Will County Board Land Use Committee Graphic.1

Land Use Committee: Monee Solar Projects Granted Extensions; Battery Storage Plans Dropped

Spread the love

Will County Land Use & Development Committee Meeting | December 2025

Article Summary: The Will County Land Use and Development Committee granted time extensions for two separate solar farm projects in Monee Township. During the review, it was revealed that the developer has removed the battery energy storage systems (BESS) from both applications, and Board Member Judy Ogalla clarified her stance on the projects based on their proximity to residential areas.

Monee Solar Extensions Key Points:

  • Project 1 (Monee Solar): Located at 26845 S. Will Center Road; extension approved 5-1.

  • Project 2 (Monee Solar West): Located at West Pauling Road and South Will Center Road; extension approved 6-0.

  • Major Change: The developer is no longer pursuing Battery Energy Storage Systems (BESS) at either location; the permits for those specific components will lapse.

  • New Deadline: Special use permits for the solar arrays are now valid through July 17, 2026.

The Will County Land Use and Development Committee on Thursday, Dec. 4, 2025, approved “first extensions” for two separate commercial solar energy facilities in Monee Township, giving the developers until July 2026 to obtain building permits.

The first project, Monee Solar, LLC, located at 26845 S. Will Center Road, was originally approved in January 2024. Staff reported that while the original approval included a special use permit for a Battery Energy Storage System (BESS), the applicant has decided not to move forward with the battery component. The extension request applies only to the solar farm itself.

Board Member Judy Ogalla voted against the extension for this specific site.

“I would not have supported this,” Ogalla said, referring to the original vote in early 2024. “That is way too close to residential… I would be a no on that.”

The committee voted 5-1 to approve the extension, with Ogalla voting no.

The second project, Monee Solar West, LLC, located at the northwest corner of West Pauling Road and South Will Center Road, also received an extension. Similar to the first project, the developer has dropped plans for a battery storage system at this site.

Ogalla voted in favor of this second extension, distinguishing it from the first project based on its location.

“The second one is not near residential, so I would be supporting that,” Ogalla noted.

The committee voted 6-0 to approve the extension for Monee Solar West. Both special use permits are now valid through July 17, 2026.

Leave a Comment





Latest News Stories

AG candidate seeks to reform SAFE-T Act

AG candidate seeks to reform SAFE-T Act

By Sean Reed | The Center SquareThe Center Square (The Center Square) – An Illinois attorney general candidate launched a new initiative to reform the SAFE-T Act. The law enacted...
Op-Ed: Senate Bill 3070 provides sensible solution for students, manufacturers

Op-Ed: Senate Bill 3070 provides sensible solution for students, manufacturers

By Ben BarnettThe Center Square Illinois manufacturers face a serious problem. We have modern, high-tech facilities running at full capacity, but we struggle to find the young talent needed to...
Washington Township Graphic.2

Meeting Summary and Briefs: Washington Township Board of Trustees for March 2, 2026

Washington Township Board of Trustees Meeting | March 2, 2026 The Washington Township Board of Trustees met on March 2, 2026, handling a brief but financially significant agenda. Alongside authorizing...
Illinois millionaire’s tax moves closer to November ballot

Illinois millionaire’s tax moves closer to November ballot

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A measure giving Illinois voters the opportunity to consider a millionaire’s tax is one step closer to...
Beecher Village Graphic.1

Beecher to Implement ‘No Food’ Rule for New Police Station Community Room

Village of Beecher Meeting | April 13, 2026 Article Summary: To avoid charging rental fees and managing cleanup logistics, the Village of Beecher will adopt a usage policy for its...
(Photo by Chad Merda)

Oldest preserve expansion pushes acreage past 24,000 milestone

The Forest Preserve’s first acquisition of the year not only expands the District’s oldest preserve, it also pushes total acreage past the 24,000 mark. On March 27, the Forest Preserve...
—photo by Jim Piacentini

Beecher Edges Gardner-South Wilmington 4-3 Behind Lane’s Perfect Day at the Plate

Easton Lane’s perfect day at the plate helped propel the Beecher varsity baseball team to a tight 4-3 home conference victory over Gardner-South Wilmington on Monday. Lane went 3-for-3 with...
Beecher Fire Protection District graphic.3

Meeting Summary and Briefs: Beecher Fire Protection District for February 26, 2026

Beecher Fire Protection District Meeting | February 26, 2026 The Beecher Fire Protection District Board of Trustees met on Thursday, February 26, 2026, to address facility maintenance and hear operational...
washington township graphic.2

Washington Township Trustees Approve Nearly $87,500 in February Disbursements

Washington Township Board of Trustees Meeting | March 2, 2026 Article Summary: The Washington Township Board unanimously approved its February financial obligations, clearing $87,437.25 in combined spending across the Road...
Beecher Village Graphic.2

Beecher Renews IGA with Will County for License Plate Reading Cameras

Village of Beecher Meeting | April 13, 2026 Article Summary: The Village of Beecher approved a three-year Intergovernmental Agreement with Will County to maintain license plate reading cameras within the...
Beecher Fire Protection District graphic.4

Beecher Fire District Reports Over 1,300 Training Hours, Details Local Initiatives

Beecher Fire Protection District Meeting | February 26, 2026 Article Summary: Beecher Fire Protection District leadership provided comprehensive operational updates to the board, highlighting 1,330 hours of firefighter training and...
Will County Board Graphic.04

Meeting Summary and Briefs: Will County Board Executive Committee for April 9, 2026

Will County Board Executive Committee Meeting | April 9, 2026 The Will County Board Executive Committee met on Thursday, April 9, 2026, to process a diverse agenda featuring major strategic,...
Rock Run Preserve —Photo by Chad Merda

On the road to 100 years: How the Forest Preserve District expanded

As the Forest Preserve District approaches its centennial year in 2027 with a total of nearly 24,000 protected acres, it’s a good time to reflect on how the District grew...
Beecher Baseball Bobcats

Easton Lane’s Two-Way Heroics, 17-Hit Attack Lift Beecher Past Milford in 14-13 Thriller

The Beecher varsity baseball team survived a wild, back-and-forth slugfest on Saturday, outlasting host Milford 14-13 in a non-conference battle that featured 30 combined hits and constant lead changes. Milford...
—photos by Jim Piacentini

Norkus Strikes Out 15, Tosses One-Hitter in Beecher’s 4-0 Victory Over Gardner-South Wilmington

Senior ace Taylor Norkus delivered a masterpiece in the circle, striking out 15 batters and tossing a complete-game one-hitter to propel the Beecher varsity softball team to a 4-0 home...