Will County Board Graphic.03

Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

Will County Board Graphic.04

County Approves Engineering for Peotone Road and Safety Upgrades

Will County Board Meeting | December 18, 2025 Article Summary: The County Board approved a Phase I engineering contract for improvements to Wilmington-Peotone Road and authorized an agreement for license...
Beecher Fire Protection District

Sprinkler System Helps Contain Christmas Eve Fire at Beecher Banquet Facility

BEECHER, Ill. — A commercial fire at a Beecher banquet facility was quickly brought under control on Christmas Eve, thanks in large part to a properly functioning automatic sprinkler system,...
Beecher Graphic.3

John Galvin Sworn In as New Police Chief

Beecher Village Board Meeting | December 22, 2025 Article Summary: Former Country Club Hills Police Chief John Galvin was officially sworn in as the new Beecher Police Chief, succeeding Terry...
Will County Board Graphic.01

Monee Solar Farm Projects Granted Extensions

Will County Board Meeting | December 18, 2025 Article Summary: The Will County Board granted six-month extensions for two special use permits related to commercial solar energy facilities in Monee...
Sufyan Farhan

Frankfort Man Arrested in Gas Station Robbery Found Hiding in McDonald’s Restroom

Article Summary: Sufyan Farhan, 27, was arrested on December 21 following an armed robbery at a Frankfort Circle K. Deputies located the suspect hiding in a nearby McDonald's restroom after...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Executive Committee for December 11, 2025

Will County Board Executive Committee Meeting | December 11, 2025 Overall Meeting SummaryThe Will County Board Executive Committee met on Thursday, December 11, 2025, tackling a diverse agenda that included...
Beecher Graphic.3

Residents Lodge Complaints Regarding Truck Noise

Beecher Village Board Meeting | December 22, 2025 Article Summary: Residents from the Charity Point Townhomes voiced concerns to the Village Board regarding excessive noise and fumes from refrigerated semi-trucks...
Planning & Zoning Graphic.4

New Lenox Homeowner Granted Variance for 4,000-Square-Foot Accessory Space

Will County Planning and Zoning Commission Meeting | December 16, 2025 Article Summary: A New Lenox homeowner received approval to build a large pole barn that exceeds the county's size limits...
Will County Board Graphic.03

County Expands Paratransit Services, Board Members Question Long-Term Funding

Will County Board Meeting | December 18, 2025 Article Summary: The Will County Board approved an intergovernmental agreement with Pace to expand paratransit services county-wide for seniors and residents with...
Beecher Graphic.1

Village Approves Agreement with Solar Energy Company

Beecher Village Board Meeting | December 22, 2025 Article Summary: The Beecher Village Board approved a Community Benefit Agreement with a solar energy developer that includes a $100,000 donation to...
Will County Board Graphic.02

Mental Health Board Updates Committee on 2026 Grant Cycle and Funding Priorities

Will County Board Executive Committee Meeting | December 11, 2025 Article Summary: The Will County Community Mental Health Board provided a quarterly update, outlining the timeline and strategic priorities for...
Beecher Police released images of the suspect-photo courtesy the Beecher Police Department.

Beecher Police Investigate Attempted Armed Robbery, Seek Public’s Help

BEECHER, Ill. — Beecher police are investigating an attempted armed robbery reported Friday evening at Silver Screen Vapes and are asking residents to review security camera footage that may help...
Will County P&Z Logo Planning Zoning

PZC Approves Homer Township Landscape Business Despite Neighbor Concerns; Adds Berm Condition

Will County Planning and Zoning Commission Meeting | December 16, 2025 Article Summary: The Will County Planning and Zoning Commission approved a special use permit for a new landscape business on...
Chicago council, 'starting to legislate,' sends $16.7 billion budget to mayor

Chicago council, ‘starting to legislate,’ sends $16.7 billion budget to mayor

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The Chicago City Council has approved a $16.7 billion budget for 2026 and sent it to Mayor...
Hegseth promises to fix barracks, but work could take time

Hegseth promises to fix barracks, but work could take time

By Brett RowlandThe Center Square Secretary of War Pete Hegseth has pledged to tackle longstanding issues with U.S. military barracks that have frustrated troops, lawmakers, and taxpayers for decades. In...