Will County Board Graphic.03

Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

Meeting-Briefs

Meeting Summary and Briefs: Washington Township Board of Trustees for May 5, 2025

The Washington Township Board of Trustees paused a decision on a major security upgrade, approved community sponsorships, and discussed the future of its senior events at its meeting on Monday,...
Screenshot 2025-05-04 at 3.03.49 PM

County Approves $4.3 Million Purchase of Wetland Banking Credits for Highway Projects

The Will County Public Works and Transportation Committee has approved an agreement to purchase wetland banking site credits for $4,324,550 from V3 Wetland Restoration LLC to support future county highway...
Meeting-Briefs

Meeting Summary and Briefs: Beecher Fire Protection District Board of Trustees for March 20, 2025

The Beecher Fire Protection District is preparing for changes in its leadership and staffing after the Board of Trustees on March 20 approved the creation of a new Lieutenant position....
Beecher Fire Protection District graphic.1

Beecher Fire District to Hire New Lieutenant, Approves Updated Appointment Process

Article Summary: The Beecher Fire Protection District Board of Trustees has authorized the creation of a new Lieutenant position and will begin accepting applications at the end of March. The...
Screenshot 2025-05-04 at 2.01.41 PM

Labor Representative Addresses County Committee on Public Transportation Reform Efforts

JOLIET — A labor representative warned Will County officials Thursday that proposed reforms to regional public transportation governance could diminish the county's voice in transit decisions during a presentation to...
Screenshot 2025-05-04 at 2.01.41 PM

Committee Advances $1.7 Million Upgrade Plan for River Valley Juvenile Detention Center

JOLIET — The Will County Executive Committee voted Thursday to advance a $1.7 million proposal to upgrade the River Valley Juvenile Detention Center rather than pursuing costlier alternatives to house...
Screenshot 2025-05-04 at 2.01.41 PM

County Executive Committee Briefs: Transportation Program Expands, Ordinances Updated

Mobility Management Program Expands to Three Townships: The Executive Committee approved an intergovernmental agreement to expand the Will County Mobility Management Program to include Channahon, Manhattan, and Plainfield townships. The...
Screenshot 2025-05-04 at 2.01.41 PM

County Executive Committee Advances Elected Officials’ Pay Increases After Extended Debate

The Will County Executive Committee voted Thursday to advance a proposal for pay increases for countywide elected officials and county board members, setting the stage for a final vote at...
Screenshot 2025-05-04 at 2.01.41 PM

County Considers Bond Refinancing That Could Save Millions

JOLIET — Will County officials on Thursday discussed a potential bond refinancing opportunity that could save the county approximately $3.6 million in debt service costs by taking advantage of favorable...
Screenshot 2025-05-04 at 2.14.20 PM

Will County Ordinance Committee Briefs: Unanimous Votes for Proclamations, Title Changes, Audits Discussed

Committee Clarifies Unanimous Vote Requirement for Honorary Proclamations: The Ordinance Committee refined language in Chapter 30 regarding honorary proclamations, specifying that they shall be allowed "only by unanimous vote" of...
Screenshot 2025-05-04 at 2.14.20 PM

County Undertakes Formatting Overhaul of Decades-Old Ordinances

JOLIET — Will County officials are modernizing the format and structure of the county's ordinances, some of which date back to 1943, as part of a comprehensive review process to...
Screenshot 2025-05-04 at 2.14.20 PM

County Reviews Rules on Virtual Meeting Attendance, Committee Participation

JOLIET — Will County officials discovered Thursday that their current practices regarding virtual meeting attendance may not fully comply with state law, as the Ordinance Committee worked through updates to...
Screenshot 2025-05-04 at 2.14.20 PM

Will County Ordinance Committee Reviews Administrative Code, Clarifies Official Powers

JOLIET — The Will County Ordinance Committee spent several hours Thursday reviewing and updating Chapter 30 of the county's Code of Ordinances, which governs county administration, with particular attention to...
Screenshot 2025-05-04 at 2.17.47 PM

Farmers, Residents Call for Action on Roadside Debris from Landfill Trucks

Local farmers and residents are urging county officials to address persistent litter problems along routes used by trucks traveling to and from Prairie View landfill. The issue emerged during public...
Screenshot 2025-05-04 at 2.17.47 PM

County Landfill Meeting Briefs

Landfill Minutes Approved: The landfill committee unanimously approved minutes from its February 11, 2025 meeting. All committee members were present, including Hickey, Brooks, Bulock, Logan, Newquest, Pretzel, and Dean Schlotman....