Metra

Metra Announces No Fare Hikes; Highlights Bridge Projects in Joliet and Mokena

Spread the love

Will County Committee of the Whole Meeting | December 2025

Article Summary: Metra officials presented a balanced 2026 budget to the Will County Board, confirming that riders will not see a fare increase in the coming year. The agency also detailed capital projects affecting Will County, including bridge replacements and the rollout of new battery-powered train sets.

Metra 2026 Budget Key Points:

  • Balanced Budget: 2026 operations are funded through a combination of strong sales tax returns and $28 million in new state funding.

  • Local Infrastructure: Design work is underway for bridge replacements at Old Lagrange Road in Mokena and over Hickory Creek in Joliet.

  • New Fleet: Metra is purchasing new rail cars with dual entrances and testing battery-powered train sets on the Rock Island line.

  • Ridership Trends: Ridership is increasing approximately 5% annually, but office attendance patterns have shifted demand away from Mondays and Fridays.

Metra Chief Financial Officer John Morris presented the agency’s 2026 operating and capital budgets to the Will County Board on Tuesday, Dec. 9, 2025, confirming a balanced budget with no fare increases.

Morris reported that strong sales tax returns and new state funding have allowed Metra to avoid raising prices for commuters in 2026. He noted that while federal COVID-19 relief funds are expected to be depleted by the end of 2026, new funding streams from Senate Bill 2111 will cover projected deficits in 2027 and 2028.

“We are seeing a ridership pattern change,” Morris said. He explained that peak ridership has dropped, and commuters are riding less frequently on Mondays and Fridays, creating challenges for scheduling.

On the capital side, Morris highlighted investments in rolling stock. Metra is purchasing new rail cars that feature two entrances per side to improve boarding speed and accessibility. Additionally, the agency has ordered eight battery-powered train sets from Stadler, which will be tested primarily on the Rock Island line’s Beverly branch.

“This will be the first battery-powered type of this train in the United States,” Morris said, noting they must test the technology in Chicago’s weather conditions before expanding.

Locally, Morris identified two significant Will County infrastructure projects currently in the design phase: the Rock Island line bridge over Old Lagrange Road in Mokena and the bridge over Hickory Creek in Joliet.

“We’re trying to design replacements or rehabilitations for those bridges and then we’re going to look for funding to be able to put them through into construction,” Morris said.

Leave a Comment





Latest News Stories

Will County Board Graphic.02

Ad-Hoc Committee: Will County Sheriff’s Office to Acquire Decibel Meters for Noise Complaints

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 Article Summary: The Will County Sheriff's Office plans to purchase a fleet of certified decibel meters to accurately...
Beecher Graphic.3

Meeting Summary and Briefs: Village of Beecher Board of Trustees for March 9, 2026

Village of Beecher Board of Trustees Meeting | March 9, 2026 The Village of Beecher Board of Trustees met on Monday, March 9, 2026, to handle a variety of municipal...
Will County Public Works Committee

Will County Public Works Approves Access for 56-Acre Truck Services Hub on Manhattan-Monee Road

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee on Tuesday approved a request to allow commercial ingress...
Will County P&Z Logo Planning Zoning

Crest Hill Homeowner Granted Side Yard Setback Variance for Accessible Addition

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission approved a side yard setback variance for a Crest Hill...
will county Committee-Legislative.Graphic

State Update: County Officials Raise Alarms Over Pritzker’s ADU Zoning Push and Data Center Tax Breaks

Legislative Committee Meeting | March 2026 Article Summary: During a state legislative update, Will County Board members expressed deep concerns over Governor J.B. Pritzker's continued push to mandate Accessory Dwelling Units...
Will County Public Works Committee

Committee Approves $317K Guardrail Maintenance Contract Amid Discussion on Installation Dangers

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: Will County officials approved an annual guardrail maintenance contract Tuesday while addressing national concerns over improperly installed...
Will County Board Graphic.03

Will County Approves Diamond Enterprise Zone Expansion to Support $355 Million Energy Investment

Will County Executive Committee Meeting | March 12, 2026 Article Summary: The Will County Executive Committee unanimously approved ordinances expanding the Diamond Enterprise Zone to include the Village of Braceville. The...
will county Committee-Legislative.Graphic

Federal Update: DHS Shutdown, War Powers, and Housing Legislation Dominate Washington

Legislative Committee Meeting | March 3, 2026 Article Summary: Will County's federal lobbyists briefed the Legislative Committee on a turbulent week in Washington, D.C., highlighting the passage of a major bipartisan...
Will County Finance Logo

Will County Corporate Revenues Surpass Expectations, Igniting Debate Over Delinquent Tax Sales

Will County Finance Committee Meeting | March 3, 2026 Article Summary: A routine review of the county’s year-end corporate fund revealed that revenues exceeded budgeted expectations by millions, largely driven by...
Will County Public Works Committee

Meeting Summary and Briefs: Will County Public Works and Transportation Committee for March 3, 2026

Will County Public Works and Transportation Committee Meeting | March 3, 2026 The Will County Public Works and Transportation Committee met on Tuesday, March 3, advancing millions of dollars in...
solar panels photovoltaics in solar farm

Will County Grants Extensions for Seven Solar and Commercial Projects Amid Permitting Delays

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: The Will County Land Use and Development Committee approved a slate of extensions for seven previously authorized...
Will County Board Graphic.03

Will County Committee Postpones Liquor, Ad-Hoc Committee: Gaming, and Tobacco Ordinance Updates Amid Extensive Revisions

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 Article Summary: A Will County Board committee paused the advancement of major updates to the county's liquor, video...
Beecher Graphic.1

Beecher Village Board Approves Street Sweeping Contract and State Right-of-Way Resolution

Village of Beecher Board of Trustees Meeting | March 9, 2026 Article Summary: The Beecher Village Board approved a $6,200 contract for comprehensive commercial street sweeping to maintain environmental compliance,...
Beecher Elementary school Graphic

Beecher Elementary Principal Resigns Amid Slew of Personnel and Contract Approvals

Beecher Board of Education Meeting | March 11, 2026 Article SummaryBeecher School District 200U approved a slate of personnel changes, most notably accepting the resignation of Elementary School Principal Nicole...
solar panels photovoltaics in solar farm

Land Use Committee Approves 4.98-Megawatt Solar Facility on Eagle Lake Road Near Peotone

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: Reversing a deadlocked Planning and Zoning Commission, the Will County Land Use and Development Committee unanimously approved...