Federal judge allows New York wind project to proceed

Federal judge allows New York wind project to proceed

Spread the love

A federal judge has given a green light for construction to resume on New York’s largest offshore wind project that was abruptly shut down by the Trump administration last month.

In a ruling issued Thursday, U.S. District Court judge Carl Nichols granted Empire Offshore Wind LLC a preliminary injunction that allows construction activities to resume on the wind project while he considers the broader legal challenge by the company. It’s the second ruling in a week blocking the Trump administration’s effort to stop several offshore wind projects.

In a statement, Norway-based Equinor said it looks forward to resuming construction of the Empire Wind I project, which, when completed, will provide enough energy to power 500,000 homes and “deliver a critical new, near-term source of electricity for New York and bolster grid reliability at a time of rapidly growing demand.”

“Empire Wind will now focus on safely restarting construction activities that were halted during the suspension period,” the company said. “In addition, the project will continue to engage with the U.S. government to ensure the safe, secure and responsible execution of its operations.”

The Interior Department did not immediately respond to a request for comment.

In its legal challenge, Equinor said the Interior Department’s stop-work order is “unlawful” and threatens the progress of ongoing work with significant implications for the project, which is nearly 60% complete.

President Donald Trump has pledged to end federal support for wind and other clean energy projects as he focuses on boosting fossil fuel production as part of broader efforts to improve the nation’s energy independence. He and other Republicans argue that the higher energy costs paid by many in the Northeast are being driven in part by the embrace of clean energy policies.

In December, the Interior Department announced it is halting federal leases for Empire and other large-scale offshore wind projects currently under construction. Besides Empire, the halt included Sunrise Wind, Vineyard Wind 1, Revolution Wind off the New England coast and Coastal Virginia Offshore Wind.

Earlier this week, a federal judge allowed the Revolution Wind project to resume construction while a separate legal challenge filed by its developers is considered by the court.

Interior Secretary Doug Burgum cited unspecified national security risks posed by the offshore wind turbines in pausing federal permits for the projects, but said the move is aimed at “protecting” the American people.

But Nichols, a Trump appointee, said in his order that the federal government’s national security concerns didn’t outweigh the “irreparable harm” Empire Wind would suffer if Trump’s order is not paused.

Speaking at an event on Thursday, Hochul praised the ruling and renewed criticism of the Trump administration for issuing the stop-work order just before Christmas, impacting thousands of workers.

“I’m sick and tired of having to go to court time and time and time again to stop these decisions,” she said in remarks. “They’re designed to do nothing other than hurt workers, hurt our states, hurt our economy and hurt our energy future.”

Leave a Comment





Latest News Stories

Screenshot 2025-05-04 at 3.03.49 PM

County Accepts $377,000 Developer Donation for Romeo Road Improvements

The Will County Public Works and Transportation Committee has accepted a $377,000 donation from a developer to fund roadway improvements at the southeast corner of Romeo Road and Weber Road...
Screenshot 2025-05-04 at 3.03.49 PM

Contracts Awarded for LED Signal Upgrades and Guardrail Maintenance

The Will County Public Works and Transportation Committee has approved contracts for two significant infrastructure maintenance projects: LED traffic signal upgrades and guardrail maintenance across the county. A contract for...
Screenshot 2025-05-04 at 3.03.49 PM

BRIEFS: Will County Public Works Projects

County Line Road Resurfacing Contract Awarded: The committee approved a $767,249 contract to Iroquois Paving Corporation for resurfacing County Highway 58 (County Line Road) from N5000 East Road east to...
Screenshot 2025-05-04 at 2.36.35 PM

County Approves Two Solar Energy Projects, Committee Discusses Zoning Challenges

The Will County Land Use and Development Committee approved two commercial solar energy projects Wednesday despite objections from the Village of Manhattan regarding one of the proposals. In a 6-1...
Screenshot 2025-05-04 at 2.36.35 PM

Committee Debates Easing Size Restrictions on Accessory Dwelling Units

Will County's Land Use and Development Committee is considering changes to its accessory dwelling unit (ADU) regulations that could provide more flexibility for homeowners looking to create additional living spaces...
Screenshot 2025-05-04 at 2.36.35 PM

“Tiny Homes” Status Creates Regulatory Confusion for County Officials

Will County officials are struggling to establish clear regulations for "tiny homes," with committee members expressing confusion over terminology and appropriate standards during Wednesday's Land Use and Development Committee meeting....
Screenshot 2025-05-04 at 2.36.35 PM

County Officials Begin Exploring Regulations for Small Modular Nuclear Reactors

Will County is beginning to explore potential regulations for small modular nuclear reactors (SMRs) after recent Illinois legislation allowed their development, planning staff told the Land Use and Development Committee...
Screenshot 2025-05-04 at 2.17.47 PM

Will County Land Use News Briefs

Truck Terminal Proposal Tabled for Traffic Study: The committee tabled a special use permit request from Litmax Multi-Service Inc. for a truck terminal in New Lenox Township at 22645 Cherry...
Screenshot 2025-05-04 at 2.57.14 PM

County Moves Forward with Veterans Building Renovations, Questions Arise on Pace Building Plans

Will County's Capital Improvements Committee received updates Tuesday on multiple county facility projects, including progress on the Copperfield Drive building renovations for veterans services, while discussions revealed questions about the...
Screenshot 2025-05-04 at 2.57.14 PM

County Continues Efforts to Reduce Leased Office Space Footprint

Will County officials reported Tuesday that efforts to consolidate county operations in owned facilities are continuing to reduce the county's leased office space footprint, with further reductions expected when the...
Screenshot 2025-05-04 at 2.57.14 PM

County Reports Significant Cost Savings Through In-House Facility Projects

Will County is achieving substantial cost savings by completing facility improvement projects with in-house staff rather than contracting the work out, according to a presentation to the Capital Improvements Committee...
Screenshot 2025-05-04 at 2.50.36 PM

County Legislative Committee Endorses Electronic Recycling Bill, Reviews Transit Governance

The Will County Legislative Committee voted Thursday to support proposed state legislation that would extend and expand Illinois' electronic recycling program, while also reviewing potential changes to regional transit governance...
Screenshot 2025-05-04 at 2.57.14 PM

Will County Capital Improvements News Briefs

Courthouse Scaffolding Expected to Come Down Soon: Scaffolding on one corner of the Will County Courthouse should be removed within the next two weeks, pending reports from material scientists. "We're...
Screenshot 2025-05-04 at 2.44.33 PM

County Finance Committee Advances Proposal for Elected Official Pay Raises After 20-Year Freeze

The Will County Finance Committee voted Thursday to advance a proposal that would provide the first salary increases for countywide elected officials and county board members in nearly two decades....
Screenshot 2025-05-04 at 2.50.36 PM

Will County Committee Debates Process for Taking Positions on State Legislation

Will County Legislative Committee members engaged in substantial discussion Thursday about how the committee should review and take positions on state legislation, with several members expressing concerns about the process...