Contractors Clash on Cause of Elementary School Leaks; Committee Weighs Window Replacement

Spread the love

Beecher School Board Facilities Committee Meeting | November 24, 2025

Article Summary: The Beecher School District 200-U Facilities Committee reviewed proposals for replacing windows at the Elementary School but paused due to conflicting reports regarding water intrusion.

Elementary Project Key Points:

  • Window Plan: A proposal from Performance Services involves replacing residential-style windows and plywood infills with full-size, energy-efficient units.

  • The Conflict: Performance Services identified tuckpointing (masonry) as the solution to water leaks, while a competing firm, GRP, suggested the root cause is a roofing and flashing issue.

  • Cost Estimates: The preliminary budget for the window and masonry work is approximately $322,000, though hard pricing could come in lower.

  • Next Steps: The committee decided to seek a third-party opinion to identify the true source of the leaks before authorizing work.

BEECHER, Ill. – A plan to replace aging windows at Beecher Elementary School hit a snag on Monday, November 24, 2025, as the District 200-U Facilities Committee wrestled with conflicting expert opinions regarding the cause of water leaks in the building.

Cameron, a representative from Performance Services, presented a design-build proposal to the committee. The project would remove existing residential-style windows and plywood infills, restoring the openings to their original full size with modern, energy-efficient glass.

However, the presentation highlighted a deeper issue: water intrusion near the “birdhouse” section of the building. Performance Services recommended extensive tuckpointing—replacing the mortar between bricks—and replacing the building’s “crown” or coping to stop the leaks.

“I don’t want you guys to have to call me in five years and say, ‘Hey, the sill around there is starting to deteriorate because water is now seeping down,'” Cameron told the committee.

The committee then reviewed a competing assessment from GRP, a contractor who had previously worked on the district’s HVAC systems. GRP’s team, which included a roofer, suggested that the water issues were likely caused by roofing and flashing failures rather than masonry problems.

District officials expressed frustration at the contradictory assessments.

“Your apples and apples are more like apples and peaches,” one official noted regarding the two proposals. “I don’t want to speak for the other company… but I don’t have enough information to tell you which one it is.”

The committee agreed that proceeding without certainty would be fiscally irresponsible.

“I don’t want people coming back and saying the school district [is] wasting $45,000,” an administrator said. “We need to solve [the problem].”

The committee directed staff to contact a third party, potentially Total Roofing, to provide a neutral assessment of the leak’s origin. The window replacement project is currently being targeted for the summer of 2026.

 

Events

No events

Leave a Comment





Latest News Stories

Meeting Summary and Briefs: Village of Beecher Board of Trustees for July 14, 2025

The Beecher Village Board passed a major overhaul of its governmental structure at its meeting on July 14, approving ordinances that dissolve the Planning and Zoning and Beautification Commissions and...
WCO Exec Cmte July 10.1

County Approves School Resource Officer, Multi-Year Planning Requirements

Will County approved hiring an additional sheriff's deputy for a school resource officer position that will be fully funded by Summit Hill School District 161, while also passing new transparency...
WCO Exec Cmte July 10.2

County Addresses Senior Tax Exemption Processing Error

A processing error that cost County Board member Julie Berkowicz $600 in senior tax exemptions has prompted discussions about improving verification systems for property tax breaks. Will County Chief Assessment...
Meeting Briefs

Executive Committee Meeting July 10 Meeting Briefs

Liquor License Expansion: The county approved increasing Class C1 liquor licenses from eight to nine to accommodate Lockport Gas and Food LLC at 14747 W. 159th Street in Homer Glen....
Screenshot 2025-08-22 at 8.12.43 PM

Beecher School Board Begins Overhaul of District Goals, Focusing on Transparency, Inclusivity, and Student Success

Article Summary: The Beecher Board of Education has initiated a comprehensive update of its district-wide goals, beginning a process to replace a strategic plan that has been in place since...
beecher ilinois school board graphic.12

Beecher School Board Finalizes Policy Updates, Approves New Student Handbook

Article Summary: The Beecher Board of Education gave its final approval to a series of policy updates and a revised Student Handbook for the 2025-2026 school year. The unanimous votes...
beecher ilinois school board graphic.5

District Modifies Janitorial Contract, Saving Money by Bringing Junior High In-House

Article Summary: The Beecher Board of Education approved a new janitorial contract with Citywide Janitorial for the 2025-2026 fiscal year that covers only the elementary school, a change that will...
Meeting Briefs

Meeting Summary and Briefs: Beecher Board of Education for July 9, 2025

The Beecher Board of Education began the process of creating a new five-year strategic plan by holding an in-depth discussion to overhaul its district goals at its July 9 meeting....
washington township graphic.1

Washington Township to Reduce Office Hours in Summer Trial

Article Summary: The Washington Township Board of Trustees has approved a plan to reduce public office hours for a trial period this summer, citing less foot traffic and potential cost...
washington township graphic.2

Washington Township Opts for $1,050 AC Repair Over $10,200 Replacement

Article Summary: The Washington Township Board of Trustees chose to repair two non-functional, 25-year-old air conditioning units for $1,050 rather than pursue a full replacement of all three units at...
washington township graphic.3

Property Assessments Set to Rise Across Washington Township

Article Summary: Washington Township Assessor Pat Peters has advised residents that property assessments are expected to rise for nearly every property in the township. The increase is due to a...
Meeting-Briefs

Meeting Summary and Briefs: Washington Township Board of Trustees for July 7, 2025

The Washington Township Board of Trustees voted to reduce its public office hours for the summer, a key decision made during its meeting on Monday, July 7. Citing a decline...
Will County Land Use July 3.1

Committee Rejects Troy Township Solar Projects Amid Strong Local Opposition

The Will County Land Use and Development Committee recommended denial for two controversial commercial solar energy projects in Troy Township on Thursday, following a wave of opposition from local municipalities,...
Will County Land Use July3.2

Controversial DuPage Township Rezoning for Outdoor Storage Advances

A contentious proposal to rezone a 20-acre parcel in DuPage Township from agricultural (A-1) to heavy industrial (I-3) for an outdoor vehicle storage facility narrowly passed the Will County Land...
Will County Land Use July3.2

Residents Allege Health Crises, Violations from Peotone Grain Facility

Two residents of unincorporated Peotone delivered emotional testimony to the Will County Land Use and Development Committee Thursday, alleging that a neighboring grain facility is causing severe health problems and...