Committee Grants Lenox Solar Farm Project Six-Month Variance Extension

Spread the love

Will County Planning and Zoning Commission Meeting | November 18, 2025

Article Summary:
The Will County Planning and Zoning Commission has approved a 180-day extension for variances tied to a commercial solar energy facility in New Lenox Township. The extension provides the developer, Greenpath New Lenox LandCo LLC, with the necessary time to prepare the site for planting pollinator-friendly ground cover in the spring of 2026.

Solar Farm Variance Extension Key Points:

  • Location: Vacant property on South Spencer Road, New Lenox Township.

  • Project: A 4.95-megawatt commercial solar energy facility.

  • Variances Extended: Four variances related to increasing ground cover height to 36 inches and reducing required mowings from five times to one time per year.

  • New Expiration Date: The variances will now expire on August 16, 2026.

JOLIET, IL – A commercial solar energy project planned for New Lenox Township received a procedural green light on Tuesday, November 18, 2025, as the Will County Planning and Zoning Commission granted a six-month extension for its previously approved zoning variances.

The applicant, Greenpath New Lenox LandCo LLC, requested the 180-day extension to prevent the variances from expiring on February 18, 2026. According to a staff memo, favorable planting conditions for the pollinator-friendly ground cover planned for the site are not expected until after that date. The extension was the first of two possible 180-day extensions allowed by the ordinance.

The commission originally approved the variances in February 2025. They allow the developer to increase the maximum height of ground cover plants from 13 inches to 36 inches and reduce the number of required mowings from five times per year to just once. These changes are designed to support the establishment of a native pollinator habitat on the site, a practice encouraged by the Illinois Pollinator-Friendly Solar Site Act.

The project involves two parcels on South Spencer Road and is planned as a 4.95 MWac commercial solar energy facility. With the unanimous approval of the extension, the variances will now remain valid until August 16, 2026, allowing the developer to proceed with site preparation and planting in the spring.

Events

No events

Leave a Comment





Latest News Stories

WCO LEG 8.5.2

Will County Leglislative Committee Opposes Federal Push for Heavier, Longer Trucks

ARTICLE SUMMARY: The Will County Board's Legislative Committee unanimously passed a resolution opposing any federal legislation that would increase the size and weight limits for commercial trucks on national roadways. Will...
WCO Public Safety.2

Will County Reports Progress in Opioid Fight, Highlights New FDA Labeling Rules

Article Summary: Will County is seeing a reduction in opioid overdose deaths and is expanding access to the reversal drug Narcan, health officials reported. The department also drew attention to...
WCO Cap Imp 8.5.4

In-House Staff Completes Major Renovations at Will County Adult Detention Facility

ARTICLE SUMMARY: Maintenance staff at the Will County Adult Detention Facility recently completed extensive renovations in-house, including a new control center and the full restoration of a 48-cell housing unit, saving...
Land use 8.5.25

Will County Advances Truck Repair Facility Plan on Manhattan Road Despite Resident Objections

Article Summary: A proposal to rezone nearly 14 acres on Manhattan Road for a truck repair facility advanced after receiving a recommendation for approval from the Will County Land Use...
WCO P&Z 8.12.1

PZC Grants Variance for Oversized Garage in Joliet Township, Reversing Staff Recommendation

Article Summary: The Will County Planning and Zoning Commission unanimously approved a variance for a Joliet Township homeowner to build a garage addition that exceeds the county's size limits. The...
WCO P&Z Aug 5.5

Will County Public Works Committee Approves Over $1.1 Million in New Agreements for 80th Avenue Project

ARTICLE SUMMARY: The Will County Public Works & Transportation Committee authorized two agreements totaling over $1.1 million for the ongoing reconstruction and widening of 80th Avenue between 191st and 183rd Streets....
Meeting Briefs

Meeting Summary and Briefs: Will County Board Legislative Committee for August 5, 2025

The Will County Board’s Legislative Committee focused on shaping its advocacy efforts at both the state and federal levels during its August 5 meeting. The primary discussion centered on crafting...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Capital Improvements & IT Committee for August 5, 2025

The future of several key county facilities dominated the Will County Capital Improvements & IT Committee meeting on Tuesday. A major topic of discussion was the ongoing buildout of the...
Meeting Briefs

Meeting Summary and Briefs: Will County Land Use & Development Committee for August 7, 2025

The Will County Land Use & Development Committee tackled two contentious zoning cases during its August 7 meeting, denying a special use permit for a landscaping business in a residential...

Meeting Summary and Briefs: Will County Planning and Zoning Commission for August 5, 2025

The Will County Planning and Zoning Commission backed two controversial projects at its August 5 meeting, unanimously approving a large-scale landscaping business on a residential lot in DuPage Township despite...
Meeting Briefs

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for August 5, 2025

The Will County Public Works & Transportation Committee received a detailed presentation on "Our Way Forward 2050," a new 25-year long-range plan designed to guide the region's transportation infrastructure through...
Beecher Fire Protection District graphic.1

Beecher Fire District Promotes Three to Lieutenant/Paramedic

Article Summary: The Beecher Fire Protection District Board of Trustees unanimously promoted Carm Welsh, Marci DuBois, and Bryce Budimir to the rank of Lieutenant/Paramedic at its June 26 meeting. The...
Beecher Fire Protection District graphic.2

Fire Board Approves $13,895 Landscaping Contract for Station

Article Summary: The Beecher Fire Protection District Board of Trustees has awarded a $13,895 contract to Tadpole for a significant landscaping project at the fire station. The decision was made...
Meeting-Briefs

Meeting Summary and Briefs: Beecher Fire Protection District Board of Trustees for June 26, 2025

The Beecher Fire Protection District Board of Trustees made several key decisions at its June 26 meeting, highlighted by the promotion of three members to leadership positions and the approval...
Meeting-Briefs

Meeting Summary: Peotone School District 207-U for July 21, 2025

District Weighs Budget Cuts vs. More Debt: Peotone schools must create a state-mandated deficit reduction plan to address a recurring ~$2 million operating shortfall. The Board of Education is debating whether...