'Ghost projects' haunt power grid planners and taxpayers

‘Ghost projects’ haunt power grid planners and taxpayers

Spread the love

(The Center Square) – As the country braces for a surge in electricity demand driven by large energy users like data centers, two questions lie at the center of the debate over the grid’s future: can it remain reliable and who will pay for it?

Utility experts warn that rising load forecasts are colliding with projected supply shortfalls. And, while PJM works to finalize new rules for connecting large load customers to the grid, some state officials, consumer advocates, and industry groups are zeroing in on the affordability piece of the puzzle.

Accurate load forecasting is essential in meeting rising demand without wasting capital on infrastructure that may never be used, and it affects everything – from keeping the lights on to the prices customers pay each month.

“Ghost projects” are a big part of the issues that are creating uncertainty, Todd Snitchler, president and CEO of the Electric Power Supply Association, or EPSA, told The Center Square.

A ghost project is a generation or transmission project that is announced or funded but never gets built.

Snitchler said gigawatts of new demand are being reported to the system, but there are duplications. Data center developers and hyperscalers routinely scout multiple locations at once, so the same potential project gets counted several times, artificially inflating the load forecast – leading to the risk of overbuilding, stranded costs, or unnecessary spending.

According to Snitchler, there are utilities pointing to these numbers to justify getting back into the business of rate-based generation, claiming they can deliver new plants faster and more cheaply, and with no impact on customers.

None of this can be true, he added, “because they’re subject to the same pressures we are as independent power producers.” And under their business model, they recover their costs plus a reasonable rate of return through a non-bypassable charge paid by customers.

Some states, he said, are tightening their tariffs to include only credible, large-load projects in forecasts. When AEP Ohio applied its new tariff, its projected growth over five years dropped from 30 GW to 13 GW – a 60% reduction. The former is equivalent to powering 26 million homes, while the latter is enough for 1.1 million.

“That suggests to me,” he said, “they can’t be alone in experiencing that.”

He noted that the load forecast for most Pennsylvania utilities was surprisingly flat, with others having only 1-1.5% annual growth, while PPL’s amounted to a 200% increase over 10 years. Something he says is wildly out of step with their peer utilities and raises questions about how thoroughly they are vetting projects, and how many are real.

He argued that overstated demand forecasts suggest developers need to build like crazy, justifying the utilities’ preference to get back into the rate-based generation business – and forcing customers to pay for new power plants instead of relying on the competitive market.

In these cases, Snitchler questions whether the projects are real, or simply advocacy tools designed to help publicly traded utilities grow their rate base and boost shareholder returns, as opposed to competitive developers who invest their own capital and bear the risk themselves.

His concern is that in addition to not having the best answer, there’s an incentive to have the wrong answer, because that helps advance policy objectives that may be better for some organizations, but are intentionally harmful to others.

The bottom line, EPSA says, is that realistic, data-driven planning ensures reliability for the 67 million customers in the PJM region. The solution to meeting demand is continued investment through competitive electricity markets in new and existing power generation, guided by disciplined, transparent forecasting that reflects the projects most likely to materialize.

“There is no silver bullet for this – and I’m not even convinced there’s silver buckshot. Because there’s so much happening that needs coordination for us to deliver and do our best, to ensure a reliable, affordable, and growing system,” Snitchler said. “I think everyone is aiming in the right direction, and we’d do a little better if we bickered less and cooperated more. But it doesn’t feel like where we are at the moment.”

“PJM is doing everything within our authority to reform our processes so they reflect load growth that is likely to occur, not just speculative activity,” Jeffrey Shields, PJM spokesperson, told The Center Square via email.

He said the potential for duplicative requests is one issue they are addressing with their stakeholders in the Critical Information Fast Path process for Large Load Additions, which will conclude on Nov. 19 with a recommendation to the PJM Board of Managers. The CIFP process was initiated by the Board in August to explore ways to continue to connect large loads to the system quickly and reliably without risking electricity shortages.

As part of the CIFP discussions, they are recommending several improvements to the load forecasting process, building on existing enhancements that incorporate large load adjustments into the long-term forecast. They have also standardized the system that load-serving entities use to request large load additions, to include evidence of binding commitments that facilities will be built.

PJM has also recommended a specific review process involving the states and utilities that operate within their borders; those states and their utilities also have authority to set rates and require commitments from data centers and other “large load” customers.

A summary of their proposal to deal with the issue will be considered along with 11 others.

