Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

Screenshot 2025-05-04 at 2.17.47 PM

County Landfill Meeting Briefs

Landfill Minutes Approved: The landfill committee unanimously approved minutes from its February 11, 2025 meeting. All committee members were present, including Hickey, Brooks, Bulock, Logan, Newquest, Pretzel, and Dean Schlotman....
Screenshot 2025-05-04 at 2.17.47 PM

Geological Features Central to Landfill Expansion Plans

Geological characteristics that were formed thousands of years ago make Prairie View an ideal location for landfill operations, according to the geologist leading expansion plans for the facility. During Wednesday's...
Screenshot 2025-05-04 at 2.17.47 PM

County Considers Two Options for Prairie View Landfill Expansion

Prairie View landfill could extend its lifespan by up to 35 additional years under expansion plans presented to the county's landfill committee on Wednesday. Consultant Marty Fallon outlined two potential...
Screenshot 2025-05-04 at 2.24.10 PM

Health Department Faces Funding Cuts, Reviews Options for Programs

The Will County Health Department is assessing its options after being notified of the termination of a $1 million federal grant for respiratory disease surveillance and outbreak response, officials told...
Screenshot 2025-05-04 at 2.24.10 PM

County Health News Briefs

Sunny Hill Nursing Home Reports Full Capacity: The county-owned Sunny Hill Nursing Home is operating at 100% capacity with all 156 beds filled and a waiting list, Administrator Maggie McDall...
Screenshot 2025-05-04 at 2.24.10 PM

Substance Use Initiative Reports Early 2025 Overdose Data, Outreach Efforts

Will County has recorded eight fatal overdoses and seven overdose reversals so far in 2025, according to data presented to the county health committee on Wednesday. Connie Dewal, program manager...
Screenshot 2025-05-04 at 2.24.10 PM

County Food Access Program Reports Progress on ARPA-Funded Initiatives

Four community organizations are expanding food assistance services across Will County through nearly $80,000 in federal American Rescue Plan Act (ARPA) funds administered by the county's food access collaborative. Caitlyn...
Screenshot 2025-05-04 at 2.24.10 PM

Sunny Hill Nursing Home Reaches Full Capacity, Completes Bed Upgrades

Will County's Sunny Hill Nursing Home is operating at 100% capacity with a waiting list for admissions, prompting officials to consider reinstating a policy that would prioritize county residents, Administrator...
Screenshot 2025-05-04 at 2.08.10 PM

Will County Land Use and Development Briefs: Minor Subdivision, Extension Approved, Tiny Homes Advocate Returns

Committee Approves Minor Subdivision to Correct Illegal Land Division: The Land Use and Development Committee unanimously approved a minor subdivision plat for the Crown Holm Family Trust in Lockport Township,...
Screenshot 2025-05-04 at 2.08.10 PM

Will County Considers Relaxing Size Restrictions on Accessory Dwelling Units

JOLIET — Will County officials are considering revisions to zoning regulations that would allow larger accessory dwelling units (ADUs), potentially expanding housing options in the county while addressing concerns about...
Screenshot 2025-05-04 at 2.08.10 PM

Resident Urges County to Restrict Residential Motocross Tracks After Neighborhood Dispute

JOLIET — A Will County resident appeared before the Land Use and Development Committee Thursday urging officials to modify zoning codes to prohibit motocross tracks in residential neighborhoods, citing an...
Screenshot 2025-05-04 at 2.08.10 PM

Committee Approves Truck Terminal Special Use Permit After Safety Modifications

JOLIET — The Will County Land Use and Development Committee voted Thursday to approve a special use permit for a truck terminal in New Lenox Township, after the applicant made...
Screenshot 2025-05-04 at 2.08.10 PM

County Committee Approves Two Solar Energy Projects Despite Farmland Concerns

JOLIET — The Will County Land Use and Development Committee approved two commercial solar energy projects Thursday, advancing the proposals to the full county board for final consideration despite concerns...
Screenshot 2025-05-04 at 3.03.49 PM

Will County Approves Vision Zero Initiative to Reduce Traffic Fatalities

Will County has officially adopted Vision Zero, a data-driven safety initiative aimed at eliminating traffic fatalities throughout the county. The Public Works and Transportation Committee unanimously approved the resolution, which...
Screenshot 2025-05-04 at 3.03.49 PM

County’s First Roundabout Planned for Exchange Street and Beecher Road Intersection

Will County's first roundabout is advancing to the final public meeting phase, with construction tentatively scheduled for 2027. County Engineer Jeff Ronaldson announced that the Department of Transportation will hold...