'Ghost projects' haunt power grid planners and taxpayers

‘Ghost projects’ haunt power grid planners and taxpayers

Spread the love

(The Center Square) – As the country braces for a surge in electricity demand driven by large energy users like data centers, two questions lie at the center of the debate over the grid’s future: can it remain reliable and who will pay for it?

Utility experts warn that rising load forecasts are colliding with projected supply shortfalls. And, while PJM works to finalize new rules for connecting large load customers to the grid, some state officials, consumer advocates, and industry groups are zeroing in on the affordability piece of the puzzle.

Accurate load forecasting is essential in meeting rising demand without wasting capital on infrastructure that may never be used, and it affects everything – from keeping the lights on to the prices customers pay each month.

“Ghost projects” are a big part of the issues that are creating uncertainty, Todd Snitchler, president and CEO of the Electric Power Supply Association, or EPSA, told The Center Square.

A ghost project is a generation or transmission project that is announced or funded but never gets built.

Snitchler said gigawatts of new demand are being reported to the system, but there are duplications. Data center developers and hyperscalers routinely scout multiple locations at once, so the same potential project gets counted several times, artificially inflating the load forecast – leading to the risk of overbuilding, stranded costs, or unnecessary spending.

According to Snitchler, there are utilities pointing to these numbers to justify getting back into the business of rate-based generation, claiming they can deliver new plants faster and more cheaply, and with no impact on customers.

None of this can be true, he added, “because they’re subject to the same pressures we are as independent power producers.” And under their business model, they recover their costs plus a reasonable rate of return through a non-bypassable charge paid by customers.

Some states, he said, are tightening their tariffs to include only credible, large-load projects in forecasts. When AEP Ohio applied its new tariff, its projected growth over five years dropped from 30 GW to 13 GW – a 60% reduction. The former is equivalent to powering 26 million homes, while the latter is enough for 1.1 million.

“That suggests to me,” he said, “they can’t be alone in experiencing that.”

He noted that the load forecast for most Pennsylvania utilities was surprisingly flat, with others having only 1-1.5% annual growth, while PPL’s amounted to a 200% increase over 10 years. Something he says is wildly out of step with their peer utilities and raises questions about how thoroughly they are vetting projects, and how many are real.

He argued that overstated demand forecasts suggest developers need to build like crazy, justifying the utilities’ preference to get back into the rate-based generation business – and forcing customers to pay for new power plants instead of relying on the competitive market.

In these cases, Snitchler questions whether the projects are real, or simply advocacy tools designed to help publicly traded utilities grow their rate base and boost shareholder returns, as opposed to competitive developers who invest their own capital and bear the risk themselves.

His concern is that in addition to not having the best answer, there’s an incentive to have the wrong answer, because that helps advance policy objectives that may be better for some organizations, but are intentionally harmful to others.

The bottom line, EPSA says, is that realistic, data-driven planning ensures reliability for the 67 million customers in the PJM region. The solution to meeting demand is continued investment through competitive electricity markets in new and existing power generation, guided by disciplined, transparent forecasting that reflects the projects most likely to materialize.

“There is no silver bullet for this – and I’m not even convinced there’s silver buckshot. Because there’s so much happening that needs coordination for us to deliver and do our best, to ensure a reliable, affordable, and growing system,” Snitchler said. “I think everyone is aiming in the right direction, and we’d do a little better if we bickered less and cooperated more. But it doesn’t feel like where we are at the moment.”

“PJM is doing everything within our authority to reform our processes so they reflect load growth that is likely to occur, not just speculative activity,” Jeffrey Shields, PJM spokesperson, told The Center Square via email.

He said the potential for duplicative requests is one issue they are addressing with their stakeholders in the Critical Information Fast Path process for Large Load Additions, which will conclude on Nov. 19 with a recommendation to the PJM Board of Managers. The CIFP process was initiated by the Board in August to explore ways to continue to connect large loads to the system quickly and reliably without risking electricity shortages.

As part of the CIFP discussions, they are recommending several improvements to the load forecasting process, building on existing enhancements that incorporate large load adjustments into the long-term forecast. They have also standardized the system that load-serving entities use to request large load additions, to include evidence of binding commitments that facilities will be built.

PJM has also recommended a specific review process involving the states and utilities that operate within their borders; those states and their utilities also have authority to set rates and require commitments from data centers and other “large load” customers.

