Consensus for power supply solution still elusive

Consensus for power supply solution still elusive

Spread the love

(The Center Square) – Rapid expansion of data centers in the mid-Atlantic region has leaves its power grid’s operator, PJM, standing at a crossroads: how can electricity supply keep up with exponential growth in demand without spiking bills for ratepayers?

After a Wednesday meeting with all of the organizations members – which include utility companies, state regulators, power plants, transmission providers, project developers, and commercial and industrial businesses – there’s still no path forward.

This, despite 12 proposals put forward for a vote. None earned majority support.

“The growth of data centers is colliding with the reality of the power grid,” said Tom Rutigliano, senior advocate for climate and energy at Natural Resources Defense Council. The advocacy group worked with Sen. Katy Fry Hester, D-Md., on one of the rejected plans.

Rutigliano told The Center Square that data centers are showing up and quickly adding cities’ worth of electric demand to the grid. Figuring out how to build power plants quickly enough to meet that demand is a $100 billion question, and reliability is at stake.

He surmises that PJM members ultimately backed proposals that served their own interests, preventing any real solution from advancing and leaving the grid’s board of directors with a hard choice – one he is optimistic will incorporate the best of each plan.

“We hope they fulfill their obligation to the 67 million people in the PJM region and commit to protecting reliability, treat all customers fairly, and not subsidize data centers at public expense,” Rutigliano said.

In addition to grappling with the core issues of reliability and affordability, open access is just as critical, Rutigliano said. It ensures all generators, including clean energy projects, have an equal opportunity to connect to the grid.

He warned that some proposed fast-track processes would heavily favor large fossil fuel plants, creating a permanent two-tier system where fossil fuel “gets a kind of concierge class connect to the grid and clean energy sits in coach.” From where NRDC sits, he added, that would be an unacceptable outcome.

Rutiglio acknowledged that while renewables alone aren’t enough to guarantee grid reliability, strategically combining them with storage and maintaining a diverse energy mix can create a reliable grid.

It is absolutely feasible, he said, to achieve 80-95% renewable integration. And, though the last stretch is the most difficult, it’s nowhere near being a problem – renewables make up single-digit percentages on PJM’s grid.

He said that renewables, combined with energy storage, can be built far faster than new gas turbines; often in 18 to 24 months, compared to years-long turbine waitlists and pipeline delays. Because storage is quicker to deploy and easier to site, he hopes the final policy outcome will encourage tech companies toward large-scale storage solutions. The goal, he added, isn’t to block data centers but to ensure they don’t shift risks onto the public, which is the goal of the “bring your own” proposals.

Roughly one-third of a data center’s cost is the power plant needed to serve it, he stated, and under the current system, taxpayers foot the bill for speculative projects – whether they get built or not – which he suggests is one of the main drivers for “bring your own.”

The voting at the Nov. 19 meeting resulted in none of the 12 proposal packages obtaining a requisite “passing” vote, Jeffrey Shields, PJM spokesman, told The Center Square via email.

“PJM opened this conversation about the integration of large loads and greatly appreciates our stakeholders for their contributions to this effort,” he said. ”The stakeholder process produced many thoughtful proposals, some of which were introduced late in the process and require additional development.”

This vote, Shields said, is advisory to PJM’s independent board, which can and does expect to act on large load additions to the system and will make its decision known in the next few weeks.

Events

No events

Leave a Comment





Latest News Stories

Meeting-Briefs

Meeting Summary and Briefs: Beecher Fire Protection District Board of Trustees for April 24, 2025

The Beecher Fire Protection District Board of Trustees approved a major investment in firefighter safety during its April 24 meeting, authorizing over $91,000 for the purchase of new turnout gear...
Beecher Fire Protection District graphic.4

Beecher Public Bodies Renew Joint Fuel Purchasing Agreement to Save Taxpayer Money

Article Summary: The Beecher Fire Protection District has renewed an intergovernmental agreement with four other local public bodies to continue purchasing fuel in bulk, a strategy designed to reduce costs...
Beecher Fire Protection District graphic.2

Beecher Fire District Invests Over $91,000 in New Protective Gear and Helmets

Article Summary: The Beecher Fire Protection District will purchase new turnout gear and helmets for its firefighters after the Board of Trustees unanimously approved two proposals totaling more than $91,000....
beecher illinois public library graphic.1

Beecher Library Board Installs New Trustees, Elects Officers for Two-Year Term

Article Summary: Following the certification of the April 1 election, the Beecher Community Library Board seated three trustees for six-year terms and unanimously re-elected Shirley R. Biery as president. The...
OLYMPUS DIGITAL CAMERA

Beecher Library Board Streamlines Bill Payments Between Meetings

Article Summary: The Beecher Community Library Board approved a new policy to allow for the payment of routine bills that arrive after its monthly meetings, a move designed to improve...
Meeting Briefs

Meeting Summary and Briefs: Beecher Community Library Board for May 20, 2025

The Beecher Community Library Board seated three newly elected trustees and appointed its officers for the next two years at its May 20 meeting. Shirley R. Biery was re-elected as...
Screenshot 2025-06-16 at 3.26.08 PM

Will County Board Rejects Two Solar Farm Projects After Heated Public Opposition

New Lenox area residents cite safety concerns, property values in opposing commercial solar facilities The Will County Board voted decisively against two proposed commercial solar energy facilities during its May...
will county board.3

County Approves $15 Million Water System Takeover for Southeast Joliet Area

700 homes to receive upgraded service as Joliet takes control of failing sanitary district The Will County Board voted 20-1 to support dissolving the Southeast Joliet Sanitary District and transferring...
will county board

Board Postpones County Purchasing Code Overhaul Amid Union Contractor Debate

Members seek clarification on requirements that could favor unionized businesses The Will County Board postponed action on proposed changes to county purchasing ordinances after members raised concerns about language that...
will county board.2

Animal Permit Hearing Reveals Neighborhood Disputes Over Horses, Roosters in Crete Township

Board postpones decision on Torres family request pending barn variance appeal A contentious hearing over Fernando Torres' request to keep horses on his Crete Township property exposed deep neighborhood divisions...
will county board.3

Transportation Projects Advance as Board Approves Vision Zero, Road Improvements

County adopts traffic safety initiative while funding major infrastructure upgrades The Will County Board approved a comprehensive transportation agenda including adoption of Vision Zero principles and multiple road improvement projects...
County Board Room

Health Department Receives Budget Boost, Sunny Hill Admission Policy Updated

Board approves funding increases and policy changes for county health services The Will County Board approved budget appropriations for the health department and updated admission policies for Sunny Hill Nursing...
Screenshot 2025-06-16 at 3.26.08 PM

Will County Board Meeting Briefs Package

COUNTY APPOINTMENTS Fire Protection District: Board approved county executive appointments to Manhattan Fire Protection District board. Agricultural Committee: Approved appointment to Agricultural Area Committee with Member Judy Ogala abstaining due...
beecher ilinois school board graphic.1

Beecher High School Slated for Over $88,000 in Major Plumbing Repairs

Article Summary: The Beecher Board of Education unanimously approved two separate, significant plumbing projects for the high school totaling over $88,000 during its May 14 meeting. The board awarded both...
beecher ilinois school board graphic.4

Beecher School Board Issues Suspension, Formal Notice to Remedy to Employee

Article Summary: The Beecher Board of Education has taken formal disciplinary action against district employee Jessica Carter, unanimously approving a resolution for an unpaid suspension and a "Third Issuance of...