Events

No events

Leave a Comment





Latest News Stories

Screenshot 2025-05-04 at 2.08.10 PM

Resident Urges County to Restrict Residential Motocross Tracks After Neighborhood Dispute

JOLIET — A Will County resident appeared before the Land Use and Development Committee Thursday urging officials to modify zoning codes to prohibit motocross tracks in residential neighborhoods, citing an...
Screenshot 2025-05-04 at 2.08.10 PM

Committee Approves Truck Terminal Special Use Permit After Safety Modifications

JOLIET — The Will County Land Use and Development Committee voted Thursday to approve a special use permit for a truck terminal in New Lenox Township, after the applicant made...
Screenshot 2025-05-04 at 2.08.10 PM

County Committee Approves Two Solar Energy Projects Despite Farmland Concerns

JOLIET — The Will County Land Use and Development Committee approved two commercial solar energy projects Thursday, advancing the proposals to the full county board for final consideration despite concerns...
Screenshot 2025-05-04 at 3.03.49 PM

Will County Approves Vision Zero Initiative to Reduce Traffic Fatalities

Will County has officially adopted Vision Zero, a data-driven safety initiative aimed at eliminating traffic fatalities throughout the county. The Public Works and Transportation Committee unanimously approved the resolution, which...
Screenshot 2025-05-04 at 3.03.49 PM

County’s First Roundabout Planned for Exchange Street and Beecher Road Intersection

Will County's first roundabout is advancing to the final public meeting phase, with construction tentatively scheduled for 2027. County Engineer Jeff Ronaldson announced that the Department of Transportation will hold...
Screenshot 2025-05-04 at 3.03.49 PM

County Accepts $377,000 Developer Donation for Romeo Road Improvements

The Will County Public Works and Transportation Committee has accepted a $377,000 donation from a developer to fund roadway improvements at the southeast corner of Romeo Road and Weber Road...
Screenshot 2025-05-04 at 3.03.49 PM

Contracts Awarded for LED Signal Upgrades and Guardrail Maintenance

The Will County Public Works and Transportation Committee has approved contracts for two significant infrastructure maintenance projects: LED traffic signal upgrades and guardrail maintenance across the county. A contract for...
Screenshot 2025-05-04 at 3.03.49 PM

BRIEFS: Will County Public Works Projects

County Line Road Resurfacing Contract Awarded: The committee approved a $767,249 contract to Iroquois Paving Corporation for resurfacing County Highway 58 (County Line Road) from N5000 East Road east to...
Screenshot 2025-05-04 at 2.36.35 PM

County Approves Two Solar Energy Projects, Committee Discusses Zoning Challenges

The Will County Land Use and Development Committee approved two commercial solar energy projects Wednesday despite objections from the Village of Manhattan regarding one of the proposals. In a 6-1...
Screenshot 2025-05-04 at 2.36.35 PM

Committee Debates Easing Size Restrictions on Accessory Dwelling Units

Will County's Land Use and Development Committee is considering changes to its accessory dwelling unit (ADU) regulations that could provide more flexibility for homeowners looking to create additional living spaces...
Screenshot 2025-05-04 at 2.36.35 PM

“Tiny Homes” Status Creates Regulatory Confusion for County Officials

Will County officials are struggling to establish clear regulations for "tiny homes," with committee members expressing confusion over terminology and appropriate standards during Wednesday's Land Use and Development Committee meeting....
Screenshot 2025-05-04 at 2.36.35 PM

County Officials Begin Exploring Regulations for Small Modular Nuclear Reactors

Will County is beginning to explore potential regulations for small modular nuclear reactors (SMRs) after recent Illinois legislation allowed their development, planning staff told the Land Use and Development Committee...
Screenshot 2025-05-04 at 2.17.47 PM

Will County Land Use News Briefs

Truck Terminal Proposal Tabled for Traffic Study: The committee tabled a special use permit request from Litmax Multi-Service Inc. for a truck terminal in New Lenox Township at 22645 Cherry...
Screenshot 2025-05-04 at 2.57.14 PM

County Moves Forward with Veterans Building Renovations, Questions Arise on Pace Building Plans

Will County's Capital Improvements Committee received updates Tuesday on multiple county facility projects, including progress on the Copperfield Drive building renovations for veterans services, while discussions revealed questions about the...
Screenshot 2025-05-04 at 2.57.14 PM

County Continues Efforts to Reduce Leased Office Space Footprint

Will County officials reported Tuesday that efforts to consolidate county operations in owned facilities are continuing to reduce the county's leased office space footprint, with further reductions expected when the...