Landfill Committee Advances Plan to Purchase Fourth Compressor for RNG Plant

Spread the love

Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable Natural Gas (RNG) facility. The $1.8 million investment aims to reduce downtime and increase revenue, despite concerns about funding sources and timing.

RNG Plant Key Points:

  • Downtime Costs: Data shows that feed compressor failures account for nearly 36% of plant downtime, costing the county an estimated $600,000 annually in lost revenue.

  • Proposed Solution: Installing a fourth compressor would ensure three units are always operational, maximizing gas production and revenue. The estimated cost is $1.8 million with a 3-5 year return on investment.

  • Budget Concerns: The purchase was not included in the current fiscal year budget. Officials discussed using remaining funds from the previous year or splitting the cost across two budget cycles due to a 46-week lead time for the equipment.

Will County officials are taking steps to boost efficiency and revenue at the Prairie View Renewable Natural Gas (RNG) plant by pursuing the addition of a fourth feed compressor.

At the Landfill Committee meeting on Tuesday, January 13, 2026, Dave Hartke, Director of the Resource Recovery & Energy Division, presented data highlighting the financial impact of equipment failures. The facility’s three existing compressors are the primary cause of outages, leading to significant revenue losses.

“If we have three feed compressors operating at all times… we’re going to be producing closer to 27 to 2900 mm BTUs,” Hartke explained, noting this would allow the plant to hit higher revenue tiers faster each month.

The proposed fourth unit, estimated at $1.8 million fully installed, would provide redundancy. However, the plan faced scrutiny regarding its financing. Board Member Sherry Newquist questioned the timing, noting, “This kind of stuff is so much easier to deal with during the budget process.”

Hartke admitted the request was not in the original budget due to a prior focus on austerity. “I wasn’t quite expecting the response… that we should move forward with it,” he said, referencing earlier informal discussions with committee leadership.

Despite the budget hurdle, the committee saw the long-term value. With a 46-week lead time for the equipment, Finance Director Marcy indicated the cost could potentially be split across two fiscal years.

Board Member Jim Richmond emphasized the need for a deeper analysis before cutting a check. “This is a massive business decision… We need to actually look at that plant and make sure that it is spec’d properly from the front door to the back door,” Richmond said.

Ultimately, the committee voted unanimously to authorize staff to proceed with obtaining firm engineering costs and a project plan, which will then be brought back for final financial approval.

Leave a Comment





Latest News Stories

WCO Landfill 8.5.25.1

Will County Receives Detailed Update on Landfill Expansion Investigation

Article Summary: The Will County Landfill Committee received a comprehensive technical update on the site investigation for the planned horizontal expansion of the county landfill, confirming the project remains on...
WCO Landfill 8.5.25.2

Report Finding Few Trucks Littering Sparks Debate on Cleanup Responsibility

Article Summary: A Will County report found that a very small percentage of waste-hauling trucks are the source of litter on roadways near the county landfill, sparking a debate among...
Meeting Briefs

Meeting Summary and Briefs: Will County Landfill Committee for August 7, 2025

The Will County Landfill Committee on Thursday heard a detailed technical update on the ongoing investigation for the county landfill expansion, confirming that the complex project remains on schedule. Consultants...
Ad Hoc.8.12.25.3

Water Well, Waste Hauler Ordinances Updated by Will County Committee

Article Summary: The Will County Ad-Hoc Ordinance Review Committee approved updates to chapters governing water well permits and waste hauler reporting, forwarding them to the Executive Committee for consideration. Changes...
Beecher Graphic.3

Beecher to Draft Ordinances Regulating Scooters and Fishing in Village Ponds

Article Summary: The Beecher Village Board is moving to create new local laws governing the use of electric scooters and fishing in village-owned ponds. Citing safety concerns and resident inquiries,...
Beecher Graphic.4

Beecher’s National Night Out Draws Large Crowd to New Police Station

Article Summary: Beecher's National Night Out was a resounding success, drawing a large and enthusiastic crowd to the new Public Safety Facility for the first time. The August 5 event...
Meeting-Briefs

Meeting Summary and Briefs: Village of Beecher Board of Trustees for July 28 & August 11, 2025

Over its last two meetings, the Beecher Village Board took significant steps on fiscal policy, new local regulations, and community appointments. On July 28, the board unanimously passed an ordinance...
beecher ilinois school board graphic.4

Finance Committee: Beecher Schools Project Balanced Budget, Earmark Funds for Major Projects

Article Summary: The Beecher School District 200-U Finance Committee reviewed a preliminary Fiscal Year 2026 budget that projects a narrow surplus, a significant turnaround from last year's initial deficit forecast....
WCO Finance Aug 5.1

Will County Health Department Seeks $1 Million to Avert ‘Drastic’ Service Cuts from Expiring Grants

ARTICLE SUMMARY: The Will County Health Department is requesting an additional $1 million in county funding for its 2026 budget to prevent the elimination of 11 critical staff positions, warning...
WCO Cap Imp 8.5.1

Will County’s “First-in-Nation” Veterans Center to House Workforce Services, Sparking Debate

ARTICLE SUMMARY: The new Will County Veteran's Assistance & Support Center will also become the home for the county's Workforce Services department, a move officials say will save approximately $250,000 in...
WCO Finance Aug 5.2

Improved Vendor Service Creates $1.2 Million Shortfall in Sheriff’s Medical Budget

ARTICLE SUMMARY: The Will County Sheriff’s Office is facing a more than $1.2 million shortfall in its budget for inmate medical services, a problem officials attribute to an ironic cause:...
WCO P&Z Aug 5.1

Will County Public Works Committee Unveils 25-Year Transportation Plan, Projects $258 Million Gap

ARTICLE SUMMARY: Will County officials have presented "Our Way Forward 2050," a new long-range transportation plan that provides a 25-year vision for infrastructure projects while forecasting a $258 million shortfall in...
WCO Public Safety.4

Will County Animal Protection Services Seeks New Facility Amid “Gaping Wound” of Space Crisis

Article Summary: Will County Animal Protection Services is seeking approval for a new facility, telling a county committee that its current building is critically inadequate for housing animals, leading to...
WCO Cap Imp 8.5.2

Board Confronts Animal Services Crowding, Explores Future Facility Options

ARTICLE SUMMARY: Will County officials are grappling with an ongoing animal housing crisis that has overwhelmed the county’s Animal Protective Services facility, prompting discussions about expansion, new construction, or even repurposing...
WCO Finance Aug 5.3

Will County Board Members Demand Transparency in Cannabis Tax Fund Allocation

ARTICLE SUMMARY: A debate over transparency and process erupted at the Will County Board’s Finance Committee meeting regarding the distribution of local cannabis tax revenue. Board members called for more...