Will County Board Graphic.03

Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Beecher Weather Full forecast →
⚠️ Flood Watch issued June 10 at 6:54PM CDT until June 11 at 4:00AM CDT by NWS Chicago IL
Wed Jun 10
Partly Sunny then Slight Chance Showers And Thunderstorms
88° 60°

Partly Sunny then Slight Chance Showers And Thunderstorms

💨 10 to 20 mph 💧 15%

Leave a Comment





Latest News Stories

U.S. to build nuclear reactor on Moon by 2030, cost unknown

U.S. to build nuclear reactor on Moon by 2030, cost unknown

By Brett RowlandThe Center Square The U.S. plans to build a nuclear reactor on the moon by 2030 to prepare for future missions to Mars. The National Aeronautics and Space...
WATCH: Gov. Polis calls out Republicans in State of the State

WATCH: Gov. Polis calls out Republicans in State of the State

By Elyse ApelThe Center Square Colorado Gov. Jared Polis delivered his last State of the State to a joint session of the Colorado General Assembly on Thursday. In his speech,...
Republican senators introduce bill to address childcare, immigration fraud

Republican senators introduce bill to address childcare, immigration fraud

By Bethany BlankleyThe Center Square U.S. senators, led by U.S. Sen. John Cornyn, R-Texas, have introduced a bill to amend federal law to address federally funded childcare provider fraud. The...
More than $1 billion spent on noncitizen hospital costs in fiscal 2025

More than $1 billion spent on noncitizen hospital costs in fiscal 2025

By Bethany BlankleyThe Center Square Taxpayer-funded medical costs for noncitizens at Texas hospitals totaled more than $1 billion last year, according to newly released state data. The data spans ten...

IL Senate GOP: Pritzker, not Trump, raised power bills

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Illinois Senate Republicans say Gov. J.B. Pritzker is wrong to blame President Donald Trump for high electric...
SC weighs whether Amazon must pay workers for mandatory COVID screenings

SC weighs whether Amazon must pay workers for mandatory COVID screenings

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – The Illinois Supreme Court is considering whether Amazon must compensate warehouse workers for time spent waiting...
Federal judge allows New York wind project to proceed

Federal judge allows New York wind project to proceed

By Chris WadeThe Center Square A federal judge has given a green light for construction to resume on New York's largest offshore wind project that was abruptly shut down by...
Goodlander faces federal probe over ‘illegal orders’ video

Goodlander faces federal probe over ‘illegal orders’ video

By Chris WadeThe Center Square Democratic New Hampshire Rep. Maggie Goodlander says she is being investigated by federal prosecutors for participating in a video message urging service members to refuse...
Pennsylvania lawmakers criticize violent ICE encounters

Pennsylvania lawmakers criticize violent ICE encounters

By Christina LengyelThe Center Square With ongoing protests across the commonwealth over the actions of the Department of Homeland Security’s Immigration and Customs Enforcement, or ICE, 18 Pennsylvania legislators have...
WATCH: Tax increase talk at Statehouse; Bost’s election lawsuit against Illinois wins standing

WATCH: Tax increase talk at Statehouse; Bost’s election lawsuit against Illinois wins standing

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square's Greg Bishop discusses the status of...
Illinois Quick Hits: Indiana governor 'working hard' to attract Bears

Illinois Quick Hits: Indiana governor ‘working hard’ to attract Bears

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Indiana Gov. Mike Braun says the Chicago Bears noticed that the Hoosier state is open for business....
Will County Logo Graphic

Meeting Summary and Briefs: Capital Improvements & IT Committee for January 6, 2026

Capital Improvements & IT Committee Meeting | January 6, 2026 Overall Meeting SummaryThe Will County Board Capital Improvements and IT Committee met on Tuesday, January 6, 2026, to discuss facility...
Beecher Graphic.1

Public Works Shifts Focus to Snow Removal; Spring Leaf Collection Promised

Village of Beecher Board Meeting | January 12, 2026 Article Summary: Public Works Superintendent Matt Conner informed the board that crews are finishing the final leaf collection of the season...
Will County Board Graphic.04

Public Works Committee: $18.8 Million Contract Awarded for Lorenzo Road Bridge Over BNSF Railway

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Article Summary: A contract for nearly $18.9 million was confirmed for the construction of a new bridge carrying...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Public Health & Safety Committee for January 7, 2026

Will County Board Public Health & Safety Committee Meeting | January 7, 2026 Overall Meeting SummaryThe Will County Board Public Health and Safety Committee met on Wednesday, January 7, 2026,...