will county board meeting graphic.5

Prairie View Landfill Expansion Plans Take Shape as Consultants Navigate Design Challenges

Spread the love

Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: Geologic Associates presented a detailed status update on the proposed expansion of the Prairie View Landfill, outlining a dual approach that includes both vertical and horizontal growth. Consultants revealed a complex engineering solution involving a diversion berm and pulley system to manage leachate collection as new cells are constructed over existing infrastructure.

Landfill Expansion Key Points:

  • Expansion Strategy: The county is pursuing both vertical (upward) and horizontal (outward) expansion simultaneously.

  • Engineering Challenge: A significant hurdle involves maintaining leachate collection from the existing landfill while building new cells on top of it. Consultants designed a 94-foot-wide phase delineation berm and a “pipe within a pipe” pulley system to address this.

  • Soil Pile Obstacle: A large soil stockpile remains on site without a current plan for relocation, necessitating the dual-track design approach. Discussions with neighboring Local 150 regarding land acquisition have stalled but may be restarted.

The Will County Board Landfill Committee received a comprehensive update on Tuesday, January 13, 2026, regarding the ongoing design and planning for the Prairie View Landfill expansion.

Marty Fallon of Geologic Associates, the county’s landfill consultant, presented the latest engineering schematics, highlighting the project’s complexity. The expansion strategy involves a “piggyback” design where new landfill cells will be constructed partially on top of the existing waste mound.

“One of the challenges that we’ve had here with this horizontal expansion… we’re going to cover up a portion of the existing landfill,” Fallon explained. This creates a conflict with the existing leachate collection sumps.

To solve this, consultants have designed a massive 94-foot-wide “phase delineation berm” to separate the old and new sections. Within this berm, they plan to install a specialized diversion system featuring a 24-inch pipe housing a smaller 12-inch pipe with a pulley mechanism. This “straw within a straw” design will allow pumps to be retrieved for maintenance even after they are buried under tons of new waste.

Fallon also addressed a critical logistical issue: a large soil stockpile currently occupying space needed for the horizontal expansion. “Currently we don’t have a plan to move that,” Fallon stated, noting that off-site relocation is required.

This issue sparked discussion about reviving negotiations with Local 150, which owns adjacent property. Chuck Helston, outside counsel for the county, confirmed that previous confidential discussions had stalled but expressed willingness to re-engage at the committee’s direction.

Committee Chair David Oxley suggested a creative solution for the union: “Perhaps they could use that as training for their employees and their apprentices to move that dirt to that pile.” Helston agreed to raise the idea again.

The expansion is not expected to disrupt operations at the adjacent Renewable Natural Gas (RNG) plant. “It won’t be any disruption to the [RNG plant] none,” Fallon assured the committee.

Leave a Comment





Latest News Stories

Beecher Fire Protection District graphic.3

Beecher Fire District Pledges $2,000 to Local Emergency Management Agency

Beecher Fire Protection District Meeting | August 28, 2025 Article Summary: The Beecher Fire Protection District Board of Trustees voted to provide $2,000 in financial support to the Beecher Emergency Management...
Beecher Fire Protection District graphic.1

Beecher Fire District to Reduce Contracted Paramedic Staffing

Beecher Fire Protection District Meeting | August 28, 2025 Article Summary: The Beecher Fire Protection District Board of Trustees has approved an amendment to its contract with Metro Paramedic Services, reducing...
Beecher Fire Protection District graphic.4

Beecher Fire District Explores Solar Farm Partnership with Letter of Intent

Beecher Fire Protection District Meeting | August 28, 2025 Article Summary: The Beecher Fire Protection District is exploring a potential partnership for a commercial solar energy facility after its Board of...
Meeting Briefs

Meeting Summary and Briefs: Washington Township Board of Trustees for August 4, 2025

The Washington Township Board of Trustees focused on employee compensation and infrastructure needs during its August 4 meeting, approving a comprehensive overhaul of its wage structure and job descriptions. The...
washington township graphic.2

Washington Township Board Backs Special Use Permit for Barn on Corning Road

Article Summary: The Washington Township Board of Trustees will support a resident's request for a Special Use Permit to construct a barn on a 5-acre property on E. Corning Road....
Meeting Briefs

Meeting Summary and Briefs: Beecher Public Library District Board for August 19, 2025

The Beecher Public Library District Board of Trustees addressed major financial milestones and a significant leadership change at its August 19 meeting. The board unanimously approved the final budget for...
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...
diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
washington township graphic.3

Failed Repair Forces Replacement of 25-Year-Old Furnace at Washington Township Center

Article Summary: A failed repair attempt on the 25-year-old furnace at the Washington Township Center, which caused a fire alarm to activate, has prompted the board to authorize a full...
OLYMPUS DIGITAL CAMERA

Beecher Library Board Approves Budgets for Current and Upcoming Fiscal Years

Article Summary: The Beecher Public Library District Board of Trustees formally approved its final budget for the current 2024-2025 fiscal year and, following a public hearing, passed the new budget...
Meeting Briefs

Meeting Summary and Briefs: Beecher School District 200-U for September 10, 2025

The Beecher School District 200-U Board of Education approved its annual budget, appointed a new member, and greenlit a cosmetic upgrade for the high school during its meeting on September...
Meeting Briefs

Meeting Summary and Briefs: Village of Beecher Board of Trustees for September 22, 2025

The Beecher Village Board addressed persistent structural issues at the new Public Safety Facility during its meeting on September 22. After a report confirmed that new roof leaks have appeared...