Safety Upgrades Planned for Wilmington-Peotone Road; Gas Line Proposal Rejected
Public Works & Transportation Committee Meeting | December 2, 2025
Article Summary: The Will County Public Works Committee approved a $1.9 million engineering contract for improvements to a dangerous stretch of Wilmington-Peotone Road. Officials confirmed the project will add safety features like passing lanes but rejected a suggestion to simultaneously run utility lines to spur development.
Wilmington-Peotone Road Project Key Points:
-
Phase I Engineering: The board approved a $1,989,737 contract with Alfred Benesch and Company for design engineering.
-
Scope of Work: The project covers the stretch from US Route 45/52 to Center Road in Peotone Township.
-
Safety Features: Planned improvements include 10-foot wide shoulders and passing lanes to accommodate heavy truck traffic; the road will not be expanded to four lanes.
-
Utility Cost: A proposal to run natural gas main lines during construction to attract housing was deemed too expensive by the county engineer.
JOLIET, Ill. — A project to improve safety along a heavily trafficked corridor in Peotone Township moved forward Tuesday, December 2, 2025, as the Will County Board Public Works Committee authorized a nearly $2 million contract for design engineering.
The project targets Wilmington-Peotone Road between US Route 45/52 and Center Road. Director of Transportation Jeff Ronaldson noted that public feedback on the corridor has been polarized, with residents split between wanting “no trucks” and requesting a massive expansion to five lanes.
Ronaldson confirmed the county is taking a middle ground focused on safety.
“There’s going to be passing lanes through there to allow opportunities to get around some trucks. Wide 10-foot shoulders,” Ronaldson said. “It is not going to be a multi-lane, four-lane highway.”
Board Member Mark Revis (R-Plainfield) asked if the road construction offered an opportunity to work with utilities to run a natural gas main line down the corridor, suggesting it could help homeowners currently on propane and potentially attract residential development.
Ronaldson pushed back on the idea, citing the immense cost.
“The main line… would be very expensive,” Ronaldson said. “You need thousands of homes in order for that to make sense for a utility company.”
Ronaldson added that current residents in the agricultural area generally oppose dense subdivisions. “I think people in that area want to see more homes… they certainly don’t think they want to see a bunch of subdivisions,” he said.
The committee also approved a speed zone extension for Channahon-Minooka Road (CH 32) and a new speed zone for Golfview Drive in Green Garden Township.
Latest News Stories
Will County Community Mental Health Board Faces $5 Million Shortfall in 2026 Grant Requests
Meeting Summary and Briefs: Public Health & Safety Committee for March 5, 2026
Beecher Officials Push IDOT for Immediate Safety Fixes at Deadly Route 1 Intersection
Will County Officials Warn of Zoom Court Scam Targeting Defendants for Fraudulent Dismissal Fees
Will Land Use Committee Evaluates Multi-Million Dollar Buyout for Flooded Harris Drive Homes
Behavioral Health Division Drops Wait Times, Reports Zero Opioid Deaths in February
Harris Drive Residents Plead for County Intervention Amid Failing Septic Systems and Flooding
Meeting Summary and Briefs: Beecher Fire Protection District for Jan. 22, 2026
Will County Sheriff’s Office Investigates Fatal Hit-and-Run in Homer Glen
Federal Funding Freezes Threaten Will County Public Health Programs Amid Ongoing Lawsuits
New Brush Truck Expected in March as Training Hours Top 16,000
Meeting Summary and Briefs: Village of Beecher Board for Feb 23, 2026