Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

Screenshot 2025-11-19 at 9.30.44 AM

Executive Committee Approves Appointments for Washington Township, Emergency Telephone Boards

Will County Board Executive Committee Meeting | November 13, 2025 Article Summary: The Will County Board Executive Committee on Thursday, November 13, 2025, recommended the approval of two key appointments, filling...
Trump signs bill to release Epstein files

Trump signs bill to release Epstein files

By Brett RowlandThe Center Square President Donald Trump signed a bill late Wednesday to release federal files related to former financier and convicted sex offender Jeffrey Epstein. After fighting the...
WATCH: Dysolve AI offers approach to dyslexia in schools

WATCH: Dysolve AI offers approach to dyslexia in schools

By Esther WickhamThe Center Square While education leaders search for breakthroughs in special education, one AI platform, Dysolve, claims it has found part of the answer. Dysolve AI, created by...
Pregnancy centers ‘crucial’ to national safety net, provide over $452M to families in 2024

Pregnancy centers ‘crucial’ to national safety net, provide over $452M to families in 2024

By Tate MillerThe Center Square Pregnancy centers in 2024 provided over $452 million in goods and services to women and families across the nation, while its client satisfaction rate rose...

WATCH: Dems leave hearing before minority group’s testimony on Biden border policies

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A member of a minority grassroots Chicago organization testified before the U.S. Senate Committee on the Judiciary...
Illinois quick hits: ICC approves smaller rate increases

Illinois quick hits: ICC approves smaller rate increases

By Jim Talamonti | The Center SquareThe Center Square ICC approves smaller rate increases The Illinois Commerce Commission has approved smaller utility rate hikes than the ones requested by Ameren...

WATCH: Ex-Illinois governor pushes for ‘millionaire’s surcharge’ amendment

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – The push continues to have voters if Illinois should be a 3% surcharge on millionaires. Former Illinois...
WATCH: Illinois continues work to reduce state’s high SNAP error rate

WATCH: Illinois continues work to reduce state’s high SNAP error rate

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – State agency officials continue to address the error rate with Illinois’ handling of federal food subsidies. During...

WATCH: Libertarian concerns persist as IL Sec of State announces IDs for Apple Wallet

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Digital IDs have gone live in Illinois, but libertarians say the move makes it easier for governments...
Illinois quick hits: Pritzkers meets the Pope; Broadview to close street outside ICE facility

Illinois quick hits: Pritzkers meets the Pope; Broadview to close street outside ICE facility

By Jim Talamonti | The Center SquareThe Center Square Pritzkers meets the Pope Gov. J.B. Pritzker says it was an honor for he and the first lady to meet with...
'Ghost projects' haunt power grid planners and taxpayers

‘Ghost projects’ haunt power grid planners and taxpayers

By Lauren Jessop | The Center Square contributorThe Center Square (The Center Square) – As the country braces for a surge in electricity demand driven by large energy users like...
WATCH: $10M campaign finance fine dropped; Digital ID unveiled, Chicagoans speak up

WATCH: $10M campaign finance fine dropped; Digital ID unveiled, Chicagoans speak up

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square Editor Greg Bishop reviews actions taken...
Screenshot 2025-11-19 at 9.29.37 AM

Will County Executive Committee Delays Vote on School Choice Referendum

Will County Board Executive Committee Meeting | November 13, 2025 Article Summary: The Will County Board’s Executive Committee on Thursday, November 13, 2025, postponed a decision on whether to place an...
beecher ilinois school board graphic.3

Beecher School Board Approves Contracts for High School Doors, Janitorial Services

Beecher Board of Education Meeting | November 12, 2025 Article Summary: The Beecher Board of Education approved multiple contracts, including over $26,000 to complete a door replacement project at the...
Meeting-Briefs

Meeting Summary and Briefs: Washington Township Board for October 2025

Washington Township Board Meeting | October 2025 The Washington Township Board meeting on Monday, October 6, 2025, was marked by the sudden resignation of Trustee Teresa Peterson, who submitted her...