A summary of their proposal to deal with the issue will be considered along with 11 others.

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Will County Board Executive Committee for December 11, 2025

Will County Board Executive Committee Meeting | December 11, 2025 Overall Meeting SummaryThe Will County Board Executive Committee met on Thursday, December 11, 2025, tackling a diverse agenda that included...
Beecher Graphic.3

Residents Lodge Complaints Regarding Truck Noise

Beecher Village Board Meeting | December 22, 2025 Article Summary: Residents from the Charity Point Townhomes voiced concerns to the Village Board regarding excessive noise and fumes from refrigerated semi-trucks...
Planning & Zoning Graphic.4

New Lenox Homeowner Granted Variance for 4,000-Square-Foot Accessory Space

Will County Planning and Zoning Commission Meeting | December 16, 2025 Article Summary: A New Lenox homeowner received approval to build a large pole barn that exceeds the county's size limits...
Will County Board Graphic.03

County Expands Paratransit Services, Board Members Question Long-Term Funding

Will County Board Meeting | December 18, 2025 Article Summary: The Will County Board approved an intergovernmental agreement with Pace to expand paratransit services county-wide for seniors and residents with...
Beecher Graphic.1

Village Approves Agreement with Solar Energy Company

Beecher Village Board Meeting | December 22, 2025 Article Summary: The Beecher Village Board approved a Community Benefit Agreement with a solar energy developer that includes a $100,000 donation to...
Will County Board Graphic.02

Mental Health Board Updates Committee on 2026 Grant Cycle and Funding Priorities

Will County Board Executive Committee Meeting | December 11, 2025 Article Summary: The Will County Community Mental Health Board provided a quarterly update, outlining the timeline and strategic priorities for...
Beecher Police released images of the suspect-photo courtesy the Beecher Police Department.

Beecher Police Investigate Attempted Armed Robbery, Seek Public’s Help

BEECHER, Ill. — Beecher police are investigating an attempted armed robbery reported Friday evening at Silver Screen Vapes and are asking residents to review security camera footage that may help...
Will County P&Z Logo Planning Zoning

PZC Approves Homer Township Landscape Business Despite Neighbor Concerns; Adds Berm Condition

Will County Planning and Zoning Commission Meeting | December 16, 2025 Article Summary: The Will County Planning and Zoning Commission approved a special use permit for a new landscape business on...
Chicago council, 'starting to legislate,' sends $16.7 billion budget to mayor

Chicago council, ‘starting to legislate,’ sends $16.7 billion budget to mayor

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The Chicago City Council has approved a $16.7 billion budget for 2026 and sent it to Mayor...
Hegseth promises to fix barracks, but work could take time

Hegseth promises to fix barracks, but work could take time

By Brett RowlandThe Center Square Secretary of War Pete Hegseth has pledged to tackle longstanding issues with U.S. military barracks that have frustrated troops, lawmakers, and taxpayers for decades. In...
‘Long overdue’: Praise for HHS’ action to bar taxpayer-funded sex-change procedures

‘Long overdue’: Praise for HHS’ action to bar taxpayer-funded sex-change procedures

By Tate MillerThe Center Square The U.S. Department of Health and Human Services’ action to bar “sex-rejecting” transgender procedures for minors has met with approval from groups that aim to...
Gas prices drop, but taxes make Illinois pricier than Midwest neighbors

Gas prices drop, but taxes make Illinois pricier than Midwest neighbors

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Although Illinois drivers are now paying less at the pump, a state lawmaker says prices would be...
Fire Graduates

Recruit Firefighters Jace Cook and Braeden Waterman Graduate

Jace and Braeden graduated from the Romeoville Fire Academy on December 12th, successfully completing nine weeks of rigorous physical and mental training, setting a sound foundation of skills in our...
Will County Board Graphic.04

Liquor License Amendments Approved for Frankfort, Joliet, and Lockport Businesses

Will County Board Executive Committee Meeting | December 11, 2025 Article Summary: The Executive Committee approved amendments to the County’s Liquor Control Ordinance to increase the number of available licenses,...
Planning & Zoning Graphic.3

Meeting Summary and Briefs: Will County Planning and Zoning Commission for December 16, 2025

Will County Planning and Zoning Commission Meeting | December 16, 2025 Overall Meeting SummaryThe Will County Planning and Zoning Commission navigated attendance issues during its December 16, 2025, meeting, beginning...