School Facilities Committee Reviews Elementary School Window and Roof Repairs

Spread the love

Beecher School District Facilities Committee Meeting | December 2025

Article Summary: The Beecher School District 200-U Facilities Committee reviewed competing assessments for water intrusion at Beecher Elementary, favoring a comprehensive window and parapet repair plan over general masonry work.

Beecher Schools Key Points:

  • The Issue: Beecher Elementary is experiencing water leaks, specifically around the second-floor windows and roof edges.

  • The Proposal: GRP, a contractor, presented a plan totaling approximately $185,000 to replace windows and repair the roof coping and parapets.

  • Timeline: The committee expects to present a recommendation to the full Board of Education for a vote in January 2026.

  • Competing Views: The committee debated between GRP’s roof-edge focus and another firm’s recommendation to prioritize tuck pointing.

The Beecher School District 200-U Board of Education Facilities Committee met on Wednesday, December 3, 2025, to discuss a significant capital improvement project aimed at stopping water leaks at Beecher Elementary School.

The committee focused on a proposal from GRP, the company that previously handled the district’s HVAC project. Scott Instrom, representing GRP, presented findings indicating that water intrusion at the elementary school is likely caused by issues with the windows and the roof’s parapet and coping, rather than the roof membrane itself or general brick mortar deterioration.

“These are your worst window areas,” Instrom told the committee. “On top of that, you’ve got a leaking situation.”

Instrom proposed a solution involving the replacement of the second-floor windows and significant work to the parapet—the wall extension at the edge of the roof. He explained that the current roof membrane needs to be cut back and extended up the parapet wall under a new metal cap to ensure a watertight seal.

Superintendent Dr. Jack Gaham guided the committee through a comparison between GRP’s findings and an assessment from another vendor, Performance. While Performance suggested extensive tuck pointing (masonry repair) to stop the leaks, GRP and a separate roofing consultant concluded the issue was not the brickwork but the roof edges.

“If it was the roof, you would have leaks everywhere,” Gaham said, relaying the opinion of a roofing expert. “It is probably your scuppers and your coping that needs to be addressed.”

The committee discussed a total project cost of approximately $185,000 for the GRP plan, which includes window replacement and the necessary roofing tie-ins. The committee debated whether to include additional tuck pointing on the south wall and courtyard, estimated at an additional cost, or to bid that work out separately to local contractors in the future.

Gaham recommended the committee focus on the immediate water intrusion issues to remain fiscally responsible. “I just want to start getting in the future to where we’re being more proactive and less reactive,” Gaham said.

The committee is expected to bring a formal recommendation to the full school board in January to ensure work can be scheduled for the summer break.

Events

No events

Leave a Comment





Latest News Stories

Meeting Summary and Briefs: Village of Beecher Board of Trustees for July 14, 2025

The Beecher Village Board passed a major overhaul of its governmental structure at its meeting on July 14, approving ordinances that dissolve the Planning and Zoning and Beautification Commissions and...
WCO Exec Cmte July 10.1

County Approves School Resource Officer, Multi-Year Planning Requirements

Will County approved hiring an additional sheriff's deputy for a school resource officer position that will be fully funded by Summit Hill School District 161, while also passing new transparency...
WCO Exec Cmte July 10.2

County Addresses Senior Tax Exemption Processing Error

A processing error that cost County Board member Julie Berkowicz $600 in senior tax exemptions has prompted discussions about improving verification systems for property tax breaks. Will County Chief Assessment...
Meeting Briefs

Executive Committee Meeting July 10 Meeting Briefs

Liquor License Expansion: The county approved increasing Class C1 liquor licenses from eight to nine to accommodate Lockport Gas and Food LLC at 14747 W. 159th Street in Homer Glen....
Screenshot 2025-08-22 at 8.12.43 PM

Beecher School Board Begins Overhaul of District Goals, Focusing on Transparency, Inclusivity, and Student Success

Article Summary: The Beecher Board of Education has initiated a comprehensive update of its district-wide goals, beginning a process to replace a strategic plan that has been in place since...
beecher ilinois school board graphic.12

Beecher School Board Finalizes Policy Updates, Approves New Student Handbook

Article Summary: The Beecher Board of Education gave its final approval to a series of policy updates and a revised Student Handbook for the 2025-2026 school year. The unanimous votes...
beecher ilinois school board graphic.5

District Modifies Janitorial Contract, Saving Money by Bringing Junior High In-House

Article Summary: The Beecher Board of Education approved a new janitorial contract with Citywide Janitorial for the 2025-2026 fiscal year that covers only the elementary school, a change that will...
Meeting Briefs

Meeting Summary and Briefs: Beecher Board of Education for July 9, 2025

The Beecher Board of Education began the process of creating a new five-year strategic plan by holding an in-depth discussion to overhaul its district goals at its July 9 meeting....
washington township graphic.1

Washington Township to Reduce Office Hours in Summer Trial

Article Summary: The Washington Township Board of Trustees has approved a plan to reduce public office hours for a trial period this summer, citing less foot traffic and potential cost...
washington township graphic.2

Washington Township Opts for $1,050 AC Repair Over $10,200 Replacement

Article Summary: The Washington Township Board of Trustees chose to repair two non-functional, 25-year-old air conditioning units for $1,050 rather than pursue a full replacement of all three units at...
washington township graphic.3

Property Assessments Set to Rise Across Washington Township

Article Summary: Washington Township Assessor Pat Peters has advised residents that property assessments are expected to rise for nearly every property in the township. The increase is due to a...
Meeting-Briefs

Meeting Summary and Briefs: Washington Township Board of Trustees for July 7, 2025

The Washington Township Board of Trustees voted to reduce its public office hours for the summer, a key decision made during its meeting on Monday, July 7. Citing a decline...
Will County Land Use July 3.1

Committee Rejects Troy Township Solar Projects Amid Strong Local Opposition

The Will County Land Use and Development Committee recommended denial for two controversial commercial solar energy projects in Troy Township on Thursday, following a wave of opposition from local municipalities,...
Will County Land Use July3.2

Controversial DuPage Township Rezoning for Outdoor Storage Advances

A contentious proposal to rezone a 20-acre parcel in DuPage Township from agricultural (A-1) to heavy industrial (I-3) for an outdoor vehicle storage facility narrowly passed the Will County Land...
Will County Land Use July3.2

Residents Allege Health Crises, Violations from Peotone Grain Facility

Two residents of unincorporated Peotone delivered emotional testimony to the Will County Land Use and Development Committee Thursday, alleging that a neighboring grain facility is causing severe health problems and...