection District Meeting | August 28, 2025 Article Summary: The Beecher Fire Protection District Board of Trustees voted to provide $2,000 in financial support to the Beecher Emergency Management...
Beecher Fire Protection District graphic.1

Beecher Fire District to Reduce Contracted Paramedic Staffing

Beecher Fire Protection District Meeting | August 28, 2025 Article Summary: The Beecher Fire Protection District Board of Trustees has approved an amendment to its contract with Metro Paramedic Services, reducing...
Beecher Fire Protection District graphic.4

Beecher Fire District Explores Solar Farm Partnership with Letter of Intent

Beecher Fire Protection District Meeting | August 28, 2025 Article Summary: The Beecher Fire Protection District is exploring a potential partnership for a commercial solar energy facility after its Board of...
Meeting Briefs

Meeting Summary and Briefs: Washington Township Board of Trustees for August 4, 2025

The Washington Township Board of Trustees focused on employee compensation and infrastructure needs during its August 4 meeting, approving a comprehensive overhaul of its wage structure and job descriptions. The...
washington township graphic.2

Washington Township Board Backs Special Use Permit for Barn on Corning Road

Article Summary: The Washington Township Board of Trustees will support a resident's request for a Special Use Permit to construct a barn on a 5-acre property on E. Corning Road....
Meeting Briefs

Meeting Summary and Briefs: Beecher Public Library District Board for August 19, 2025

The Beecher Public Library District Board of Trustees addressed major financial milestones and a significant leadership change at its August 19 meeting. The board unanimously approved the final budget for...
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...
diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
washington township graphic.3

Failed Repair Forces Replacement of 25-Year-Old Furnace at Washington Township Center

Article Summary: A failed repair attempt on the 25-year-old furnace at the Washington Township Center, which caused a fire alarm to activate, has prompted the board to authorize a full...
OLYMPUS DIGITAL CAMERA

Beecher Library Board Approves Budgets for Current and Upcoming Fiscal Years

Article Summary: The Beecher Public Library District Board of Trustees formally approved its final budget for the current 2024-2025 fiscal year and, following a public hearing, passed the new budget...
Meeting Briefs

Meeting Summary and Briefs: Beecher School District 200-U for September 10, 2025

The Beecher School District 200-U Board of Education approved its annual budget, appointed a new member, and greenlit a cosmetic upgrade for the high school during its meeting on September...