Contractors Clash on Cause of Elementary School Leaks; Committee Weighs Window Replacement

Spread the love

Beecher School Board Facilities Committee Meeting | November 24, 2025

Article Summary: The Beecher School District 200-U Facilities Committee reviewed proposals for replacing windows at the Elementary School but paused due to conflicting reports regarding water intrusion.

Elementary Project Key Points:

  • Window Plan: A proposal from Performance Services involves replacing residential-style windows and plywood infills with full-size, energy-efficient units.

  • The Conflict: Performance Services identified tuckpointing (masonry) as the solution to water leaks, while a competing firm, GRP, suggested the root cause is a roofing and flashing issue.

  • Cost Estimates: The preliminary budget for the window and masonry work is approximately $322,000, though hard pricing could come in lower.

  • Next Steps: The committee decided to seek a third-party opinion to identify the true source of the leaks before authorizing work.

BEECHER, Ill. – A plan to replace aging windows at Beecher Elementary School hit a snag on Monday, November 24, 2025, as the District 200-U Facilities Committee wrestled with conflicting expert opinions regarding the cause of water leaks in the building.

Cameron, a representative from Performance Services, presented a design-build proposal to the committee. The project would remove existing residential-style windows and plywood infills, restoring the openings to their original full size with modern, energy-efficient glass.

However, the presentation highlighted a deeper issue: water intrusion near the “birdhouse” section of the building. Performance Services recommended extensive tuckpointing—replacing the mortar between bricks—and replacing the building’s “crown” or coping to stop the leaks.

“I don’t want you guys to have to call me in five years and say, ‘Hey, the sill around there is starting to deteriorate because water is now seeping down,'” Cameron told the committee.

The committee then reviewed a competing assessment from GRP, a contractor who had previously worked on the district’s HVAC systems. GRP’s team, which included a roofer, suggested that the water issues were likely caused by roofing and flashing failures rather than masonry problems.

District officials expressed frustration at the contradictory assessments.

“Your apples and apples are more like apples and peaches,” one official noted regarding the two proposals. “I don’t want to speak for the other company… but I don’t have enough information to tell you which one it is.”

The committee agreed that proceeding without certainty would be fiscally irresponsible.

“I don’t want people coming back and saying the school district [is] wasting $45,000,” an administrator said. “We need to solve [the problem].”

The committee directed staff to contact a third party, potentially Total Roofing, to provide a neutral assessment of the leak’s origin. The window replacement project is currently being targeted for the summer of 2026.

 

Events

No events

Leave a Comment





Latest News Stories

will county board.2

Will County Finance Committee Approves Juvenile Detention Center Upgrades

Committee votes to keep facility operational, moves forward with compliance modifications Will County Finance Committee members voted unanimously Monday to recommend keeping the River Valley Detention Center operational and making...
will county board.2

Major Grade Separation Projects Advance with Engineering Contracts

The committee approved two significant engineering agreements for major railroad overpass projects totaling over $4 million. TranSystems Corporation received a $4,003,256 contract for construction engineering services on the Lorenzo Road...
County Board Room

County Authorizes Condemnation for Francis Road Project

The committee authorized the State's Attorney's Office to proceed with condemnation cases for right-of-way acquisition needed for Francis Road improvements between Gougar Road and Interstate 80. Eight property parcels are...
will county board

Solar Farm Access Approved for Manhattan-Arsenal Road

The committee granted access approval for a solar farm development on Manhattan-Arsenal Road approximately 1,000 feet east of Cherry Hill Road. The MCH Solar 1 project, developed by Soltage LLC,...
will county board.3

Will County Finance Committee Meeting Briefs

Budget Transfers Approved: The Finance Committee approved transferring $18,643 within the Supervisor of Assessments budget to move funds from software licensing to computer hardware purchases. Animal Protection Services Funding: Committee...
will county board.2

Public Works Committee Briefs

Major Projects Update: Construction continues on several major projects including the 80th Avenue expressway overpass, Laraway Road widening near Cedar Road, and Bell Road improvements. The Bell Road project at...
will county board

Capital Improvements & IT Committee Briefs

Bed donation program: Will County donated old beds from Sunny Hill Nursing Home to Joliet Junior College and Project Cure after the nursing home received all new beds for residents....
washington township graphic.1

Washington Township Approves $13,260 Security Overhaul, Opts for Local Vendor with 24/7 Service

Article Summary: The Washington Township Board of Trustees unanimously approved a $13,260 contract with TK Audio & Visual to comprehensively upgrade the security system at the Township Center. The final...
washington township graphic.2

Washington Township Board Appoints Teresa Peterson to Fill Vacancy

Article Summary: The Washington Township Board of Trustees is once again at full strength after unanimously appointing resident Teresa Peterson to fill a trustee vacancy. Peterson took the Oath of...
washington township graphic.3

Washington Township Board Passes 2025-2026 Town Budget

Article Summary: The Washington Township Board of Trustees gave its final approval to the fiscal year 2025-2026 Town Budget, passing the ordinance with a unanimous 4-0 vote. The action occurred...
Meeting-Briefs

Meeting Summary and Briefs: Washington Township Board of Trustees for June 2, 2025

The Washington Township Board of Trustees approved a major security upgrade for its township center and appointed a new trustee to fill a board vacancy during a busy meeting on...
Meeting-Briefs

Meeting Summary and Briefs: Beecher Fire Protection District Board of Trustees for April 24, 2025

The Beecher Fire Protection District Board of Trustees approved a major investment in firefighter safety during its April 24 meeting, authorizing over $91,000 for the purchase of new turnout gear...
Beecher Fire Protection District graphic.4

Beecher Public Bodies Renew Joint Fuel Purchasing Agreement to Save Taxpayer Money

Article Summary: The Beecher Fire Protection District has renewed an intergovernmental agreement with four other local public bodies to continue purchasing fuel in bulk, a strategy designed to reduce costs...
Beecher Fire Protection District graphic.2

Beecher Fire District Invests Over $91,000 in New Protective Gear and Helmets

Article Summary: The Beecher Fire Protection District will purchase new turnout gear and helmets for its firefighters after the Board of Trustees unanimously approved two proposals totaling more than $91,000....
beecher illinois public library graphic.1

Beecher Library Board Installs New Trustees, Elects Officers for Two-Year Term

Article Summary: Following the certification of the April 1 election, the Beecher Community Library Board seated three trustees for six-year terms and unanimously re-elected Shirley R. Biery as president. The...