Committee-Executive.Graphic

Executive Committee Advances $28.7 Million BNSF Bridge Project for Lorenzo Road

Spread the love

Will County Executive Committee Meeting | February 11, 2026

Article Summary: The Executive Committee approved an agreement with BNSF Railway to construct a grade separation bridge on Lorenzo Road in Wilmington. The railroad will contribute over $15 million toward the project and provide a one-time maintenance payment to the county.

Lorenzo Road Bridge Key Points:

  • Project: Construction of a grade separation bridge carrying Lorenzo Road (CH 80) over the BNSF Railroad tracks.

  • Location: 1.25 miles west of I-55 in County Board District 1.

  • Total Cost: The estimated total project cost is $28,717,523.80.

  • Railroad Contribution: BNSF will reimburse the county 100% of costs after the execution of ICC funds, up to a cap of $15,102,943.80.

  • Maintenance Fee: BNSF will pay Will County a one-time maintenance fee of $675,003.28 for the useful life of the overpass.

The Will County Board Executive Committee on Wednesday, February 11, 2026, approved Resolution 26-046, authorizing an agreement between the County and BNSF Railway for a major infrastructure project on Lorenzo Road.

The project involves constructing a bridge to separate the grade of Lorenzo Road (County Highway 80) from the BNSF rail line, located approximately 1.25 miles west of Interstate 55. The project aims to eliminate the at-grade crossing, improving safety and traffic flow in the heavy industrial corridor.

According to the agreement attached to the agenda, the total estimated cost of construction is $28,717,523.80. Under the terms of the deal, BNSF Railway will contribute significantly to the project. Once $12 million in Illinois Commerce Commission (ICC) funds are executed, BNSF will reimburse the county for remaining costs up to a cap of $15,102,943.80.

Additionally, the agreement stipulates that BNSF will provide a one-time lump sum payment of $675,003.28 to the county to cover future maintenance costs for the structure over its useful life. The county will be responsible for maintaining the roadway, bridge structure, and drainage.

The agreement requires the contractor to maintain strict safety clearances during construction, including 25 feet horizontally from the track centerline.

The measure was moved by Member Jacqueline Traynere and seconded by Member Denise Winfrey. It passed unanimously.

Beecher Weather Full forecast →
⚠️ Flood Watch issued June 11 at 12:39PM CDT until June 11 at 11:00PM CDT by NWS Chicago IL
Today Jun 10
Partly Sunny then Chance Showers And Thunderstorms
82° 59°

Partly Sunny then Chance Showers And Thunderstorms

💨 10 to 20 mph 💧 52%

Leave a Comment





Latest News Stories

Will County Board Graphic.02

Ad-Hoc Committee: Will County Sheriff’s Office to Acquire Decibel Meters for Noise Complaints

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 Article Summary: The Will County Sheriff's Office plans to purchase a fleet of certified decibel meters to accurately...
Beecher Graphic.3

Meeting Summary and Briefs: Village of Beecher Board of Trustees for March 9, 2026

Village of Beecher Board of Trustees Meeting | March 9, 2026 The Village of Beecher Board of Trustees met on Monday, March 9, 2026, to handle a variety of municipal...
Will County Public Works Committee

Will County Public Works Approves Access for 56-Acre Truck Services Hub on Manhattan-Monee Road

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee on Tuesday approved a request to allow commercial ingress...
Will County P&Z Logo Planning Zoning

Crest Hill Homeowner Granted Side Yard Setback Variance for Accessible Addition

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission approved a side yard setback variance for a Crest Hill...
will county Committee-Legislative.Graphic

State Update: County Officials Raise Alarms Over Pritzker’s ADU Zoning Push and Data Center Tax Breaks

Legislative Committee Meeting | March 2026 Article Summary: During a state legislative update, Will County Board members expressed deep concerns over Governor J.B. Pritzker's continued push to mandate Accessory Dwelling Units...
Will County Public Works Committee

Committee Approves $317K Guardrail Maintenance Contract Amid Discussion on Installation Dangers

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: Will County officials approved an annual guardrail maintenance contract Tuesday while addressing national concerns over improperly installed...
Will County Board Graphic.03

Will County Approves Diamond Enterprise Zone Expansion to Support $355 Million Energy Investment

Will County Executive Committee Meeting | March 12, 2026 Article Summary: The Will County Executive Committee unanimously approved ordinances expanding the Diamond Enterprise Zone to include the Village of Braceville. The...
will county Committee-Legislative.Graphic

Federal Update: DHS Shutdown, War Powers, and Housing Legislation Dominate Washington

Legislative Committee Meeting | March 3, 2026 Article Summary: Will County's federal lobbyists briefed the Legislative Committee on a turbulent week in Washington, D.C., highlighting the passage of a major bipartisan...
Will County Finance Logo

Will County Corporate Revenues Surpass Expectations, Igniting Debate Over Delinquent Tax Sales

Will County Finance Committee Meeting | March 3, 2026 Article Summary: A routine review of the county’s year-end corporate fund revealed that revenues exceeded budgeted expectations by millions, largely driven by...
Will County Public Works Committee

Meeting Summary and Briefs: Will County Public Works and Transportation Committee for March 3, 2026

Will County Public Works and Transportation Committee Meeting | March 3, 2026 The Will County Public Works and Transportation Committee met on Tuesday, March 3, advancing millions of dollars in...
solar panels photovoltaics in solar farm

Will County Grants Extensions for Seven Solar and Commercial Projects Amid Permitting Delays

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: The Will County Land Use and Development Committee approved a slate of extensions for seven previously authorized...
Will County Board Graphic.03

Will County Committee Postpones Liquor, Ad-Hoc Committee: Gaming, and Tobacco Ordinance Updates Amid Extensive Revisions

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 Article Summary: A Will County Board committee paused the advancement of major updates to the county's liquor, video...
Beecher Graphic.1

Beecher Village Board Approves Street Sweeping Contract and State Right-of-Way Resolution

Village of Beecher Board of Trustees Meeting | March 9, 2026 Article Summary: The Beecher Village Board approved a $6,200 contract for comprehensive commercial street sweeping to maintain environmental compliance,...
Beecher Elementary school Graphic

Beecher Elementary Principal Resigns Amid Slew of Personnel and Contract Approvals

Beecher Board of Education Meeting | March 11, 2026 Article SummaryBeecher School District 200U approved a slate of personnel changes, most notably accepting the resignation of Elementary School Principal Nicole...
solar panels photovoltaics in solar farm

Land Use Committee Approves 4.98-Megawatt Solar Facility on Eagle Lake Road Near Peotone

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: Reversing a deadlocked Planning and Zoning Commission, the Will County Land Use and Development Committee unanimously approved...