Will County Board Graphic.03

Landfill Committee Advances Plan to Purchase Fourth Compressor for RNG Plant

Spread the love

Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable Natural Gas (RNG) facility. The $1.8 million investment aims to reduce downtime and increase revenue, despite concerns about funding sources and timing.

RNG Plant Key Points:

  • Downtime Costs: Data shows that feed compressor failures account for nearly 36% of plant downtime, costing the county an estimated $600,000 annually in lost revenue.

  • Proposed Solution: Installing a fourth compressor would ensure three units are always operational, maximizing gas production and revenue. The estimated cost is $1.8 million with a 3-5 year return on investment.

  • Budget Concerns: The purchase was not included in the current fiscal year budget. Officials discussed using remaining funds from the previous year or splitting the cost across two budget cycles due to a 46-week lead time for the equipment.

Will County officials are taking steps to boost efficiency and revenue at the Prairie View Renewable Natural Gas (RNG) plant by pursuing the addition of a fourth feed compressor.

At the Landfill Committee meeting on Tuesday, January 13, 2026, Dave Hartke, Director of the Resource Recovery & Energy Division, presented data highlighting the financial impact of equipment failures. The facility’s three existing compressors are the primary cause of outages, leading to significant revenue losses.

“If we have three feed compressors operating at all times… we’re going to be producing closer to 27 to 2900 mm BTUs,” Hartke explained, noting this would allow the plant to hit higher revenue tiers faster each month.

The proposed fourth unit, estimated at $1.8 million fully installed, would provide redundancy. However, the plan faced scrutiny regarding its financing. Board Member Sherry Newquist questioned the timing, noting, “This kind of stuff is so much easier to deal with during the budget process.”

Hartke admitted the request was not in the original budget due to a prior focus on austerity. “I wasn’t quite expecting the response… that we should move forward with it,” he said, referencing earlier informal discussions with committee leadership.

Despite the budget hurdle, the committee saw the long-term value. With a 46-week lead time for the equipment, Finance Director Marcy indicated the cost could potentially be split across two fiscal years.

Board Member Jim Richmond emphasized the need for a deeper analysis before cutting a check. “This is a massive business decision… We need to actually look at that plant and make sure that it is spec’d properly from the front door to the back door,” Richmond said.

Ultimately, the committee voted unanimously to authorize staff to proceed with obtaining firm engineering costs and a project plan, which will then be brought back for final financial approval.

Leave a Comment





Latest News Stories

Meeting Briefs

In Brief: Ordinance Review Committee Actions

The Will County Ad-Hoc Ordinance Review Committee met June 10 to continue its comprehensive update of the county code. Here are some of the key actions and discussions: Court Fees...
Beecher Graphic.1

Beecher Approves Over $35,000 for Emergency Repairs to Well #5

Article Summary: The Beecher Village Board unanimously approved more than $35,000 in emergency repairs for Well #5 after a recent video inspection revealed significant corrosion, mineral buildup, and a failing...
Beecher Graphic.3

Beecher to Seek Legal Advice on Chronic Nuisance Property After Years of Complaints

Article Summary: The Beecher Village Board is exploring stronger legal options, including a possible circuit court injunction, to address a chronic nuisance property on Catalpa Street. A neighboring resident voiced...
Beecher Graphic.4

New Beecher Public Safety Facility Nears Completion Amidst Minor Setbacks

Article Summary: Beecher's new Public Safety Facility is nearing the final stages of completion, with the parking lot recently paved and striped, but the village is now addressing a potential...
Beecher Graphic.5

Beecher Pushes Forward with Downtown Enhancement Projects

Article Summary: The Village of Beecher is advancing several initiatives to support its downtown business district, including the installation of a new wayfinding sign, the creation of a formal application...
Meeting Briefs

Meeting Summary and Briefs: Village of Beecher Board of Trustees for June 9, 2025

The Beecher Village Board of Trustees took decisive action on critical infrastructure and grappled with a chronic public nuisance issue at its meeting on June 9. The board unanimously approved...
Will County Jail

Will County Jail Faces Major Staffing Crisis as 70 Employees Eligible to Retire by 2030

County officials warn of potential budget impact as adult detention facility grapples with unprecedented turnover Will County's adult detention facility is heading toward a staffing crisis that could significantly impact...
will county board.3

Will County Health Department Reports Sharp Decline in Overdose Deaths

2025 fatalities running 40% lower than previous year, officials attribute success to expanded Narcan distribution Will County is experiencing a significant reduction in overdose deaths, with 2025 fatalities running 40%...
will county board

Solar Project Extensions Approved as Industry Faces Permitting Delays

Three solar energy projects received 180-day extensions from Will County's Land Use & Development Committee Thursday as developers continue working through lengthy permitting processes with utility companies and other agencies....
will county board.3

Committee Approves Truck Terminal Despite Residential Concerns

A Monee Township truck terminal received approval from Will County's Land Use & Development Committee Thursday despite concerns about its proximity to residential areas. The committee voted 5-1 to approve...
will county board

Will County Health Department Faces Funding Uncertainty as Federal Grants Under Review

Multiple revenue sources threatened as department seeks legislative support for public health programs Will County Health Department officials are closely monitoring potential federal funding cuts that could impact multiple programs...

Will County Land Use Meeting Briefs

LAND USE ACTIONS Accessory Dwelling Unit Rules Modified: The committee recommended approval of text amendments allowing accessory dwelling units to exceed current building area limitations in certain circumstances. The changes...
will county board.2

Public Health and Safety Committee Meeting Briefs

Sunny Hill Nursing Home Tour Praised: Committee members who attended the May 9 tour of Sunny Hill Nursing Home praised the facility's condition and operations. Member Raquel Mitchell called it...
Medicaid-logo

Federal Reconciliation Bill Targets Medicaid, SNAP Programs

Will County Legislators Briefed on Potential Local Impacts Federal legislation making sweeping cuts to Medicaid and food assistance programs could significantly impact Will County residents and services, county legislators learned...
will county board.2

Will County Approves Modified $756 Million Transportation Plan Despite Terminology Debate

Will County's Public Works and Transportation Committee approved a five-year, $756 million transportation improvement plan on June 3, but not before a heated debate over whether to call it a...