Will County Board Graphic.03

Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

WATCH: U.S. Rep. Miller live; Heated rhetoric in Congress; SNAP, ‘basic income’ debate

WATCH: U.S. Rep. Miller live; Heated rhetoric in Congress; SNAP, ‘basic income’ debate

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square Editor Greg Bishop talks live with...
beecher ilinois school board graphic.5

Solution Found to Revive Broken Junior High Digital Sign

Beecher School Board Facilities Committee Meeting | November 24, 2025 Article Summary: The Facilities Committee received a report detailing a cost-effective solution to retrofit the non-functional digital sign at Beecher...
Beecher Graphic.1

Beecher Sets Schedule for Parade of Lights and Holiday Contests

Village of Beecher Meeting | November 24, 2025 Article Summary: The Beecher Village Board finalized the schedule for the upcoming Parade of Lights and the Holiday Lights Decorating Contest. Holiday...
beecher ilinois school board graphic.3

“Cheaper to Go Up”: Beecher Schools Discuss Vertical Expansion Concepts

Beecher School Board Facilities Committee Meeting | November 24, 2025 Article Summary: Facing potential future enrollment growth and high land costs, the Beecher School Board Facilities Committee discussed conceptual plans...
Beecher Graphic.2

Weather Delays Force Extension of Leaf Collection in Beecher

Village of Beecher Meeting | November 24, 2025 Article Summary: The Village of Beecher is extending its annual leaf collection program through mid-December due to recent snow and rain delays....
Weather-Winter

Beecher Digs Out from 12.4 Inches of Snow; Sub-Zero Cold Forecast for Friday

Article Summary: Beecher residents are clearing more than a foot of snow following a major weekend storm, while forecasters warn of a dangerous drop in temperatures and additional snowfall arriving...
Illinois rejects federal ‘no tax on tips’ rule, keeps state tax on tipped income

Illinois rejects federal ‘no tax on tips’ rule, keeps state tax on tipped income

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Illinois is not adopting the new federal “no tax on tips” provision, meaning tipped workers in...
Beecher Elementary school Graphic

Contractors Clash on Cause of Elementary School Leaks; Committee Weighs Window Replacement

Beecher School Board Facilities Committee Meeting | November 24, 2025 Article Summary: The Beecher School District 200-U Facilities Committee reviewed proposals for replacing windows at the Elementary School but paused...
Will County Board Graphic.01

Frankfort Turns to County for Wildlife & Dangerous Animal Control

Will County Board Meeting | November 2025 Article Summary: The Village of Frankfort has entered into a two-year agreement with Will County Animal Protection Services to handle calls regarding bats...
joliet junior college foundation

JJC Foundation Director Kristin Mulvey to Retire After 25 Years of Transformative Leadership

Joliet Junior College Meeting | November 12, 2025 Article Summary:Kristin Mulvey, the longtime Executive Director of Institutional Advancement and the JJC Foundation, was honored by the Board of Trustees as...
Attack foiled in Ft. Worth day before National Guard troops shot in WDC

Attack foiled in Ft. Worth day before National Guard troops shot in WDC

By Bethany BlankleyThe Center Square Another Afghan-related terrorist attack was foiled one day before two National Guardsmen were shot in Washington, D.C., federal authorites said Saturday. The alleged perpetrators were...
Hundreds of flights canceled in Chicago as winter storm wreaks havoc

Hundreds of flights canceled in Chicago as winter storm wreaks havoc

By Dan McCaleb | The Center SquareThe Center Square (The Center Square) – More than 1,000 flights were canceled or delayed at Chicago's airports Saturday as a winter storm threatened...

WATCH: IL legislator wants more transparency for taxpayer funded credit cards

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – A Democratic state legislator is looking to require more transparency for how local governments in Illinois use...
Beecher Graphic.3

Beecher Officials Review Recreational Fire Rules Following Smoke Complaints

Village of Beecher Meeting | November 24, 2025 Article Summary: Beecher Village President Marcy Meyer initiated a discussion regarding potential updates to the village's recreational fire ordinance following resident complaints...
Will County Logo Graphic

Crete “Group Care” Home Approved for Senior Living

Will County Board Meeting | November 2025 Article Summary: The Will County Board unanimously approved a special use permit for a senior group care home in Crete Township. The facility...