'Ghost projects' haunt power grid planners and taxpayers

‘Ghost projects’ haunt power grid planners and taxpayers

Spread the love

(The Center Square) – As the country braces for a surge in electricity demand driven by large energy users like data centers, two questions lie at the center of the debate over the grid’s future: can it remain reliable and who will pay for it?

Utility experts warn that rising load forecasts are colliding with projected supply shortfalls. And, while PJM works to finalize new rules for connecting large load customers to the grid, some state officials, consumer advocates, and industry groups are zeroing in on the affordability piece of the puzzle.

Accurate load forecasting is essential in meeting rising demand without wasting capital on infrastructure that may never be used, and it affects everything – from keeping the lights on to the prices customers pay each month.

“Ghost projects” are a big part of the issues that are creating uncertainty, Todd Snitchler, president and CEO of the Electric Power Supply Association, or EPSA, told The Center Square.

A ghost project is a generation or transmission project that is announced or funded but never gets built.

Snitchler said gigawatts of new demand are being reported to the system, but there are duplications. Data center developers and hyperscalers routinely scout multiple locations at once, so the same potential project gets counted several times, artificially inflating the load forecast – leading to the risk of overbuilding, stranded costs, or unnecessary spending.

According to Snitchler, there are utilities pointing to these numbers to justify getting back into the business of rate-based generation, claiming they can deliver new plants faster and more cheaply, and with no impact on customers.

None of this can be true, he added, “because they’re subject to the same pressures we are as independent power producers.” And under their business model, they recover their costs plus a reasonable rate of return through a non-bypassable charge paid by customers.

Some states, he said, are tightening their tariffs to include only credible, large-load projects in forecasts. When AEP Ohio applied its new tariff, its projected growth over five years dropped from 30 GW to 13 GW – a 60% reduction. The former is equivalent to powering 26 million homes, while the latter is enough for 1.1 million.

“That suggests to me,” he said, “they can’t be alone in experiencing that.”

He noted that the load forecast for most Pennsylvania utilities was surprisingly flat, with others having only 1-1.5% annual growth, while PPL’s amounted to a 200% increase over 10 years. Something he says is wildly out of step with their peer utilities and raises questions about how thoroughly they are vetting projects, and how many are real.

He argued that overstated demand forecasts suggest developers need to build like crazy, justifying the utilities’ preference to get back into the rate-based generation business – and forcing customers to pay for new power plants instead of relying on the competitive market.

In these cases, Snitchler questions whether the projects are real, or simply advocacy tools designed to help publicly traded utilities grow their rate base and boost shareholder returns, as opposed to competitive developers who invest their own capital and bear the risk themselves.

His concern is that in addition to not having the best answer, there’s an incentive to have the wrong answer, because that helps advance policy objectives that may be better for some organizations, but are intentionally harmful to others.

The bottom line, EPSA says, is that realistic, data-driven planning ensures reliability for the 67 million customers in the PJM region. The solution to meeting demand is continued investment through competitive electricity markets in new and existing power generation, guided by disciplined, transparent forecasting that reflects the projects most likely to materialize.

“There is no silver bullet for this – and I’m not even convinced there’s silver buckshot. Because there’s so much happening that needs coordination for us to deliver and do our best, to ensure a reliable, affordable, and growing system,” Snitchler said. “I think everyone is aiming in the right direction, and we’d do a little better if we bickered less and cooperated more. But it doesn’t feel like where we are at the moment.”

“PJM is doing everything within our authority to reform our processes so they reflect load growth that is likely to occur, not just speculative activity,” Jeffrey Shields, PJM spokesperson, told The Center Square via email.

He said the potential for duplicative requests is one issue they are addressing with their stakeholders in the Critical Information Fast Path process for Large Load Additions, which will conclude on Nov. 19 with a recommendation to the PJM Board of Managers. The CIFP process was initiated by the Board in August to explore ways to continue to connect large loads to the system quickly and reliably without risking electricity shortages.

As part of the CIFP discussions, they are recommending several improvements to the load forecasting process, building on existing enhancements that incorporate large load adjustments into the long-term forecast. They have also standardized the system that load-serving entities use to request large load additions, to include evidence of binding commitments that facilities will be built.

PJM has also recommended a specific review process involving the states and utilities that operate within their borders; those states and their utilities also have authority to set rates and require commitments from data centers and other “large load” customers.

