Beecher Elementary school Graphic

Contractors Clash on Cause of Elementary School Leaks; Committee Weighs Window Replacement

Spread the love

Beecher School Board Facilities Committee Meeting | November 24, 2025

Article Summary: The Beecher School District 200-U Facilities Committee reviewed proposals for replacing windows at the Elementary School but paused due to conflicting reports regarding water intrusion.

Elementary Project Key Points:

  • Window Plan: A proposal from Performance Services involves replacing residential-style windows and plywood infills with full-size, energy-efficient units.

  • The Conflict: Performance Services identified tuckpointing (masonry) as the solution to water leaks, while a competing firm, GRP, suggested the root cause is a roofing and flashing issue.

  • Cost Estimates: The preliminary budget for the window and masonry work is approximately $322,000, though hard pricing could come in lower.

  • Next Steps: The committee decided to seek a third-party opinion to identify the true source of the leaks before authorizing work.

BEECHER, Ill. – A plan to replace aging windows at Beecher Elementary School hit a snag on Monday, November 24, 2025, as the District 200-U Facilities Committee wrestled with conflicting expert opinions regarding the cause of water leaks in the building.

Cameron, a representative from Performance Services, presented a design-build proposal to the committee. The project would remove existing residential-style windows and plywood infills, restoring the openings to their original full size with modern, energy-efficient glass.

However, the presentation highlighted a deeper issue: water intrusion near the “birdhouse” section of the building. Performance Services recommended extensive tuckpointing—replacing the mortar between bricks—and replacing the building’s “crown” or coping to stop the leaks.

“I don’t want you guys to have to call me in five years and say, ‘Hey, the sill around there is starting to deteriorate because water is now seeping down,'” Cameron told the committee.

The committee then reviewed a competing assessment from GRP, a contractor who had previously worked on the district’s HVAC systems. GRP’s team, which included a roofer, suggested that the water issues were likely caused by roofing and flashing failures rather than masonry problems.

District officials expressed frustration at the contradictory assessments.

“Your apples and apples are more like apples and peaches,” one official noted regarding the two proposals. “I don’t want to speak for the other company… but I don’t have enough information to tell you which one it is.”

The committee agreed that proceeding without certainty would be fiscally irresponsible.

“I don’t want people coming back and saying the school district [is] wasting $45,000,” an administrator said. “We need to solve [the problem].”

The committee directed staff to contact a third party, potentially Total Roofing, to provide a neutral assessment of the leak’s origin. The window replacement project is currently being targeted for the summer of 2026.

 

Events

No events

Leave a Comment





Latest News Stories

washington township graphic.2

Washington Township Approves $2,500 in Sponsorships for Beecher EMS, July 4th Celebration

Article Summary: The Washington Township Board unanimously approved two community sponsorships totaling $2,500, continuing its financial support for the Village of Beecher's Emergency Management Agency (EMA) and the annual 4th...
washington township graphic.3

Washington Township to Continue Annual Senior Breakfast Amid Post-COVID Attendance Changes

Article Summary: Following a discussion about lower-than-historic attendance at its recent Senior Breakfast, the Washington Township Board decided to maintain one breakfast event per year. The board concluded that the...
Meeting-Briefs

Meeting Summary and Briefs: Washington Township Board of Trustees for May 5, 2025

The Washington Township Board of Trustees paused a decision on a major security upgrade, approved community sponsorships, and discussed the future of its senior events at its meeting on Monday,...
Screenshot 2025-05-04 at 3.03.49 PM

County Approves $4.3 Million Purchase of Wetland Banking Credits for Highway Projects

The Will County Public Works and Transportation Committee has approved an agreement to purchase wetland banking site credits for $4,324,550 from V3 Wetland Restoration LLC to support future county highway...
Meeting-Briefs

Meeting Summary and Briefs: Beecher Fire Protection District Board of Trustees for March 20, 2025

The Beecher Fire Protection District is preparing for changes in its leadership and staffing after the Board of Trustees on March 20 approved the creation of a new Lieutenant position....
Beecher Fire Protection District graphic.1

Beecher Fire District to Hire New Lieutenant, Approves Updated Appointment Process

Article Summary: The Beecher Fire Protection District Board of Trustees has authorized the creation of a new Lieutenant position and will begin accepting applications at the end of March. The...
Screenshot 2025-05-04 at 2.01.41 PM

Labor Representative Addresses County Committee on Public Transportation Reform Efforts

JOLIET — A labor representative warned Will County officials Thursday that proposed reforms to regional public transportation governance could diminish the county's voice in transit decisions during a presentation to...
Screenshot 2025-05-04 at 2.01.41 PM

Committee Advances $1.7 Million Upgrade Plan for River Valley Juvenile Detention Center

JOLIET — The Will County Executive Committee voted Thursday to advance a $1.7 million proposal to upgrade the River Valley Juvenile Detention Center rather than pursuing costlier alternatives to house...
Screenshot 2025-05-04 at 2.01.41 PM

County Executive Committee Briefs: Transportation Program Expands, Ordinances Updated

Mobility Management Program Expands to Three Townships: The Executive Committee approved an intergovernmental agreement to expand the Will County Mobility Management Program to include Channahon, Manhattan, and Plainfield townships. The...
Screenshot 2025-05-04 at 2.01.41 PM

County Executive Committee Advances Elected Officials’ Pay Increases After Extended Debate

The Will County Executive Committee voted Thursday to advance a proposal for pay increases for countywide elected officials and county board members, setting the stage for a final vote at...
Screenshot 2025-05-04 at 2.01.41 PM

County Considers Bond Refinancing That Could Save Millions

JOLIET — Will County officials on Thursday discussed a potential bond refinancing opportunity that could save the county approximately $3.6 million in debt service costs by taking advantage of favorable...
Screenshot 2025-05-04 at 2.14.20 PM

Will County Ordinance Committee Briefs: Unanimous Votes for Proclamations, Title Changes, Audits Discussed

Committee Clarifies Unanimous Vote Requirement for Honorary Proclamations: The Ordinance Committee refined language in Chapter 30 regarding honorary proclamations, specifying that they shall be allowed "only by unanimous vote" of...
Screenshot 2025-05-04 at 2.14.20 PM

County Undertakes Formatting Overhaul of Decades-Old Ordinances

JOLIET — Will County officials are modernizing the format and structure of the county's ordinances, some of which date back to 1943, as part of a comprehensive review process to...
Screenshot 2025-05-04 at 2.14.20 PM

County Reviews Rules on Virtual Meeting Attendance, Committee Participation

JOLIET — Will County officials discovered Thursday that their current practices regarding virtual meeting attendance may not fully comply with state law, as the Ordinance Committee worked through updates to...
Screenshot 2025-05-04 at 2.14.20 PM

Will County Ordinance Committee Reviews Administrative Code, Clarifies Official Powers

JOLIET — The Will County Ordinance Committee spent several hours Thursday reviewing and updating Chapter 30 of the county's Code of Ordinances, which governs county administration, with particular attention to...