Consensus for power supply solution still elusive

Consensus for power supply solution still elusive

Spread the love

(The Center Square) – Rapid expansion of data centers in the mid-Atlantic region has leaves its power grid’s operator, PJM, standing at a crossroads: how can electricity supply keep up with exponential growth in demand without spiking bills for ratepayers?

After a Wednesday meeting with all of the organizations members – which include utility companies, state regulators, power plants, transmission providers, project developers, and commercial and industrial businesses – there’s still no path forward.

This, despite 12 proposals put forward for a vote. None earned majority support.

“The growth of data centers is colliding with the reality of the power grid,” said Tom Rutigliano, senior advocate for climate and energy at Natural Resources Defense Council. The advocacy group worked with Sen. Katy Fry Hester, D-Md., on one of the rejected plans.

Rutigliano told The Center Square that data centers are showing up and quickly adding cities’ worth of electric demand to the grid. Figuring out how to build power plants quickly enough to meet that demand is a $100 billion question, and reliability is at stake.

He surmises that PJM members ultimately backed proposals that served their own interests, preventing any real solution from advancing and leaving the grid’s board of directors with a hard choice – one he is optimistic will incorporate the best of each plan.

“We hope they fulfill their obligation to the 67 million people in the PJM region and commit to protecting reliability, treat all customers fairly, and not subsidize data centers at public expense,” Rutigliano said.

In addition to grappling with the core issues of reliability and affordability, open access is just as critical, Rutigliano said. It ensures all generators, including clean energy projects, have an equal opportunity to connect to the grid.

He warned that some proposed fast-track processes would heavily favor large fossil fuel plants, creating a permanent two-tier system where fossil fuel “gets a kind of concierge class connect to the grid and clean energy sits in coach.” From where NRDC sits, he added, that would be an unacceptable outcome.

Rutiglio acknowledged that while renewables alone aren’t enough to guarantee grid reliability, strategically combining them with storage and maintaining a diverse energy mix can create a reliable grid.

It is absolutely feasible, he said, to achieve 80-95% renewable integration. And, though the last stretch is the most difficult, it’s nowhere near being a problem – renewables make up single-digit percentages on PJM’s grid.

He said that renewables, combined with energy storage, can be built far faster than new gas turbines; often in 18 to 24 months, compared to years-long turbine waitlists and pipeline delays. Because storage is quicker to deploy and easier to site, he hopes the final policy outcome will encourage tech companies toward large-scale storage solutions. The goal, he added, isn’t to block data centers but to ensure they don’t shift risks onto the public, which is the goal of the “bring your own” proposals.

Roughly one-third of a data center’s cost is the power plant needed to serve it, he stated, and under the current system, taxpayers foot the bill for speculative projects – whether they get built or not – which he suggests is one of the main drivers for “bring your own.”

The voting at the Nov. 19 meeting resulted in none of the 12 proposal packages obtaining a requisite “passing” vote, Jeffrey Shields, PJM spokesman, told The Center Square via email.

“PJM opened this conversation about the integration of large loads and greatly appreciates our stakeholders for their contributions to this effort,” he said. ”The stakeholder process produced many thoughtful proposals, some of which were introduced late in the process and require additional development.”

This vote, Shields said, is advisory to PJM’s independent board, which can and does expect to act on large load additions to the system and will make its decision known in the next few weeks.

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Beecher Public Library District Board for August 19, 2025

The Beecher Public Library District Board of Trustees addressed major financial milestones and a significant leadership change at its August 19 meeting. The board unanimously approved the final budget for...
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...
diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
washington township graphic.3

Failed Repair Forces Replacement of 25-Year-Old Furnace at Washington Township Center

Article Summary: A failed repair attempt on the 25-year-old furnace at the Washington Township Center, which caused a fire alarm to activate, has prompted the board to authorize a full...
OLYMPUS DIGITAL CAMERA

Beecher Library Board Approves Budgets for Current and Upcoming Fiscal Years

Article Summary: The Beecher Public Library District Board of Trustees formally approved its final budget for the current 2024-2025 fiscal year and, following a public hearing, passed the new budget...
Meeting Briefs

Meeting Summary and Briefs: Beecher School District 200-U for September 10, 2025

The Beecher School District 200-U Board of Education approved its annual budget, appointed a new member, and greenlit a cosmetic upgrade for the high school during its meeting on September...
Meeting Briefs

Meeting Summary and Briefs: Village of Beecher Board of Trustees for September 22, 2025

The Beecher Village Board addressed persistent structural issues at the new Public Safety Facility during its meeting on September 22. After a report confirmed that new roof leaks have appeared...
washington township graphic.1

Washington Township Overhauls Wage Structure, Boosts Bus Driver Pay

Article Summary: The Washington Township Board of Trustees has initiated a comprehensive review of its wage and job structures to align with state law, improve competitiveness for key positions like...
beecher illinois public library graphic.1

Beecher Library Board President Shirley Biery Announces Resignation

Article Summary: Shirley Biery has announced she will resign from her position as President and Trustee of the Beecher Public Library District Board, effective August 31, 2025. Following the announcement...
Screenshot 2025-09-23 at 7.57.19 PM

Beecher Creates New Adjudication Clerk Position to Manage Municipal Court

Article Summary: The Village of Beecher has formally created the position of Adjudication Clerk by amending its municipal code, aiming to streamline the management of its local ordinance violation hearings....
Screenshot 2025-09-23 at 8.04.29 PM

Beecher High School to Get New Look with Approved Window Wrap

Article Summary: Beecher High School is set for an aesthetic upgrade after the Board of Education approved a nearly $12,500 proposal for a decorative and security-enhancing window wrap. After some...
Screenshot 2025-09-23 at 7.55.43 PM

State’s Attorney Donates Tint Meters to Beecher Police to Enhance Traffic Safety

Article Summary: The Beecher Police Department has received 14 new window tint meters through a donation from the Will County State's Attorney's Office. State's Attorney Jim Glasgow personally presented the...