Meeting Summary
The Will County Board Public Works & Transportation Committee met on Tuesday, January 6, 2026, to discuss a range of infrastructure projects and contracts. The meeting was dominated by a debate over a proposed agreement with the Illinois State Police to install license plate reading cameras on county roads, which resulted in a vote to postpone the decision for one month. In other business, the committee moved forward with significant investments in roadway safety, including a $18.8 million bridge project for Lorenzo Road and a $3.2 million engineering contract for Mills Road.

The committee also engaged in a strategic discussion regarding the potential takeover of a section of Kankakee County Line Road to ensure better long-term maintenance and bridge safety for the southern portion of the county. Routine maintenance contracts and access permits were also approved during the session.

News Briefs

Laraway Road Access Granted:
The committee approved a request from Northern Builders for two new access points on Laraway Road (County Highway 74). The access points will serve a new development located approximately 1,100 feet west of Gougar Road and directly south of Gougar Road in County Board District 2. This approval allows for ingress and egress for new businesses planned for the site.

Bluff Road Project Initiated:
Director of Transportation Jeff Ronaldson presented a proposal to initiate a reconstruction project for Bluff Road (County Highway 77) in Channahon, between US Route 6 and the I-55 West Frontage Road. The project aims to reconstruct the aging roadway to current standards, including curb and gutter and potential turn lanes. The committee concurred with moving forward to secure a negotiated contract for engineering services.

Tree Removal Contract Awarded:
The committee confirmed the award of a $70,336.50 contract to Homer Tree Service, Inc. for countywide tree removal. The project involves removing trees within the existing right-of-way of various county highways across all board districts. Work is estimated to begin in February 2026 and conclude by March 31, 2026.

Bridge Inspection Services Approved:
A professional services agreement was approved with Willett, Hofmann & Associates for the 2026 biennial bridge inspections. The contract, valued at $140,220.00, covers the inspection of various structures throughout Will County Districts 1 through 11 to ensure safety and compliance with state and federal regulations.

Leave a Comment





Latest News Stories

WCO LEG 8.5.2

Will County Leglislative Committee Opposes Federal Push for Heavier, Longer Trucks

ARTICLE SUMMARY: The Will County Board's Legislative Committee unanimously passed a resolution opposing any federal legislation that would increase the size and weight limits for commercial trucks on national roadways. Will...
WCO Public Safety.2

Will County Reports Progress in Opioid Fight, Highlights New FDA Labeling Rules

Article Summary: Will County is seeing a reduction in opioid overdose deaths and is expanding access to the reversal drug Narcan, health officials reported. The department also drew attention to...
WCO Cap Imp 8.5.4

In-House Staff Completes Major Renovations at Will County Adult Detention Facility

ARTICLE SUMMARY: Maintenance staff at the Will County Adult Detention Facility recently completed extensive renovations in-house, including a new control center and the full restoration of a 48-cell housing unit, saving...
Land use 8.5.25

Will County Advances Truck Repair Facility Plan on Manhattan Road Despite Resident Objections

Article Summary: A proposal to rezone nearly 14 acres on Manhattan Road for a truck repair facility advanced after receiving a recommendation for approval from the Will County Land Use...
WCO P&Z 8.12.1

PZC Grants Variance for Oversized Garage in Joliet Township, Reversing Staff Recommendation

Article Summary: The Will County Planning and Zoning Commission unanimously approved a variance for a Joliet Township homeowner to build a garage addition that exceeds the county's size limits. The...
WCO P&Z Aug 5.5

Will County Public Works Committee Approves Over $1.1 Million in New Agreements for 80th Avenue Project

ARTICLE SUMMARY: The Will County Public Works & Transportation Committee authorized two agreements totaling over $1.1 million for the ongoing reconstruction and widening of 80th Avenue between 191st and 183rd Streets....
Meeting Briefs

Meeting Summary and Briefs: Will County Board Legislative Committee for August 5, 2025

The Will County Board’s Legislative Committee focused on shaping its advocacy efforts at both the state and federal levels during its August 5 meeting. The primary discussion centered on crafting...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Capital Improvements & IT Committee for August 5, 2025

The future of several key county facilities dominated the Will County Capital Improvements & IT Committee meeting on Tuesday. A major topic of discussion was the ongoing buildout of the...
Meeting Briefs

Meeting Summary and Briefs: Will County Land Use & Development Committee for August 7, 2025

The Will County Land Use & Development Committee tackled two contentious zoning cases during its August 7 meeting, denying a special use permit for a landscaping business in a residential...

Meeting Summary and Briefs: Will County Planning and Zoning Commission for August 5, 2025

The Will County Planning and Zoning Commission backed two controversial projects at its August 5 meeting, unanimously approving a large-scale landscaping business on a residential lot in DuPage Township despite...
Meeting Briefs

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for August 5, 2025

The Will County Public Works & Transportation Committee received a detailed presentation on "Our Way Forward 2050," a new 25-year long-range plan designed to guide the region's transportation infrastructure through...
Beecher Fire Protection District graphic.1

Beecher Fire District Promotes Three to Lieutenant/Paramedic

Article Summary: The Beecher Fire Protection District Board of Trustees unanimously promoted Carm Welsh, Marci DuBois, and Bryce Budimir to the rank of Lieutenant/Paramedic at its June 26 meeting. The...
Beecher Fire Protection District graphic.2

Fire Board Approves $13,895 Landscaping Contract for Station

Article Summary: The Beecher Fire Protection District Board of Trustees has awarded a $13,895 contract to Tadpole for a significant landscaping project at the fire station. The decision was made...
Meeting-Briefs

Meeting Summary and Briefs: Beecher Fire Protection District Board of Trustees for June 26, 2025

The Beecher Fire Protection District Board of Trustees made several key decisions at its June 26 meeting, highlighted by the promotion of three members to leadership positions and the approval...
Meeting-Briefs

Meeting Summary: Peotone School District 207-U for July 21, 2025

District Weighs Budget Cuts vs. More Debt: Peotone schools must create a state-mandated deficit reduction plan to address a recurring ~$2 million operating shortfall. The Board of Education is debating whether...