Will County Capital Improvements & IT Committee Meeting | Jan. 6, 2026
Article Summary: A malfunctioning elevator at the Will County Health Department has been repaired for approximately $18,000 to $20,000, avoiding a potential replacement cost of over $1 million. Facilities staff confirmed the unit is suitable for the building’s needs.
Facilities Key Points:
-
Repair Cost: The final repair bill is estimated between $18,000 and $20,000.
-
Cost Avoidance: Initial fears suggested a full replacement could have exceeded $1 million.
-
In-House Projects: Facilities staff saved money by framing and hanging judge photos at the courthouse internally.
-
Efficiency: The department completed over 750 work orders in the last month with a 98% completion rate.
JOLIET — A potentially budget-breaking elevator issue at the Will County Health Department was resolved for a fraction of the feared cost, Facilities Director William Fern reported to the Capital Improvements and IT Committee on Tuesday, Jan. 6, 2026.
During a facilities update, Chair Mica Freeman (D-Plainfield) requested the final cost for the elevator repair, noting that previous discussions had raised concerns about the unit’s suitability and the potential need for a total replacement.
“I think it was about $18,000 to $20,000,” Fern said.
Freeman noted this was significantly under the $30,000 to $40,000 estimates discussed previously, and far below the cost of a full replacement.
“Or the over million to replace, right?” Fern added. “So I think they got to the root cause of the issue from the initial install and were able to repair it.”
Fern confirmed that the existing elevator was deemed suitable for the space, eliminating the need for major construction.
In other facilities news, Fern highlighted a project at the Will County Courthouse where maintenance staff framed and hung photos of current and past judges on the third floor.
“Originally, we got a quote. It was pretty expensive. It was over like $18,000 for a contractor to do it,” Fern said.
By utilizing the Sheriff’s carpentry staff and county facilities personnel, the project was completed in-house for a “fraction of the cost.” However, Fern noted that a few photos were hung out of order and will be corrected.
Fern also reported that the department continues to operate efficiently, saving the county over $118,000 in evaporation credits on cooling towers at the courthouse to date.
Latest News Stories
Wheat price drop brings notable Thanksgiving savings for Illinois families
Illinois lawmaker calls FDA hormone therapy reversal ‘overdue’
September jobs report adds 119,000, steady unemployment
Indicted Florida congresswoman leaves committee leadership post
Existing home sales up 1.2% in October
Chip Roy calls for full pause on all U.S. immigration
Prosecutors defend indictment in Comey case after defense questions
IL Rep on congressmen trading: ‘We’re not going to take a pile of money to hell’
House axes provision letting senators sue over data surveillance
DoEd’s six new agency partnerships will give parents freedom, break up bureaucracy
Illinois quick hits: Officer shot report numbers down; Thanksgiving meal costs down
WATCH: Chicago activist testifies; Quinn’s millionaire surcharge; High SNAP error rate