A summary of their proposal to deal with the issue will be considered along with 11 others.

Events

No events

Leave a Comment





Latest News Stories

Screenshot 2025-10-25 at 10.48.48 AM

New Lenox Solar Farm Proposal Advances with Conditions, Following Village and Forest Preserve Input

Will County Planning and Zoning Commission Meeting | October 21, 2025 Article Summary: The Will County Planning and Zoning Commission recommended approval for a 62.7-acre commercial solar energy facility in...
Meeting Briefs

Meeting Summary and Briefs: Will County Board for October 16, 2025

Will County Board Regular Meeting | October 16, 2025 The Will County Board took major action on property taxes at its meeting on Thursday, October 16, 2025, narrowly voting to...
30 MPH Speed Limit

Will County Board Approves New 30 MPH Speed Limit for Frankfort Township Road

Will County Board Regular Meeting | October 16, 2025 Article Summary: The Will County Board approved a new 30 MPH speed limit for a section of 78th Avenue in Frankfort Township,...
Screenshot 2025-10-25 at 12.42.59 PM

Will County Committee Grapples with $8.9 Million Budget Gap After Contentious 0% Tax Levy Vote

Will County Board Finance Committee Meeting | October 21, 2025 Article Summary: The Will County Board Finance Committee held a contentious debate over how to close an $8.9 million budget shortfall...
Screenshot 2025-10-25 at 10.49.15 AM

Frankfort Township Board Objects, but County Commission Recommends Bar with Video Gaming

Will County Planning and Zoning Commission Meeting | October 21, 2025 Article Summary: Despite a formal objection from the Frankfort Township Board, the Will County Planning and Zoning Commission recommended...
Screenshot 2025-10-25 at 10.49.23 AM

Senior Shared Housing Facility Recommended for Approval in Crete Township

Will County Planning and Zoning Commission Meeting | October 21, 2025 Article Summary: The Will County Planning and Zoning Commission has recommended approval for a special use permit that would...
Screenshot 2025-10-25 at 10.49.32 AM

Crete Township ‘Tiny Home’ Owner Appeals Permit Denial

Will County Planning and Zoning Commission Meeting | October 21, 2025 Article Summary: A Crete Township property owner has appealed to the Will County Planning and Zoning Commission after being...
Will County Finance Logo

Will County Finance Committee Forwards 1.75% Compromise Property Tax Levy to Full Board

Will County Finance Committee Forwards 1.75% Compromise Property Tax Levy to Full Board Article Summary:The Will County Board’s Finance Committee on Tuesday, November 12, 2025, narrowly approved a series of...

WATCH: Trump calls Pritzker a ‘fat slob,’ Illinois governor blasts president

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – President Donald Trump has revived his criticism of Illinois Gov. J.B. Pritzker over crime, and Pritzker has...
Illinois business group warns of 'backbreaking' progressive income tax

Illinois business group warns of ‘backbreaking’ progressive income tax

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – Manufacturers say legislators at the Illinois State Capitol have done enough damage and a progressive tax would...
Illinois tops U.S. in pumpkin production despite recent decline in value

Illinois tops U.S. in pumpkin production despite recent decline in value

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Despite a recent decline in production value, Illinois is far and away the leader when it comes...
Congress moves to restore federal union powers, critics warn of higher costs

Congress moves to restore federal union powers, critics warn of higher costs

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – The U.S. Congress is set to vote on House Resolution 2550, a bill that would restore...
Illinois quick hits: Chiropractor sentenced for fraud; fatal airport shooting investigation

Illinois quick hits: Chiropractor sentenced for fraud; fatal airport shooting investigation

By Jim Talamonti | The Center SquareThe Center Square Chiropractor sentenced for fraud A Chicago chiropractor has been sentenced to nearly six years in federal prison for billing a private...
Will County P&Z Logo Planning Zoning.2

Committee Grants Lenox Solar Farm Project Six-Month Variance Extension

Will County Planning and Zoning Commission Meeting | November 18, 2025 Article Summary:The Will County Planning and Zoning Commission has approved a 180-day extension for variances tied to a commercial...
Will County Logo Graphic

Speed Limits Lowered in Green Garden and Frankfort Neighborhoods

Will County Board Meeting | November 2025 Article Summary: The Will County Board adopted ordinances to establish new, lower speed limits in specific areas of Green Garden and Frankfort Townships....